Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 2.✅ What is a mini-deadline? (a) a late fine (b) the final due date (c) a holiday (d) a date for one step
- 3.📅 Your eco-club poster is due in 11 days. Research takes 1 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
- 4.True or false: “guessing how long” is good project planning. (a) True (b) False
- 5.Which of these is poor project planning? (a) no spare time (b) using a simple timetable (c) hard part first (d) starting early
- 6.True or false: “breaking work into steps” is poor project planning. (a) True (b) False
- 7.Which of these is poor project planning? (a) using a simple timetable (b) breaking work into steps (c) no task list (d) listing tasks first
- 8.Which of these is good project planning? (a) setting mini-deadlines (b) forgetting the due date (c) one huge deadline (d) doing only easy bits
- 9.Which of these is poor project planning? (a) ignoring the timetable (b) hard part first (c) starting early (d) using a simple timetable
- 10.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
- 11.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
- 12.⏰ You start at 5:15 PM. Homework takes 40 minutes, then project work takes 20 minutes. When will you finish? (a) 5:55 PM (b) 5:35 PM (c) 6:30 PM (d) 6:15 PM
- 13.📅 Your science model is due in 6 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 14.📅 Your class magazine is due in 13 days. Research takes 4 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
- 15.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 16.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
- 17.🔍 Which is the odd one out? (a) breaking work into steps (b) starting on the last day (c) guessing how long (d) one huge deadline
- 18.🔍 Which is the odd one out? (a) keeping spare days (b) no spare time (c) no task list (d) starting on the last day
- 19.True or false: “keeping spare days” is poor project planning. (a) True (b) False
- 20.🔍 Which is the odd one out? (a) guessing how long (b) hard part first (c) breaking work into steps (d) checking progress weekly
- 21.🔍 Which is the odd one out? (a) listing tasks first (b) hard part first (c) ignoring the timetable (d) checking progress weekly
- 22.True or false: “keeping spare days” is good project planning. (a) True (b) False
- 23.✂️ Your team must make 18 paper flowers in 3 days, the same number each day. How many paper flowers a day?
- 24.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
- 25.🔍 Which is the odd one out? (a) doing only easy bits (b) using a simple timetable (c) starting on the last day (d) no task list
- 26.True or false: “forgetting the due date” is poor project planning. (a) True (b) False
- 27.📅 Your history chart is due in 12 days. Research takes 3 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
- 28.Which of these is poor project planning? (a) starting early (b) doing only easy bits (c) checking progress weekly (d) breaking work into steps
- 29.Which of these is good project planning? (a) starting on the last day (b) listing tasks first (c) one huge deadline (d) forgetting the due date
- 30.True or false: “starting early” is good project planning. (a) False (b) True
- 31.🔍 Which is the odd one out? (a) forgetting the due date (b) starting on the last day (c) doing only easy bits (d) listing tasks first
- 32.✂️ Your team must make 24 paper bags in 3 days, the same number each day. How many paper bags a day?
- 33.🔍 Which is the odd one out? (a) hard part first (b) starting on the last day (c) listing tasks first (d) using a simple timetable
- 34.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) to start late (c) there is no need (d) for surprises
- 35.Which of these is poor project planning? (a) one huge deadline (b) keeping spare days (c) listing tasks first (d) breaking work into steps
- 36.True or false: “forgetting the due date” is good project planning. (a) False (b) True
- 37.⏰ You start at 3:00 PM. Homework takes 25 minutes, then project work takes 35 minutes. When will you finish? (a) 3:25 PM (b) 3:35 PM (c) 4:15 PM (d) 4:00 PM
- 38.✂️ Your team must make 42 paper flowers in 6 days, the same number each day. How many paper flowers a day?
- 39.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) after it is due (c) in the third week (d) the night before
- 40.📅 Your class magazine is due in 11 days. Research takes 1 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
Answer key
- good planning
- a date for one step
- 5
- False
- no spare time
- False
- no task list
- setting mini-deadlines
- ignoring the timetable
- poor planning
- poor planning
- 6:15 PM
- 1
- 4
- good planning
- good planning
- breaking work into steps
- keeping spare days
- False
- guessing how long
- ignoring the timetable
- True
- 6
- poor planning
- using a simple timetable
- True
- 3
- doing only easy bits
- listing tasks first
- True
- listing tasks first
- 8
- starting on the last day
- for surprises
- one huge deadline
- False
- 4:00 PM
- 7
- this week
- 3