Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 1 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) there is no need (c) for surprises (d) to start late
  2. 2.📅 Your history chart is due in 13 days. Research takes 2 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
  3. 3.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) neither (c) study for the test (d) make the poster
  4. 4.🔍 Which is the odd one out? (a) checking progress weekly (b) hard part first (c) setting mini-deadlines (d) guessing how long
  5. 5.True or false: “starting early” is poor project planning. (a) False (b) True
  6. 6.Which of these is good project planning? (a) guessing how long (b) setting mini-deadlines (c) no spare time (d) starting on the last day
  7. 7.⏰ You start at 5:45 PM. Homework takes 35 minutes, then project work takes 15 minutes. When will you finish? (a) 6:00 PM (b) 6:50 PM (c) 6:20 PM (d) 6:35 PM
  8. 8.Which of these is poor project planning? (a) hard part first (b) breaking work into steps (c) ignoring the timetable (d) listing tasks first
  9. 9.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
  10. 10.True or false: “one huge deadline” is good project planning. (a) False (b) True
  11. 11.Which of these is good project planning? (a) no task list (b) doing only easy bits (c) ignoring the timetable (d) checking progress weekly
  12. 12.Which of these is poor project planning? (a) hard part first (b) setting mini-deadlines (c) using a simple timetable (d) guessing how long
  13. 13.Which of these is poor project planning? (a) keeping spare days (b) checking progress weekly (c) forgetting the due date (d) listing tasks first
  14. 14.✂️ Your team must make 24 paper flowers in 3 days, the same number each day. How many paper flowers a day?
  15. 15.✂️ Your team must make 12 paper bags in 3 days, the same number each day. How many paper bags a day?
  16. 16.True or false: “guessing how long” is good project planning. (a) True (b) False
  17. 17.Which of these is poor project planning? (a) listing tasks first (b) no task list (c) keeping spare days (d) checking progress weekly
  18. 18.📅 Your art display is due in 12 days. Research takes 4 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
  19. 19.Which of these is poor project planning? (a) hard part first (b) breaking work into steps (c) starting on the last day (d) keeping spare days
  20. 20.Which of these is good project planning? (a) using a simple timetable (b) ignoring the timetable (c) doing only easy bits (d) no task list
  21. 21.True or false: “doing only easy bits” is good project planning. (a) True (b) False
  22. 22.✂️ Your team must make 54 bookmarks in 6 days, the same number each day. How many bookmarks a day?
  23. 23.True or false: “breaking work into steps” is poor project planning. (a) True (b) False
  24. 24.Which of these is poor project planning? (a) using a simple timetable (b) doing only easy bits (c) listing tasks first (d) keeping spare days
  25. 25.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) the night before (c) this week (d) after it is due
  26. 26.🔍 Which is the odd one out? (a) one huge deadline (b) using a simple timetable (c) keeping spare days (d) setting mini-deadlines
  27. 27.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
  28. 28.True or false: “no task list” is good project planning. (a) True (b) False
  29. 29.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
  30. 30.🔍 Which is the odd one out? (a) forgetting the due date (b) starting on the last day (c) ignoring the timetable (d) setting mini-deadlines
  31. 31.🧩 A big project feels scary. What should you do first? (a) give up (b) do it all at once (c) wait for help (d) break it into steps
  32. 32.🔍 Which is the odd one out? (a) setting mini-deadlines (b) no spare time (c) listing tasks first (d) checking progress weekly
  33. 33.True or false: “breaking work into steps” is good project planning. (a) True (b) False
  34. 34.Which of these is good project planning? (a) no spare time (b) hard part first (c) no task list (d) guessing how long
  35. 35.Which of these is good project planning? (a) keeping spare days (b) no task list (c) no spare time (d) ignoring the timetable
  36. 36.📅 Good or poor project planning: guessing how long? (a) poor planning (b) good planning
  37. 37.Which of these is poor project planning? (a) listing tasks first (b) breaking work into steps (c) one huge deadline (d) starting early
  38. 38.True or false: “keeping spare days” is good project planning. (a) False (b) True
  39. 39.✅ What is a mini-deadline? (a) a holiday (b) the final due date (c) a date for one step (d) a late fine
  40. 40.🔍 Which is the odd one out? (a) no task list (b) breaking work into steps (c) setting mini-deadlines (d) hard part first

Answer key

  1. for surprises
  2. 4
  3. study for the test
  4. guessing how long
  5. False
  6. setting mini-deadlines
  7. 6:35 PM
  8. ignoring the timetable
  9. poor planning
  10. False
  11. checking progress weekly
  12. guessing how long
  13. forgetting the due date
  14. 8
  15. 4
  16. False
  17. no task list
  18. 1
  19. starting on the last day
  20. using a simple timetable
  21. False
  22. 9
  23. False
  24. doing only easy bits
  25. this week
  26. one huge deadline
  27. good planning
  28. False
  29. good planning
  30. setting mini-deadlines
  31. break it into steps
  32. no spare time
  33. True
  34. hard part first
  35. keeping spare days
  36. poor planning
  37. one huge deadline
  38. True
  39. a date for one step
  40. no task list