App Dev Worksheet: Idea to Release

App development lesson 4: Idea to release: the making order · Set 259 · 40 questions
TalentJR

Developer's tip (Five steps in order): Idea → plan → build → test → release. Plan before you build: sketches and flows are quick to change; code is not. After release: read reviews → list fixes → fix → test again → release an update.

NameDateTime takenScore ___ / 40
  1. 1.🔢 When you make an app, which comes first: “build the app” or “test the app”? (a) test the app (b) build the app
  2. 2.🛠️ At which stage do you write the code? (a) the plan stage (b) the idea stage (c) the test stage (d) the build stage
  3. 3.📅 An app team plans for 4 days, builds for 10 days, tests for 3 days and releases on 1 more day. Planning starts on day 1. On which day does building finish?
  4. 4.🔢 When you make an app, which comes FIRST? (a) release it (b) build the app (c) plan the screens (d) get an idea
  5. 5.Which of these happens at the build stage? (a) share the download link (b) list what users need (c) let friends try it (d) write the code
  6. 6.🔢 After an app is released, what comes right after “list what to fix”? (a) read user reviews (b) test it again (c) fix and improve (d) release an update
  7. 7.🔍 Which is the odd one out? (a) draw the user flow (b) pick the features (c) sketch the screens (d) put it on an app store
  8. 8.🔢 When you make an app, what comes right after “get an idea”? (a) plan the screens (b) build the app (c) release it (d) test the app
  9. 9.📅 An app team plans for 2 days, builds for 11 days, tests for 3 days and releases on 1 more day. How many days does the whole project take?
  10. 10.📅 An app team plans for 4 days, builds for 9 days, tests for 3 days and releases on 1 more day. Planning starts on day 1. On which day does building finish?
  11. 11.🔢 After an app is released, which comes first: “read user reviews” or “list what to fix”? (a) read user reviews (b) list what to fix
  12. 12.📅 An app team plans for 4 days, builds for 12 days, tests for 1 days and releases on 1 more day. Planning starts on day 1. On which day does building finish?
  13. 13.True or false: you talk to possible users at the test stage. (a) True (b) False
  14. 14.📅 An app team plans for 3 days, builds for 11 days, tests for 1 days and releases on 1 more day. How many more days does building take than testing?
  15. 15.True or false: you sketch the screens at the release stage. (a) True (b) False
  16. 16.🛠️ At which stage do you write the store text? (a) the release stage (b) the plan stage (c) the test stage (d) the build stage
  17. 17.📅 An app team plans for 2 days, builds for 5 days, tests for 3 days and releases on 1 more day. How many more days does building take than testing?
  18. 18.True or false: you put it on an app store at the release stage. (a) False (b) True
  19. 19.🛠️ At which stage do you pick the features? (a) the build stage (b) the plan stage (c) the test stage (d) the idea stage
  20. 20.🔍 Which is the odd one out? (a) list what users need (b) spot a problem to solve (c) talk to possible users (d) try every button
  21. 21.🔢 When you make an app, which comes first: “plan the screens” or “release it”? (a) release it (b) plan the screens
  22. 22.Which of these happens at the release stage? (a) list what users need (b) try every button (c) share the download link (d) sketch the screens
  23. 23.📅 An app team plans for 2 days, builds for 11 days, tests for 1 days and releases on 1 more day. How many more days does building take than testing?
  24. 24.🔍 Which is the odd one out? (a) list what users need (b) connect the data (c) spot a problem to solve (d) talk to possible users
  25. 25.🔢 When you make an app, which comes first: “test the app” or “build the app”? (a) build the app (b) test the app
  26. 26.📅 An app team plans for 3 days, builds for 4 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?
  27. 27.🔢 When you make an app, what comes right after “test the app”? (a) plan the screens (b) build the app (c) release it (d) get an idea
  28. 28.🔢 After an app is released, which comes first: “test it again” or “fix and improve”? (a) fix and improve (b) test it again
  29. 29.📅 An app team plans for 4 days, builds for 5 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?
  30. 30.🛠️ At which stage do you let friends try it? (a) the release stage (b) the test stage (c) the build stage (d) the idea stage
  31. 31.🔢 After an app is released, what comes right after “read user reviews”? (a) release an update (b) test it again (c) fix and improve (d) list what to fix
  32. 32.🔢 When you make an app, which comes first: “plan the screens” or “build the app”? (a) build the app (b) plan the screens
  33. 33.📅 An app team plans for 4 days, builds for 12 days, tests for 3 days and releases on 1 more day. How many days does the whole project take?
  34. 34.True or false: you add the buttons at the idea stage. (a) False (b) True
  35. 35.📅 An app team plans for 4 days, builds for 9 days, tests for 3 days and releases on 1 more day. How many days does the whole project take?
  36. 36.📅 An app team plans for 5 days, builds for 8 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?
  37. 37.Which of these happens at the idea stage? (a) pick the features (b) write the store text (c) spot a problem to solve (d) connect the data
  38. 38.📅 An app team plans for 2 days, builds for 6 days, tests for 3 days and releases on 1 more day. How many more days does building take than testing?
  39. 39.True or false: you talk to possible users at the idea stage. (a) False (b) True
  40. 40.📅 An app team plans for 5 days, builds for 10 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?

Answer key

  1. build the app
  2. the build stage
  3. 14
  4. get an idea
  5. write the code
  6. fix and improve
  7. put it on an app store
  8. plan the screens
  9. 17
  10. 13
  11. read user reviews
  12. 16
  13. False
  14. 10
  15. False
  16. the release stage
  17. 2
  18. True
  19. the plan stage
  20. try every button
  21. plan the screens
  22. share the download link
  23. 10
  24. connect the data
  25. build the app
  26. 9
  27. release it
  28. fix and improve
  29. 11
  30. the test stage
  31. list what to fix
  32. plan the screens
  33. 20
  34. False
  35. 17
  36. 15
  37. spot a problem to solve
  38. 3
  39. True
  40. 17