App Dev Worksheet: Planning Features
Developer's tip (Must before nice): Must-have: the app cannot do its main job without it. Nice-to-have: it can wait. Version 1 (the MVP) = must-haves only. Days left for extras = days available − days for the must-haves.
NameDateTime takenScore ___ / 40
- 1.🗒️ In MVP, the M stands for ___. (a) maximum (b) music (c) mobile (d) minimum
- 2.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) water animations (b) see today’s total (c) set a reminder time (d) log a glass of water
-
3.🗒️ Version 1 of a homework planner must be ready in 14 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 2 days - 4.🗒️ When should nice-to-have features be built? (a) never (b) before anything (c) after the must-haves (d) on day one
- 5.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) pick a theme colour (b) see tasks by day (c) earn stickers (d) share tasks to friends
- 6.🗒️ You are planning version 1 of a homework planner. Which feature is a MUST-HAVE? (a) share tasks to friends (b) set a due date (c) pick a theme colour (d) earn stickers
- 7.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) confetti effects (b) check the answer (c) background music (d) an avatar shop
- 8.🗒️ You are planning version 1 of a water reminder. Which feature is a MUST-HAVE? (a) share your streak (b) water animations (c) set a reminder time (d) custom alert sounds
- 9.🗒️ Why keep version 1 small? (a) to use up storage (b) to confuse users (c) to learn from users soon (d) to look bigger
- 10.🗒️ You are planning version 1 of a pocket-money tracker. Which feature can WAIT for a later version? (a) add money received (b) pie-chart colours (c) add money spent (d) show the balance
-
11.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 1 days
pick your bus stop: 3 days - 12.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) rate the driver (b) pick your bus stop (c) a dark mode (d) change the bus icon
-
13.🗒️ Version 1 of a quiz app must be ready in 9 days. How many days are left for extras after the must-haves?
show a question: 1 days
check the answer: 3 days
show the score: 3 days - 14.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) add money spent (c) pie-chart colours (d) export to a file
- 15.🗒️ You are planning version 1 of a water reminder. Which feature can WAIT for a later version? (a) see today’s total (b) custom alert sounds (c) log a glass of water (d) set a reminder time
- 16.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) pie-chart colours (b) export to a file (c) add money received (d) savings stickers
-
17.🗒️ Version 1 of a quiz app must be ready in 13 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 1 days
show the score: 5 days -
18.🗒️ Version 1 of a homework planner must be ready in 8 days. How many days are left for extras after the must-haves?
add a homework task: 2 days
set a due date: 1 days
see tasks by day: 2 days -
19.🗒️ Version 1 of a bus tracker must be ready in 10 days. How many days are left for extras after the must-haves?
see where the bus is: 3 days
show arrival time: 2 days
pick your bus stop: 5 days - 20.🗒️ You are planning version 1 of a quiz app. Which feature is a MUST-HAVE? (a) background music (b) confetti effects (c) an avatar shop (d) show a question
- 21.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) earn stickers (b) set a due date (c) add a homework task (d) see tasks by day
-
22.🗒️ Version 1 of a quiz app must be ready in 18 days. How many days are left for extras after the must-haves?
show a question: 4 days
check the answer: 4 days
show the score: 4 days - 23.🗒️ What is a must-have feature? (a) a nice extra (b) a sound effect (c) a colour theme (d) one the app cannot skip
-
24.🗒️ Version 1 of a water reminder must be ready in 13 days. How many days are left for extras after the must-haves?
set a reminder time: 2 days
log a glass of water: 1 days
see today’s total: 5 days - 25.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) show a question (b) show the score (c) check the answer (d) confetti effects
-
26.🗒️ Version 1 of a bus tracker must be ready in 14 days. How many days are left for extras after the must-haves?
see where the bus is: 2 days
show arrival time: 4 days
pick your bus stop: 3 days - 27.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) add a homework task (b) set a due date (c) pick a theme colour (d) see tasks by day
- 28.🗒️ You are planning version 1 of a bus tracker. Which feature is a MUST-HAVE? (a) change the bus icon (b) rate the driver (c) see where the bus is (d) a dark mode
- 29.🗒️ You are planning version 1 of a homework planner. Which feature can WAIT for a later version? (a) set a due date (b) share tasks to friends (c) add a homework task (d) see tasks by day
- 30.🗒️ The first small, working version of an app is often called an ___. (a) FAQ (b) MVP (c) CPU (d) URL
-
31.🗒️ Version 1 of a water reminder must be ready in 15 days. How many days are left for extras after the must-haves?
set a reminder time: 3 days
log a glass of water: 4 days
see today’s total: 2 days - 32.🗒️ You are planning version 1 of a pocket-money tracker. Which feature is a MUST-HAVE? (a) savings stickers (b) show the balance (c) export to a file (d) pie-chart colours
-
33.🗒️ Version 1 of a water reminder must be ready in 12 days. How many days are left for extras after the must-haves?
set a reminder time: 1 days
log a glass of water: 4 days
see today’s total: 4 days -
34.🗒️ Version 1 of a quiz app must be ready in 11 days. How many days are left for extras after the must-haves?
show a question: 3 days
check the answer: 3 days
show the score: 4 days -
35.🗒️ Version 1 of a pocket-money tracker must be ready in 14 days. How many days are left for extras after the must-haves?
add money received: 4 days
add money spent: 2 days
show the balance: 4 days -
36.🗒️ Version 1 of a homework planner must be ready in 10 days. How many days are left for extras after the must-haves?
add a homework task: 3 days
set a due date: 4 days
see tasks by day: 2 days - 37.🗒️ You are planning version 1 of a quiz app. Which feature can WAIT for a later version? (a) background music (b) show the score (c) check the answer (d) show a question
-
38.🗒️ Version 1 of a bus tracker must be ready in 12 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 4 days
pick your bus stop: 4 days -
39.🗒️ Version 1 of a bus tracker must be ready in 5 days. How many days are left for extras after the must-haves?
see where the bus is: 1 days
show arrival time: 1 days
pick your bus stop: 2 days - 40.🗒️ You are planning version 1 of a bus tracker. Which feature can WAIT for a later version? (a) change the bus icon (b) pick your bus stop (c) see where the bus is (d) show arrival time
Answer key
- minimum
- water animations
- 5
- after the must-haves
- see tasks by day
- set a due date
- check the answer
- set a reminder time
- to learn from users soon
- pie-chart colours
- 4
- pick your bus stop
- 2
- add money spent
- custom alert sounds
- add money received
- 3
- 3
- 0
- show a question
- earn stickers
- 6
- one the app cannot skip
- 5
- confetti effects
- 5
- pick a theme colour
- see where the bus is
- share tasks to friends
- MVP
- 6
- show the balance
- 3
- 1
- 4
- 1
- background music
- 3
- 1
- change the bus icon
Free app development lessons, practice and worksheets at talentjr.in/app-development-for-students