App Dev Worksheet: Idea to Release

App development lesson 4: Idea to release: the making order · Set 747 · 40 questions
TalentJR

Developer's tip (Five steps in order): Idea → plan → build → test → release. Plan before you build: sketches and flows are quick to change; code is not. After release: read reviews → list fixes → fix → test again → release an update.

NameDateTime takenScore ___ / 40
  1. 1.🔢 After an app is released, which comes first: “read user reviews” or “list what to fix”? (a) read user reviews (b) list what to fix
  2. 2.Which of these happens at the release stage? (a) list what users need (b) sketch the screens (c) write the store text (d) spot a problem to solve
  3. 3.🛠️ At which stage do you write the code? (a) the idea stage (b) the plan stage (c) the build stage (d) the release stage
  4. 4.True or false: you write the code at the idea stage. (a) False (b) True
  5. 5.🔍 Which is the odd one out? (a) connect the data (b) write the code (c) add the buttons (d) list what users need
  6. 6.📅 An app team plans for 3 days, builds for 5 days, tests for 1 days and releases on 1 more day. Planning starts on day 1. On which day does building finish?
  7. 7.🔍 Which is the odd one out? (a) talk to possible users (b) spot a problem to solve (c) share the download link (d) list what users need
  8. 8.🔢 After an app is released, what comes right after “fix and improve”? (a) list what to fix (b) test it again (c) release an update (d) read user reviews
  9. 9.Which of these happens at the idea stage? (a) share the download link (b) write the code (c) let friends try it (d) list what users need
  10. 10.Which of these happens at the idea stage? (a) talk to possible users (b) put it on an app store (c) draw the user flow (d) write the store text
  11. 11.🔢 After an app is released, what comes right after “list what to fix”? (a) fix and improve (b) release an update (c) test it again (d) read user reviews
  12. 12.📅 An app team plans for 2 days, builds for 8 days, tests for 3 days and releases on 1 more day. Planning starts on day 1. On which day does building finish?
  13. 13.🔍 Which is the odd one out? (a) list what users need (b) spot a problem to solve (c) pick the features (d) talk to possible users
  14. 14.Which of these happens at the plan stage? (a) talk to possible users (b) sketch the screens (c) add the buttons (d) share the download link
  15. 15.🔢 When you make an app, which comes first: “get an idea” or “test the app”? (a) get an idea (b) test the app
  16. 16.🔢 When you make an app, which comes first: “plan the screens” or “test the app”? (a) plan the screens (b) test the app
  17. 17.True or false: you try every button at the test stage. (a) False (b) True
  18. 18.True or false: you share the download link at the release stage. (a) True (b) False
  19. 19.📅 An app team plans for 4 days, builds for 8 days, tests for 3 days and releases on 1 more day. How many days does the whole project take?
  20. 20.📅 An app team plans for 2 days, builds for 4 days, tests for 2 days and releases on 1 more day. How many days does the whole project take?
  21. 21.🔢 When you make an app, which comes LAST? (a) plan the screens (b) test the app (c) build the app (d) release it
  22. 22.📅 An app team plans for 4 days, builds for 8 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?
  23. 23.📅 An app team plans for 5 days, builds for 4 days, tests for 2 days and releases on 1 more day. Planning starts on day 1. On which day does building finish?
  24. 24.🛠️ At which stage do you spot a problem to solve? (a) the test stage (b) the build stage (c) the idea stage (d) the plan stage
  25. 25.📅 An app team plans for 5 days, builds for 9 days, tests for 2 days and releases on 1 more day. How many more days does building take than testing?
  26. 26.🔢 When you make an app, which comes first: “plan the screens” or “build the app”? (a) plan the screens (b) build the app
  27. 27.🔢 When you make an app, which comes FIRST? (a) release it (b) get an idea (c) plan the screens (d) build the app
  28. 28.📅 An app team plans for 5 days, builds for 12 days, tests for 2 days and releases on 1 more day. How many more days does building take than testing?
  29. 29.🔍 Which is the odd one out? (a) pick the features (b) draw the user flow (c) spot a problem to solve (d) sketch the screens
  30. 30.🔍 Which is the odd one out? (a) list what users need (b) spot a problem to solve (c) try every button (d) talk to possible users
  31. 31.🔢 When you make an app, what comes right after “get an idea”? (a) plan the screens (b) test the app (c) release it (d) build the app
  32. 32.Which of these happens at the release stage? (a) sketch the screens (b) put it on an app store (c) list what users need (d) write down the bugs
  33. 33.🔢 When you make an app, what comes right after “test the app”? (a) release it (b) get an idea (c) plan the screens (d) build the app
  34. 34.🔢 After an app is released, which comes first: “release an update” or “read user reviews”? (a) release an update (b) read user reviews
  35. 35.🔢 After an app is released, which comes first: “fix and improve” or “test it again”? (a) fix and improve (b) test it again
  36. 36.🛠️ At which stage do you sketch the screens? (a) the build stage (b) the release stage (c) the idea stage (d) the plan stage
  37. 37.True or false: you put it on an app store at the release stage. (a) True (b) False
  38. 38.🔢 After an app is released, which comes FIRST? (a) fix and improve (b) read user reviews (c) test it again (d) release an update
  39. 39.📅 An app team plans for 2 days, builds for 7 days, tests for 3 days and releases on 1 more day. Planning starts on day 1. On which day does building finish?
  40. 40.📅 An app team plans for 2 days, builds for 9 days, tests for 1 days and releases on 1 more day. How many days does the whole project take?

Answer key

  1. read user reviews
  2. write the store text
  3. the build stage
  4. False
  5. list what users need
  6. 8
  7. share the download link
  8. test it again
  9. list what users need
  10. talk to possible users
  11. fix and improve
  12. 10
  13. pick the features
  14. sketch the screens
  15. get an idea
  16. plan the screens
  17. True
  18. True
  19. 16
  20. 9
  21. release it
  22. 14
  23. 9
  24. the idea stage
  25. 7
  26. plan the screens
  27. get an idea
  28. 10
  29. spot a problem to solve
  30. try every button
  31. plan the screens
  32. put it on an app store
  33. release it
  34. read user reviews
  35. fix and improve
  36. the plan stage
  37. True
  38. read user reviews
  39. 9
  40. 13