Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Your eco-club poster is due in 11 days. Research takes 3 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 2.📅 Your art display is due in 13 days. Research takes 4 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
- 3.Which of these is poor project planning? (a) breaking work into steps (b) starting on the last day (c) keeping spare days (d) listing tasks first
- 4.Which of these is poor project planning? (a) listing tasks first (b) keeping spare days (c) ignoring the timetable (d) starting early
- 5.✂️ Your team must make 10 posters in 5 days, the same number each day. How many posters a day?
- 6.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) make the poster (b) neither (c) play first (d) study for the test
- 7.⏰ You start at 3:30 PM. Homework takes 35 minutes, then project work takes 15 minutes. When will you finish? (a) 3:45 PM (b) 4:35 PM (c) 4:20 PM (d) 4:05 PM
- 8.Which of these is poor project planning? (a) hard part first (b) keeping spare days (c) one huge deadline (d) using a simple timetable
- 9.✂️ Your team must make 36 bookmarks in 4 days, the same number each day. How many bookmarks a day?
- 10.✂️ Your team must make 18 paper bags in 2 days, the same number each day. How many paper bags a day?
- 11.✂️ Your team must make 30 paper bags in 6 days, the same number each day. How many paper bags a day?
- 12.✂️ Your team must make 28 paper bags in 4 days, the same number each day. How many paper bags a day?
- 13.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
- 14.True or false: “setting mini-deadlines” is poor project planning. (a) True (b) False
- 15.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
- 16.Which of these is poor project planning? (a) checking progress weekly (b) keeping spare days (c) doing only easy bits (d) using a simple timetable
- 17.🗓️ Your project is due in three weeks. When should you start? (a) the night before (b) after it is due (c) in the third week (d) this week
- 18.🔍 Which is the odd one out? (a) breaking work into steps (b) listing tasks first (c) hard part first (d) forgetting the due date
- 19.Which of these is good project planning? (a) starting on the last day (b) breaking work into steps (c) ignoring the timetable (d) doing only easy bits
- 20.🧩 A big project feels scary. What should you do first? (a) wait for help (b) give up (c) do it all at once (d) break it into steps
- 21.Which of these is good project planning? (a) guessing how long (b) no spare time (c) one huge deadline (d) using a simple timetable
- 22.🔍 Which is the odd one out? (a) no spare time (b) checking progress weekly (c) doing only easy bits (d) starting on the last day
- 23.🔍 Which is the odd one out? (a) breaking work into steps (b) no spare time (c) starting early (d) checking progress weekly
- 24.Which of these is poor project planning? (a) keeping spare days (b) breaking work into steps (c) no task list (d) checking progress weekly
- 25.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 26.True or false: “keeping spare days” is good project planning. (a) False (b) True
- 27.True or false: “forgetting the due date” is poor project planning. (a) True (b) False
- 28.Which of these is good project planning? (a) one huge deadline (b) doing only easy bits (c) checking progress weekly (d) no spare time
- 29.Which of these is poor project planning? (a) keeping spare days (b) checking progress weekly (c) guessing how long (d) hard part first
- 30.✂️ Your team must make 18 posters in 3 days, the same number each day. How many posters a day?
- 31.Which of these is good project planning? (a) forgetting the due date (b) no task list (c) starting on the last day (d) hard part first
- 32.📅 Your history chart is due in 9 days. Research takes 1 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 33.📅 Your science model is due in 8 days. Research takes 1 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 34.✂️ Your team must make 35 paper bags in 5 days, the same number each day. How many paper bags a day?
- 35.True or false: “starting on the last day” is poor project planning. (a) False (b) True
- 36.Which of these is poor project planning? (a) hard part first (b) starting early (c) forgetting the due date (d) breaking work into steps
- 37.True or false: “breaking work into steps” is good project planning. (a) True (b) False
- 38.🔍 Which is the odd one out? (a) one huge deadline (b) starting early (c) setting mini-deadlines (d) breaking work into steps
- 39.True or false: “no task list” is poor project planning. (a) True (b) False
- 40.🔍 Which is the odd one out? (a) guessing how long (b) setting mini-deadlines (c) ignoring the timetable (d) forgetting the due date
Answer key
- 2
- 4
- starting on the last day
- ignoring the timetable
- 2
- study for the test
- 4:20 PM
- one huge deadline
- 9
- 9
- 5
- 7
- good planning
- False
- poor planning
- doing only easy bits
- this week
- forgetting the due date
- breaking work into steps
- break it into steps
- using a simple timetable
- checking progress weekly
- no spare time
- no task list
- poor planning
- True
- True
- checking progress weekly
- guessing how long
- 6
- hard part first
- 4
- 3
- 7
- True
- forgetting the due date
- True
- one huge deadline
- True
- setting mini-deadlines