App Dev Worksheet: Idea to Release

App development lesson 4: Idea to release: the making order · Set 188 · 40 questions
TalentJR

Developer's tip (Five steps in order): Idea → plan → build → test → release. Plan before you build: sketches and flows are quick to change; code is not. After release: read reviews → list fixes → fix → test again → release an update.

NameDateTime takenScore ___ / 40
  1. 1.📅 An app team plans for 2 days, builds for 9 days, tests for 2 days and releases on 1 more day. Planning starts on day 1. On which day does building finish?
  2. 2.🛠️ At which stage do you connect the data? (a) the release stage (b) the idea stage (c) the test stage (d) the build stage
  3. 3.Which of these happens at the build stage? (a) write the code (b) write the store text (c) sketch the screens (d) spot a problem to solve
  4. 4.📅 An app team plans for 3 days, builds for 11 days, tests for 2 days and releases on 1 more day. How many days does the whole project take?
  5. 5.🔢 After an app is released, what comes right after “list what to fix”? (a) fix and improve (b) release an update (c) read user reviews (d) test it again
  6. 6.🔢 When you make an app, which comes first: “plan the screens” or “test the app”? (a) test the app (b) plan the screens
  7. 7.🔢 When you make an app, what comes right after “test the app”? (a) build the app (b) release it (c) get an idea (d) plan the screens
  8. 8.📅 An app team plans for 2 days, builds for 12 days, tests for 3 days and releases on 1 more day. How many days does the whole project take?
  9. 9.🔢 After an app is released, which comes first: “release an update” or “read user reviews”? (a) read user reviews (b) release an update
  10. 10.🔢 When you make an app, what comes right after “get an idea”? (a) plan the screens (b) build the app (c) test the app (d) release it
  11. 11.📅 An app team plans for 3 days, builds for 12 days, tests for 1 days and releases on 1 more day. How many more days does building take than testing?
  12. 12.🔢 When you make an app, which comes LAST? (a) plan the screens (b) get an idea (c) release it (d) build the app
  13. 13.📅 An app team plans for 4 days, builds for 5 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?
  14. 14.🔍 Which is the odd one out? (a) write the code (b) try every button (c) let friends try it (d) write down the bugs
  15. 15.📅 An app team plans for 2 days, builds for 10 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?
  16. 16.📅 An app team plans for 2 days, builds for 5 days, tests for 3 days and releases on 1 more day. How many days does the whole project take?
  17. 17.True or false: you spot a problem to solve at the release stage. (a) False (b) True
  18. 18.📅 An app team plans for 4 days, builds for 8 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?
  19. 19.🛠️ At which stage do you pick the features? (a) the plan stage (b) the build stage (c) the test stage (d) the idea stage
  20. 20.True or false: you put it on an app store at the idea stage. (a) False (b) True
  21. 21.Which of these happens at the idea stage? (a) sketch the screens (b) spot a problem to solve (c) let friends try it (d) pick the features
  22. 22.🔍 Which is the odd one out? (a) talk to possible users (b) write the code (c) add the buttons (d) connect the data
  23. 23.🔢 When you make an app, which comes first: “release it” or “test the app”? (a) test the app (b) release it
  24. 24.Which of these happens at the test stage? (a) share the download link (b) pick the features (c) put it on an app store (d) try every button
  25. 25.Which of these happens at the release stage? (a) share the download link (b) spot a problem to solve (c) write down the bugs (d) connect the data
  26. 26.🔍 Which is the odd one out? (a) pick the features (b) sketch the screens (c) draw the user flow (d) try every button
  27. 27.True or false: you list what users need at the plan stage. (a) False (b) True
  28. 28.🛠️ At which stage do you share the download link? (a) the build stage (b) the idea stage (c) the release stage (d) the test stage
  29. 29.📅 An app team plans for 4 days, builds for 7 days, tests for 3 days and releases on 1 more day. Planning starts on day 1. On which day does building finish?
  30. 30.📅 An app team plans for 2 days, builds for 4 days, tests for 1 days and releases on 1 more day. How many more days does building take than testing?
  31. 31.📅 An app team plans for 2 days, builds for 10 days, tests for 2 days and releases on 1 more day. How many days does the whole project take?
  32. 32.🛠️ At which stage do you add the buttons? (a) the test stage (b) the plan stage (c) the release stage (d) the build stage
  33. 33.📅 An app team plans for 3 days, builds for 10 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?
  34. 34.🔢 When you make an app, which comes FIRST? (a) plan the screens (b) build the app (c) release it (d) get an idea
  35. 35.🛠️ At which stage do you sketch the screens? (a) the idea stage (b) the build stage (c) the release stage (d) the plan stage
  36. 36.🔢 After an app is released, which comes LAST? (a) fix and improve (b) release an update (c) read user reviews (d) test it again
  37. 37.🛠️ At which stage do you talk to possible users? (a) the release stage (b) the idea stage (c) the build stage (d) the test stage
  38. 38.🔢 After an app is released, what comes right after “test it again”? (a) list what to fix (b) fix and improve (c) release an update (d) read user reviews
  39. 39.🔢 When you make an app, which comes first: “get an idea” or “build the app”? (a) get an idea (b) build the app
  40. 40.Which of these happens at the idea stage? (a) put it on an app store (b) write the code (c) list what users need (d) share the download link

Answer key

  1. 11
  2. the build stage
  3. write the code
  4. 17
  5. fix and improve
  6. plan the screens
  7. release it
  8. 18
  9. read user reviews
  10. plan the screens
  11. 11
  12. release it
  13. 11
  14. write the code
  15. 14
  16. 11
  17. False
  18. 14
  19. the plan stage
  20. False
  21. spot a problem to solve
  22. talk to possible users
  23. test the app
  24. try every button
  25. share the download link
  26. try every button
  27. False
  28. the release stage
  29. 11
  30. 3
  31. 15
  32. the build stage
  33. 15
  34. get an idea
  35. the plan stage
  36. release an update
  37. the idea stage
  38. release an update
  39. get an idea
  40. list what users need