Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) to start late (c) for surprises (d) there is no need
- 2.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 3.🔍 Which is the odd one out? (a) no task list (b) doing only easy bits (c) guessing how long (d) hard part first
- 4.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
- 5.True or false: “listing tasks first” is good project planning. (a) True (b) False
- 6.Which of these is good project planning? (a) no spare time (b) checking progress weekly (c) doing only easy bits (d) starting on the last day
- 7.Which of these is poor project planning? (a) no task list (b) checking progress weekly (c) setting mini-deadlines (d) keeping spare days
- 8.📅 Your school play is due in 10 days. Research takes 4 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
- 9.🔍 Which is the odd one out? (a) breaking work into steps (b) doing only easy bits (c) forgetting the due date (d) no task list
- 10.Which of these is poor project planning? (a) starting early (b) checking progress weekly (c) hard part first (d) starting on the last day
- 11.True or false: “starting early” is poor project planning. (a) True (b) False
- 12.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
- 13.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) make the poster (c) neither (d) study for the test
- 14.⏰ You start at 4:45 PM. Homework takes 35 minutes, then project work takes 20 minutes. When will you finish? (a) 5:05 PM (b) 5:55 PM (c) 5:20 PM (d) 5:40 PM
- 15.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
- 16.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
- 17.📅 Good or poor project planning: one huge deadline? (a) poor planning (b) good planning
- 18.📅 Your history chart is due in 7 days. Research takes 1 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 19.🔍 Which is the odd one out? (a) listing tasks first (b) starting early (c) keeping spare days (d) no task list
- 20.✂️ Your team must make 45 paper bags in 5 days, the same number each day. How many paper bags a day?
- 21.⏰ You start at 5:30 PM. Homework takes 45 minutes, then project work takes 20 minutes. When will you finish? (a) 5:50 PM (b) 6:35 PM (c) 6:50 PM (d) 6:15 PM
- 22.⏰ You start at 4:15 PM. Homework takes 35 minutes, then project work takes 30 minutes. When will you finish? (a) 4:50 PM (b) 4:45 PM (c) 5:35 PM (d) 5:20 PM
- 23.Which of these is good project planning? (a) ignoring the timetable (b) doing only easy bits (c) starting on the last day (d) starting early
- 24.🔍 Which is the odd one out? (a) no task list (b) ignoring the timetable (c) using a simple timetable (d) one huge deadline
- 25.📅 Your art display is due in 11 days. Research takes 4 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 26.True or false: “no spare time” is poor project planning. (a) False (b) True
- 27.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 28.🔍 Which is the odd one out? (a) starting early (b) starting on the last day (c) keeping spare days (d) setting mini-deadlines
- 29.✂️ Your team must make 10 bookmarks in 2 days, the same number each day. How many bookmarks a day?
- 30.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 31.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) in the third week (c) this week (d) the night before
- 32.🔍 Which is the odd one out? (a) ignoring the timetable (b) forgetting the due date (c) listing tasks first (d) doing only easy bits
- 33.🔍 Which is the odd one out? (a) starting early (b) ignoring the timetable (c) starting on the last day (d) no spare time
- 34.🔍 Which is the odd one out? (a) doing only easy bits (b) no spare time (c) setting mini-deadlines (d) one huge deadline
- 35.🔍 Which is the odd one out? (a) listing tasks first (b) checking progress weekly (c) using a simple timetable (d) ignoring the timetable
- 36.📅 Your history chart is due in 9 days. Research takes 3 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 37.True or false: “no task list” is poor project planning. (a) True (b) False
- 38.⏰ You start at 5:45 PM. Homework takes 45 minutes, then project work takes 15 minutes. When will you finish? (a) 7:00 PM (b) 6:45 PM (c) 6:00 PM (d) 6:30 PM
- 39.⏰ You start at 3:30 PM. Homework takes 45 minutes, then project work takes 30 minutes. When will you finish? (a) 4:15 PM (b) 5:00 PM (c) 4:00 PM (d) 4:45 PM
- 40.📅 Your art display is due in 12 days. Research takes 4 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
Answer key
- for surprises
- good planning
- hard part first
- good planning
- True
- checking progress weekly
- no task list
- 1
- breaking work into steps
- starting on the last day
- False
- poor planning
- study for the test
- 5:40 PM
- poor planning
- poor planning
- poor planning
- 3
- no task list
- 9
- 6:35 PM
- 5:20 PM
- starting early
- using a simple timetable
- 1
- True
- poor planning
- starting on the last day
- 5
- poor planning
- this week
- listing tasks first
- starting early
- setting mini-deadlines
- ignoring the timetable
- 2
- True
- 6:45 PM
- 4:45 PM
- 3