Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.✅ What is a mini-deadline? (a) a date for one step (b) a late fine (c) a holiday (d) the final due date
- 2.📅 Your science model is due in 9 days. Research takes 3 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 3.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) for surprises (c) to rest only (d) to start late
- 4.🔍 Which is the odd one out? (a) breaking work into steps (b) starting on the last day (c) hard part first (d) listing tasks first
- 5.True or false: “ignoring the timetable” is poor project planning. (a) False (b) True
- 6.📅 Your school play is due in 10 days. Research takes 1 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 7.Which of these is good project planning? (a) doing only easy bits (b) one huge deadline (c) keeping spare days (d) starting on the last day
- 8.📅 Your maths exhibit is due in 11 days. Research takes 1 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
- 9.Which of these is good project planning? (a) hard part first (b) ignoring the timetable (c) one huge deadline (d) doing only easy bits
- 10.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 11.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
- 12.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 13.🔍 Which is the odd one out? (a) setting mini-deadlines (b) using a simple timetable (c) checking progress weekly (d) no task list
- 14.True or false: “no task list” is poor project planning. (a) True (b) False
- 15.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
- 16.🔍 Which is the odd one out? (a) setting mini-deadlines (b) hard part first (c) no spare time (d) checking progress weekly
- 17.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
- 18.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
- 19.⏰ You start at 3:30 PM. Homework takes 40 minutes, then project work takes 15 minutes. When will you finish? (a) 4:40 PM (b) 4:25 PM (c) 4:10 PM (d) 3:45 PM
- 20.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) after it is due (c) in the third week (d) the night before
- 21.True or false: “one huge deadline” is good project planning. (a) False (b) True
- 22.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 23.⏰ You start at 3:00 PM. Homework takes 35 minutes, then project work takes 40 minutes. When will you finish? (a) 4:30 PM (b) 4:15 PM (c) 3:35 PM (d) 3:40 PM
- 24.🔍 Which is the odd one out? (a) starting on the last day (b) one huge deadline (c) no spare time (d) setting mini-deadlines
- 25.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 26.📅 Good or poor project planning: guessing how long? (a) poor planning (b) good planning
- 27.✂️ Your team must make 18 posters in 2 days, the same number each day. How many posters a day?
- 28.✂️ Your team must make 6 name badges in 2 days, the same number each day. How many name badges a day?
- 29.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) give up (c) wait for help (d) break it into steps
- 30.Which of these is poor project planning? (a) listing tasks first (b) no task list (c) using a simple timetable (d) setting mini-deadlines
- 31.🔍 Which is the odd one out? (a) starting on the last day (b) no task list (c) checking progress weekly (d) guessing how long
- 32.✂️ Your team must make 16 name badges in 2 days, the same number each day. How many name badges a day?
- 33.Which of these is poor project planning? (a) listing tasks first (b) starting early (c) forgetting the due date (d) checking progress weekly
- 34.True or false: “forgetting the due date” is good project planning. (a) False (b) True
- 35.✂️ Your team must make 12 thank-you cards in 6 days, the same number each day. How many thank-you cards a day?
- 36.📅 Your eco-club poster is due in 8 days. Research takes 1 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
- 37.✂️ Your team must make 14 posters in 2 days, the same number each day. How many posters a day?
- 38.⏰ You start at 3:00 PM. Homework takes 30 minutes, then project work takes 35 minutes. When will you finish? (a) 3:30 PM (b) 4:20 PM (c) 3:35 PM (d) 4:05 PM
- 39.⏰ You start at 4:45 PM. Homework takes 20 minutes, then project work takes 30 minutes. When will you finish? (a) 5:05 PM (b) 5:15 PM (c) 5:35 PM (d) 5:50 PM
- 40.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
Answer key
- a date for one step
- 3
- for surprises
- starting on the last day
- True
- 2
- keeping spare days
- 5
- hard part first
- poor planning
- good planning
- good planning
- no task list
- True
- good planning
- no spare time
- poor planning
- good planning
- 4:25 PM
- this week
- False
- good planning
- 4:15 PM
- setting mini-deadlines
- poor planning
- poor planning
- 9
- 3
- break it into steps
- no task list
- checking progress weekly
- 8
- forgetting the due date
- False
- 2
- 2
- 7
- 4:05 PM
- 5:35 PM
- poor planning
Free leadership lessons, practice and worksheets at talentjr.in/leadership-skills-for-students