Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Your science model is due in 13 days. Research takes 3 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
- 2.✂️ Your team must make 10 paper bags in 5 days, the same number each day. How many paper bags a day?
- 3.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
- 4.✅ What is a mini-deadline? (a) the final due date (b) a holiday (c) a late fine (d) a date for one step
- 5.Which of these is good project planning? (a) keeping spare days (b) starting on the last day (c) forgetting the due date (d) guessing how long
- 6.⏳ Why keep a spare day or two before the deadline? (a) for surprises (b) to start late (c) to rest only (d) there is no need
- 7.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 8.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
- 9.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) in the third week (c) the night before (d) after it is due
- 10.Which of these is poor project planning? (a) starting early (b) listing tasks first (c) no task list (d) setting mini-deadlines
- 11.Which of these is good project planning? (a) ignoring the timetable (b) one huge deadline (c) starting early (d) guessing how long
- 12.Which of these is good project planning? (a) breaking work into steps (b) doing only easy bits (c) starting on the last day (d) no spare time
- 13.Which of these is good project planning? (a) no task list (b) using a simple timetable (c) one huge deadline (d) starting on the last day
- 14.Which of these is poor project planning? (a) no spare time (b) listing tasks first (c) setting mini-deadlines (d) breaking work into steps
- 15.📅 Your eco-club poster is due in 9 days. Research takes 1 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
- 16.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
- 17.🔍 Which is the odd one out? (a) listing tasks first (b) checking progress weekly (c) breaking work into steps (d) starting on the last day
- 18.True or false: “starting early” is good project planning. (a) True (b) False
- 19.True or false: “no task list” is good project planning. (a) False (b) True
- 20.🔍 Which is the odd one out? (a) doing only easy bits (b) ignoring the timetable (c) checking progress weekly (d) no spare time
- 21.True or false: “keeping spare days” is poor project planning. (a) True (b) False
- 22.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
- 23.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 24.📅 Your history chart is due in 14 days. Research takes 3 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 25.Which of these is good project planning? (a) no task list (b) doing only easy bits (c) ignoring the timetable (d) checking progress weekly
- 26.True or false: “forgetting the due date” is poor project planning. (a) False (b) True
- 27.Which of these is good project planning? (a) forgetting the due date (b) doing only easy bits (c) setting mini-deadlines (d) one huge deadline
- 28.🧩 A big project feels scary. What should you do first? (a) wait for help (b) give up (c) do it all at once (d) break it into steps
- 29.🔍 Which is the odd one out? (a) listing tasks first (b) doing only easy bits (c) keeping spare days (d) setting mini-deadlines
- 30.Which of these is poor project planning? (a) ignoring the timetable (b) starting early (c) keeping spare days (d) using a simple timetable
- 31.True or false: “starting on the last day” is good project planning. (a) True (b) False
- 32.🔍 Which is the odd one out? (a) one huge deadline (b) doing only easy bits (c) setting mini-deadlines (d) no spare time
- 33.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
- 34.📅 Your science model is due in 8 days. Research takes 1 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 35.📅 Your class magazine is due in 13 days. Research takes 3 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
- 36.🔍 Which is the odd one out? (a) guessing how long (b) ignoring the timetable (c) using a simple timetable (d) one huge deadline
- 37.✂️ Your team must make 16 bookmarks in 4 days, the same number each day. How many bookmarks a day?
- 38.True or false: “doing only easy bits” is good project planning. (a) True (b) False
- 39.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 40.📅 Your history chart is due in 7 days. Research takes 3 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
Answer key
- 5
- 2
- poor planning
- a date for one step
- keeping spare days
- for surprises
- poor planning
- good planning
- this week
- no task list
- starting early
- breaking work into steps
- using a simple timetable
- no spare time
- 3
- poor planning
- starting on the last day
- True
- False
- checking progress weekly
- False
- good planning
- poor planning
- 5
- checking progress weekly
- True
- setting mini-deadlines
- break it into steps
- doing only easy bits
- ignoring the timetable
- False
- setting mini-deadlines
- good planning
- 1
- 3
- using a simple timetable
- 4
- False
- good planning
- 1