Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 177 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
  2. 2.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
  3. 3.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) there is no need (c) to start late (d) for surprises
  4. 4.Which of these is poor project planning? (a) breaking work into steps (b) using a simple timetable (c) starting on the last day (d) hard part first
  5. 5.🔍 Which is the odd one out? (a) one huge deadline (b) no spare time (c) starting early (d) guessing how long
  6. 6.📅 Good or poor project planning: using a simple timetable? (a) poor planning (b) good planning
  7. 7.True or false: “hard part first” is good project planning. (a) False (b) True
  8. 8.📅 Your maths exhibit is due in 13 days. Research takes 2 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  9. 9.Which of these is poor project planning? (a) forgetting the due date (b) breaking work into steps (c) using a simple timetable (d) keeping spare days
  10. 10.🧩 A big project feels scary. What should you do first? (a) wait for help (b) give up (c) do it all at once (d) break it into steps
  11. 11.🔍 Which is the odd one out? (a) doing only easy bits (b) checking progress weekly (c) one huge deadline (d) no task list
  12. 12.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
  13. 13.Which of these is poor project planning? (a) setting mini-deadlines (b) checking progress weekly (c) listing tasks first (d) no spare time
  14. 14.True or false: “using a simple timetable” is poor project planning. (a) True (b) False
  15. 15.Which of these is good project planning? (a) doing only easy bits (b) starting early (c) no spare time (d) no task list
  16. 16.✅ What is a mini-deadline? (a) a date for one step (b) a late fine (c) the final due date (d) a holiday
  17. 17.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
  18. 18.True or false: “keeping spare days” is good project planning. (a) True (b) False
  19. 19.Which of these is good project planning? (a) using a simple timetable (b) guessing how long (c) no task list (d) one huge deadline
  20. 20.Which of these is poor project planning? (a) ignoring the timetable (b) breaking work into steps (c) keeping spare days (d) checking progress weekly
  21. 21.Which of these is poor project planning? (a) one huge deadline (b) hard part first (c) using a simple timetable (d) listing tasks first
  22. 22.✂️ Your team must make 12 thank-you cards in 6 days, the same number each day. How many thank-you cards a day?
  23. 23.True or false: “hard part first” is poor project planning. (a) True (b) False
  24. 24.🔍 Which is the odd one out? (a) starting on the last day (b) no task list (c) breaking work into steps (d) doing only easy bits
  25. 25.⏰ You start at 3:15 PM. Homework takes 30 minutes, then project work takes 15 minutes. When will you finish? (a) 3:45 PM (b) 4:15 PM (c) 3:30 PM (d) 4:00 PM
  26. 26.📅 Your eco-club poster is due in 11 days. Research takes 3 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
  27. 27.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) in the third week (c) after it is due (d) the night before
  28. 28.True or false: “listing tasks first” is good project planning. (a) True (b) False
  29. 29.Which of these is poor project planning? (a) breaking work into steps (b) keeping spare days (c) doing only easy bits (d) starting early
  30. 30.Which of these is good project planning? (a) no spare time (b) hard part first (c) starting on the last day (d) no task list
  31. 31.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
  32. 32.⏰ You start at 3:30 PM. Homework takes 45 minutes, then project work takes 20 minutes. When will you finish? (a) 4:15 PM (b) 4:50 PM (c) 3:50 PM (d) 4:35 PM
  33. 33.📅 Your maths exhibit is due in 12 days. Research takes 3 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  34. 34.🔍 Which is the odd one out? (a) listing tasks first (b) checking progress weekly (c) one huge deadline (d) starting early
  35. 35.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
  36. 36.🔍 Which is the odd one out? (a) one huge deadline (b) no spare time (c) listing tasks first (d) starting on the last day
  37. 37.Which of these is poor project planning? (a) starting early (b) checking progress weekly (c) setting mini-deadlines (d) no task list
  38. 38.📅 Your class magazine is due in 9 days. Research takes 2 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
  39. 39.📅 Your eco-club poster is due in 10 days. Research takes 2 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
  40. 40.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning

Answer key

  1. poor planning
  2. good planning
  3. for surprises
  4. starting on the last day
  5. starting early
  6. good planning
  7. True
  8. 3
  9. forgetting the due date
  10. break it into steps
  11. checking progress weekly
  12. poor planning
  13. no spare time
  14. False
  15. starting early
  16. a date for one step
  17. poor planning
  18. True
  19. using a simple timetable
  20. ignoring the timetable
  21. one huge deadline
  22. 2
  23. False
  24. breaking work into steps
  25. 4:00 PM
  26. 1
  27. this week
  28. True
  29. doing only easy bits
  30. hard part first
  31. good planning
  32. 4:35 PM
  33. 1
  34. one huge deadline
  35. good planning
  36. listing tasks first
  37. no task list
  38. 2
  39. 3
  40. poor planning