Time and Work Worksheet
The method (LCM units): Take the whole job as the LCM of the days. Units a day for each person = job ÷ their days. Add for working together. Days = job ÷ units a day. The answer can be a fraction like 20/9 days. Someone works a few days and stops: find what is left, then share it out.
NameDateTime takenScore ___ / 40
- 1.Rohan can finish a job in 18 days and Ananya in 13 days. What fraction of the job do they finish if they work together for 3 days? =
- 2.Priya can finish a job in 7 days and Kabir in 20 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 3.Meera can finish a job in 20 days and Rohan in 7 days. What fraction of the job do they finish if they work together for 2 days? =
- 4.Meera works twice as fast as Saanvi. Together they finish a job in 5 days. How many days would Saanvi take alone?
- 5.Vivaan can finish a job in 10 days and Ananya in 28 days. Vivaan works alone for 5 days and then stops. Ananya finishes the rest. How many days does Ananya take?
- 6.Nisha can finish a job in 12 days and Kabir in 6 days. What fraction of the job do they finish if they work together for 3 days? =
- 7.Diya can finish a job in 4 days and Isha in 8 days. Diya works alone for 1 day and then stops. Isha finishes the rest. How many days does Isha take?
- 8.Saanvi can finish a job in 19 days and Kavya in 11 days. What fraction of the job do they finish if they work together for 1 day? =
- 9.Arjun works three times as fast as Meera. Together they finish a job in 3 days. How many days would Meera take alone?
- 10.Rahul can finish a job in 8 days and Ishaan in 6 days. Rahul works alone for 4 days and then stops. Ishaan finishes the rest. How many days does Ishaan take?
- 11.Zoya can finish a job in 12 days and Dev in 6 days. What fraction of the job do they finish if they work together for 2 days? =
- 12.Ananya can finish a job in 10 days and Rohan in 30 days. Ananya works alone for 2 days and then stops. Rohan finishes the rest. How many days does Rohan take?
- 13.Rohan can finish a job in 19 days and Arjun in 13 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 14.Aditya and Tara together finish a job in 2 days. Aditya alone takes 4 days. How many days would Tara take alone?
- 15.Sneha can finish a job in 8 days and Nisha in 30 days. Sneha works alone for 4 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 16.Arjun and Isha together finish a job in 4 days. Arjun alone takes 12 days. How many days would Isha take alone?
- 17.Arjun and Farhan together finish a job in 2 days. Arjun alone takes 4 days. How many days would Farhan take alone?
- 18.Saanvi works three times as fast as Manav. Together they finish a job in 5 days. How many days would Manav take alone?
- 19.Zoya can finish a job in 9 days and Manav in 7 days. What fraction of the job do they finish if they work together for 2 days? =
- 20.Farhan can finish a job in 14 days and Rahul in 12 days. What fraction of the job do they finish if they work together for 2 days? =
- 21.Meera and Ananya together finish a job in 6 days. Meera alone takes 7 days. How many days would Ananya take alone?
- 22.Zoya can finish a job in 3 days and Aditya in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 23.Rohan works twice as fast as Manav. Together they finish a job in 12 days. How many days would Manav take alone?
- 24.Tara works twice as fast as Sneha. Together they finish a job in 6 days. How many days would Sneha take alone?
- 25.Ishaan can finish a job in 6 days and Nisha in 24 days. Ishaan works alone for 2 days and then stops. Nisha finishes the rest. How many days does Nisha take?
- 26.Karan can finish a job in 14 days and Arjun in 16 days. What fraction of the job do they finish if they work together for 1 day? =
- 27.Ananya can finish a job in 12 days and Manav in 9 days. What fraction of the job do they finish if they work together for 2 days? =
- 28.Arjun can finish a job in 6 days and Rahul in 12 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 29.Nisha can finish a job in 8 days and Arjun in 4 days. Nisha works alone for 2 days and then stops. Arjun finishes the rest. How many days does Arjun take?
- 30.Tara and Pooja together finish a job in 12 days. Tara alone takes 18 days. How many days would Pooja take alone?
- 31.Isha can finish a job in 10 days and Arjun in 5 days. How many days will they take working together? Give a fraction if the answer is not a whole number. =
- 32.Farhan works twice as fast as Sneha. Together they finish a job in 5 days. How many days would Sneha take alone?
- 33.Dev works twice as fast as Isha. Together they finish a job in 9 days. How many days would Isha take alone?
- 34.Kabir and Aarav together finish a job in 7 days. Kabir alone takes 8 days. How many days would Aarav take alone?
- 35.Saanvi works three times as fast as Meera. Together they finish a job in 12 days. How many days would Meera take alone?
- 36.Tara can finish a job in 8 days and Priya in 19 days. What fraction of the job do they finish if they work together for 1 day? =
- 37.Ishaan and Sneha together finish a job in 6 days. Ishaan alone takes 12 days. How many days would Sneha take alone?
- 38.Isha can finish a job in 4 days and Karan in 8 days. What fraction of the job do they finish if they work together for 1 day? =
- 39.Manav and Ishaan together finish a job in 3 days. Manav alone takes 4 days. How many days would Ishaan take alone?
- 40.Tara can finish a job in 17 days and Aarav in 9 days. What fraction of the job do they finish if they work together for 3 days? =
Answer key
- 31/78
- 140/27
- 27/70
- 15
- 14
- 3/4
- 6
- 30/209
- 12
- 3
- 1/2
- 24
- 247/32
- 4
- 15
- 6
- 4
- 20
- 32/63
- 13/42
- 42
- 15/8
- 36
- 18
- 16
- 15/112
- 7/18
- 4
- 3
- 36
- 10/3
- 15
- 27
- 56
- 48
- 27/152
- 12
- 3/8
- 12
- 26/51