Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.🔍 Which is the odd one out? (a) forgetting the due date (b) breaking work into steps (c) setting mini-deadlines (d) hard part first
- 2.🔍 Which is the odd one out? (a) starting early (b) no task list (c) using a simple timetable (d) checking progress weekly
- 3.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
- 4.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) give up (c) wait for help (d) break it into steps
- 5.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) for surprises (c) to rest only (d) to start late
- 6.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 7.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
- 8.True or false: “guessing how long” is good project planning. (a) True (b) False
- 9.Which of these is good project planning? (a) setting mini-deadlines (b) one huge deadline (c) starting on the last day (d) no task list
- 10.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 11.⏰ You start at 5:00 PM. Homework takes 40 minutes, then project work takes 15 minutes. When will you finish? (a) 5:55 PM (b) 5:40 PM (c) 5:15 PM (d) 6:10 PM
- 12.Which of these is good project planning? (a) no task list (b) using a simple timetable (c) one huge deadline (d) guessing how long
- 13.🔍 Which is the odd one out? (a) one huge deadline (b) checking progress weekly (c) breaking work into steps (d) starting early
- 14.Which of these is good project planning? (a) no task list (b) one huge deadline (c) keeping spare days (d) doing only easy bits
- 15.✂️ Your team must make 15 bookmarks in 5 days, the same number each day. How many bookmarks a day?
- 16.⏰ You start at 3:15 PM. Homework takes 20 minutes, then project work takes 40 minutes. When will you finish? (a) 3:35 PM (b) 4:15 PM (c) 4:30 PM (d) 3:55 PM
- 17.Which of these is poor project planning? (a) starting early (b) listing tasks first (c) guessing how long (d) hard part first
- 18.🔍 Which is the odd one out? (a) checking progress weekly (b) using a simple timetable (c) listing tasks first (d) starting on the last day
- 19.📅 Your maths exhibit is due in 11 days. Research takes 4 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 20.True or false: “breaking work into steps” is good project planning. (a) True (b) False
- 21.Which of these is poor project planning? (a) keeping spare days (b) hard part first (c) one huge deadline (d) starting early
- 22.Which of these is poor project planning? (a) setting mini-deadlines (b) using a simple timetable (c) keeping spare days (d) forgetting the due date
- 23.Which of these is good project planning? (a) listing tasks first (b) ignoring the timetable (c) no task list (d) guessing how long
- 24.True or false: “listing tasks first” is good project planning. (a) True (b) False
- 25.🔍 Which is the odd one out? (a) forgetting the due date (b) ignoring the timetable (c) setting mini-deadlines (d) no task list
- 26.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
- 27.Which of these is good project planning? (a) no spare time (b) one huge deadline (c) starting on the last day (d) breaking work into steps
- 28.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) after it is due (c) this week (d) the night before
- 29.📅 Your eco-club poster is due in 14 days. Research takes 3 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
- 30.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 31.Which of these is poor project planning? (a) keeping spare days (b) hard part first (c) checking progress weekly (d) starting on the last day
- 32.📅 Good or poor project planning: one huge deadline? (a) poor planning (b) good planning
- 33.📅 Your school play is due in 11 days. Research takes 4 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
- 34.✅ What is a mini-deadline? (a) the final due date (b) a date for one step (c) a late fine (d) a holiday
- 35.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 36.✂️ Your team must make 27 paper flowers in 3 days, the same number each day. How many paper flowers a day?
- 37.True or false: “doing only easy bits” is good project planning. (a) False (b) True
- 38.Which of these is poor project planning? (a) listing tasks first (b) setting mini-deadlines (c) breaking work into steps (d) ignoring the timetable
- 39.🔍 Which is the odd one out? (a) guessing how long (b) listing tasks first (c) keeping spare days (d) breaking work into steps
- 40.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
Answer key
- forgetting the due date
- no task list
- good planning
- break it into steps
- for surprises
- poor planning
- good planning
- False
- setting mini-deadlines
- poor planning
- 5:55 PM
- using a simple timetable
- one huge deadline
- keeping spare days
- 3
- 4:15 PM
- guessing how long
- starting on the last day
- 3
- True
- one huge deadline
- forgetting the due date
- listing tasks first
- True
- setting mini-deadlines
- poor planning
- breaking work into steps
- this week
- 3
- good planning
- starting on the last day
- poor planning
- 1
- a date for one step
- poor planning
- 9
- False
- ignoring the timetable
- guessing how long
- good planning