Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) play first (c) make the poster (d) neither
- 2.🔍 Which is the odd one out? (a) keeping spare days (b) no task list (c) guessing how long (d) forgetting the due date
- 3.True or false: “hard part first” is poor project planning. (a) True (b) False
- 4.True or false: “no spare time” is poor project planning. (a) False (b) True
- 5.Which of these is good project planning? (a) no spare time (b) checking progress weekly (c) ignoring the timetable (d) no task list
- 6.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 7.True or false: “guessing how long” is good project planning. (a) False (b) True
- 8.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
- 9.⏰ You start at 4:00 PM. Homework takes 35 minutes, then project work takes 25 minutes. When will you finish? (a) 5:15 PM (b) 5:00 PM (c) 4:25 PM (d) 4:35 PM
- 10.Which of these is good project planning? (a) no spare time (b) no task list (c) guessing how long (d) hard part first
- 11.🔍 Which is the odd one out? (a) forgetting the due date (b) one huge deadline (c) no task list (d) setting mini-deadlines
- 12.🔍 Which is the odd one out? (a) hard part first (b) no spare time (c) no task list (d) guessing how long
- 13.📅 Your eco-club poster is due in 10 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 14.📅 Your class magazine is due in 14 days. Research takes 4 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
- 15.True or false: “forgetting the due date” is good project planning. (a) True (b) False
- 16.True or false: “keeping spare days” is poor project planning. (a) True (b) False
- 17.✂️ Your team must make 9 paper bags in 3 days, the same number each day. How many paper bags a day?
- 18.🔍 Which is the odd one out? (a) doing only easy bits (b) listing tasks first (c) forgetting the due date (d) no spare time
- 19.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
- 20.🔍 Which is the odd one out? (a) checking progress weekly (b) forgetting the due date (c) one huge deadline (d) no task list
- 21.Which of these is good project planning? (a) keeping spare days (b) doing only easy bits (c) guessing how long (d) ignoring the timetable
- 22.Which of these is good project planning? (a) no spare time (b) no task list (c) listing tasks first (d) doing only easy bits
- 23.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
- 24.📅 Good or poor project planning: using a simple timetable? (a) poor planning (b) good planning
- 25.🔍 Which is the odd one out? (a) using a simple timetable (b) keeping spare days (c) setting mini-deadlines (d) ignoring the timetable
- 26.🔍 Which is the odd one out? (a) starting on the last day (b) listing tasks first (c) keeping spare days (d) setting mini-deadlines
- 27.True or false: “doing only easy bits” is poor project planning. (a) False (b) True
- 28.True or false: “using a simple timetable” is good project planning. (a) False (b) True
- 29.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
- 30.True or false: “guessing how long” is poor project planning. (a) True (b) False
- 31.True or false: “one huge deadline” is poor project planning. (a) True (b) False
- 32.True or false: “listing tasks first” is poor project planning. (a) True (b) False
- 33.True or false: “starting early” is good project planning. (a) True (b) False
- 34.Which of these is good project planning? (a) forgetting the due date (b) using a simple timetable (c) no task list (d) starting on the last day
- 35.⏳ Why keep a spare day or two before the deadline? (a) to start late (b) to rest only (c) for surprises (d) there is no need
- 36.📅 Your eco-club poster is due in 6 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 37.🔍 Which is the odd one out? (a) breaking work into steps (b) checking progress weekly (c) forgetting the due date (d) starting early
- 38.🧩 A big project feels scary. What should you do first? (a) wait for help (b) give up (c) break it into steps (d) do it all at once
- 39.True or false: “setting mini-deadlines” is good project planning. (a) False (b) True
- 40.📅 Your school play is due in 7 days. Research takes 1 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
Answer key
- study for the test
- keeping spare days
- False
- True
- checking progress weekly
- poor planning
- False
- good planning
- 5:00 PM
- hard part first
- setting mini-deadlines
- hard part first
- 5
- 4
- False
- False
- 3
- listing tasks first
- good planning
- checking progress weekly
- keeping spare days
- listing tasks first
- good planning
- good planning
- ignoring the timetable
- starting on the last day
- True
- True
- poor planning
- True
- True
- False
- True
- using a simple timetable
- for surprises
- 1
- forgetting the due date
- break it into steps
- True
- 1