App Dev Worksheet: Idea to Release
Developer's tip (Five steps in order): Idea → plan → build → test → release. Plan before you build: sketches and flows are quick to change; code is not. After release: read reviews → list fixes → fix → test again → release an update.
NameDateTime takenScore ___ / 40
- 1.🔍 Which is the odd one out? (a) write the code (b) connect the data (c) pick the features (d) add the buttons
- 2.🔢 When you make an app, which comes FIRST? (a) release it (b) build the app (c) get an idea (d) plan the screens
- 3.📅 An app team plans for 3 days, builds for 11 days, tests for 3 days and releases on 1 more day. How many days does the whole project take?
- 4.🔢 After an app is released, which comes first: “read user reviews” or “test it again”? (a) read user reviews (b) test it again
- 5.🔍 Which is the odd one out? (a) write the code (b) add the buttons (c) try every button (d) connect the data
- 6.🔢 When you make an app, what comes right after “build the app”? (a) test the app (b) get an idea (c) release it (d) plan the screens
- 7.🔢 When you make an app, which comes first: “build the app” or “plan the screens”? (a) build the app (b) plan the screens
- 8.📅 An app team plans for 2 days, builds for 10 days, tests for 1 days and releases on 1 more day. Planning starts on day 1. On which day does building finish?
- 9.True or false: you talk to possible users at the idea stage. (a) True (b) False
- 10.🔍 Which is the odd one out? (a) add the buttons (b) talk to possible users (c) connect the data (d) write the code
- 11.Which of these happens at the test stage? (a) share the download link (b) write the code (c) draw the user flow (d) write down the bugs
- 12.Which of these happens at the build stage? (a) put it on an app store (b) let friends try it (c) pick the features (d) connect the data
- 13.📅 An app team plans for 5 days, builds for 9 days, tests for 3 days and releases on 1 more day. How many more days does building take than testing?
- 14.True or false: you pick the features at the plan stage. (a) True (b) False
- 15.🔢 After an app is released, which comes FIRST? (a) release an update (b) read user reviews (c) fix and improve (d) test it again
- 16.Which of these happens at the release stage? (a) connect the data (b) talk to possible users (c) write down the bugs (d) put it on an app store
- 17.🔢 When you make an app, what comes right after “plan the screens”? (a) release it (b) build the app (c) test the app (d) get an idea
- 18.📅 An app team plans for 5 days, builds for 7 days, tests for 2 days and releases on 1 more day. How many days does the whole project take?
- 19.🛠️ At which stage do you talk to possible users? (a) the idea stage (b) the plan stage (c) the test stage (d) the build stage
- 20.🔢 When you make an app, which comes first: “release it” or “build the app”? (a) build the app (b) release it
- 21.🔢 When you make an app, which comes first: “plan the screens” or “get an idea”? (a) plan the screens (b) get an idea
- 22.🔢 After an app is released, what comes right after “list what to fix”? (a) test it again (b) release an update (c) read user reviews (d) fix and improve
- 23.🛠️ At which stage do you write the code? (a) the release stage (b) the plan stage (c) the build stage (d) the test stage
- 24.🔢 After an app is released, which comes LAST? (a) release an update (b) list what to fix (c) read user reviews (d) fix and improve
- 25.📅 An app team plans for 2 days, builds for 6 days, tests for 2 days and releases on 1 more day. How many more days does building take than testing?
- 26.🔍 Which is the odd one out? (a) spot a problem to solve (b) write the store text (c) list what users need (d) talk to possible users
- 27.True or false: you list what users need at the plan stage. (a) True (b) False
- 28.🔢 When you make an app, which comes first: “test the app” or “plan the screens”? (a) plan the screens (b) test the app
- 29.True or false: you try every button at the plan stage. (a) False (b) True
- 30.True or false: you sketch the screens at the idea stage. (a) False (b) True
- 31.📅 An app team plans for 5 days, builds for 12 days, tests for 1 days and releases on 1 more day. How many more days does building take than testing?
- 32.📅 An app team plans for 5 days, builds for 4 days, tests for 3 days and releases on 1 more day. How many days does the whole project take?
- 33.🔍 Which is the odd one out? (a) let friends try it (b) write down the bugs (c) try every button (d) share the download link
- 34.📅 An app team plans for 4 days, builds for 8 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?
- 35.📅 An app team plans for 3 days, builds for 6 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?
- 36.🛠️ At which stage do you sketch the screens? (a) the test stage (b) the release stage (c) the plan stage (d) the build stage
- 37.🔢 After an app is released, which comes first: “list what to fix” or “fix and improve”? (a) fix and improve (b) list what to fix
- 38.🔢 When you make an app, which comes LAST? (a) plan the screens (b) release it (c) test the app (d) get an idea
- 39.🔢 After an app is released, which comes first: “release an update” or “fix and improve”? (a) release an update (b) fix and improve
- 40.True or false: you share the download link at the release stage. (a) False (b) True
Answer key
- pick the features
- get an idea
- 18
- read user reviews
- try every button
- test the app
- plan the screens
- 12
- True
- talk to possible users
- write down the bugs
- connect the data
- 6
- True
- read user reviews
- put it on an app store
- build the app
- 15
- the idea stage
- build the app
- get an idea
- fix and improve
- the build stage
- release an update
- 4
- write the store text
- False
- plan the screens
- False
- False
- 11
- 13
- share the download link
- 14
- 11
- the plan stage
- list what to fix
- release it
- fix and improve
- True