Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 118 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.🔍 Which is the odd one out? (a) keeping spare days (b) forgetting the due date (c) listing tasks first (d) starting early
  2. 2.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
  3. 3.✅ What is a mini-deadline? (a) a holiday (b) the final due date (c) a date for one step (d) a late fine
  4. 4.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
  5. 5.🔍 Which is the odd one out? (a) one huge deadline (b) no task list (c) keeping spare days (d) doing only easy bits
  6. 6.Which of these is good project planning? (a) keeping spare days (b) doing only easy bits (c) starting on the last day (d) one huge deadline
  7. 7.🔍 Which is the odd one out? (a) no task list (b) ignoring the timetable (c) hard part first (d) starting on the last day
  8. 8.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
  9. 9.📅 Your history chart is due in 13 days. Research takes 2 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
  10. 10.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
  11. 11.🔍 Which is the odd one out? (a) guessing how long (b) ignoring the timetable (c) one huge deadline (d) starting early
  12. 12.🔍 Which is the odd one out? (a) setting mini-deadlines (b) no task list (c) breaking work into steps (d) starting early
  13. 13.🔍 Which is the odd one out? (a) setting mini-deadlines (b) no spare time (c) checking progress weekly (d) listing tasks first
  14. 14.🔍 Which is the odd one out? (a) setting mini-deadlines (b) starting on the last day (c) guessing how long (d) ignoring the timetable
  15. 15.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) this week (c) in the third week (d) the night before
  16. 16.Which of these is poor project planning? (a) starting on the last day (b) breaking work into steps (c) checking progress weekly (d) listing tasks first
  17. 17.Which of these is poor project planning? (a) using a simple timetable (b) hard part first (c) ignoring the timetable (d) keeping spare days
  18. 18.🔍 Which is the odd one out? (a) listing tasks first (b) breaking work into steps (c) checking progress weekly (d) ignoring the timetable
  19. 19.🧩 A big project feels scary. What should you do first? (a) give up (b) wait for help (c) break it into steps (d) do it all at once
  20. 20.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
  21. 21.✂️ Your team must make 32 posters in 4 days, the same number each day. How many posters a day?
  22. 22.Which of these is good project planning? (a) listing tasks first (b) no spare time (c) ignoring the timetable (d) doing only easy bits
  23. 23.True or false: “checking progress weekly” is poor project planning. (a) False (b) True
  24. 24.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) study for the test (c) make the poster (d) play first
  25. 25.📅 Your science model is due in 9 days. Research takes 3 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
  26. 26.True or false: “setting mini-deadlines” is good project planning. (a) True (b) False
  27. 27.Which of these is good project planning? (a) doing only easy bits (b) one huge deadline (c) setting mini-deadlines (d) no spare time
  28. 28.True or false: “doing only easy bits” is poor project planning. (a) False (b) True
  29. 29.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
  30. 30.Which of these is good project planning? (a) no spare time (b) starting on the last day (c) guessing how long (d) breaking work into steps
  31. 31.✂️ Your team must make 24 posters in 3 days, the same number each day. How many posters a day?
  32. 32.🔍 Which is the odd one out? (a) guessing how long (b) ignoring the timetable (c) starting on the last day (d) listing tasks first
  33. 33.Which of these is poor project planning? (a) no task list (b) hard part first (c) starting early (d) keeping spare days
  34. 34.🔍 Which is the odd one out? (a) setting mini-deadlines (b) doing only easy bits (c) listing tasks first (d) checking progress weekly
  35. 35.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
  36. 36.True or false: “using a simple timetable” is poor project planning. (a) False (b) True
  37. 37.📅 Your art display is due in 10 days. Research takes 3 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  38. 38.📅 Your art display is due in 14 days. Research takes 3 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  39. 39.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to start late (c) to rest only (d) for surprises
  40. 40.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning

Answer key

  1. forgetting the due date
  2. good planning
  3. a date for one step
  4. poor planning
  5. keeping spare days
  6. keeping spare days
  7. hard part first
  8. poor planning
  9. 5
  10. good planning
  11. starting early
  12. no task list
  13. no spare time
  14. setting mini-deadlines
  15. this week
  16. starting on the last day
  17. ignoring the timetable
  18. ignoring the timetable
  19. break it into steps
  20. good planning
  21. 8
  22. listing tasks first
  23. False
  24. study for the test
  25. 1
  26. True
  27. setting mini-deadlines
  28. True
  29. poor planning
  30. breaking work into steps
  31. 8
  32. listing tasks first
  33. no task list
  34. doing only easy bits
  35. poor planning
  36. False
  37. 4
  38. 3
  39. for surprises
  40. poor planning