Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 2.True or false: “guessing how long” is poor project planning. (a) False (b) True
- 3.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
- 4.📅 Your class magazine is due in 16 days. Research takes 3 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
- 5.🔍 Which is the odd one out? (a) one huge deadline (b) breaking work into steps (c) listing tasks first (d) setting mini-deadlines
- 6.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
- 7.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) neither (c) make the poster (d) study for the test
- 8.✂️ Your team must make 12 posters in 2 days, the same number each day. How many posters a day?
- 9.🗓️ Your project is due in three weeks. When should you start? (a) the night before (b) in the third week (c) this week (d) after it is due
- 10.🔍 Which is the odd one out? (a) checking progress weekly (b) setting mini-deadlines (c) listing tasks first (d) ignoring the timetable
- 11.True or false: “hard part first” is poor project planning. (a) False (b) True
- 12.🔍 Which is the odd one out? (a) checking progress weekly (b) starting on the last day (c) no spare time (d) ignoring the timetable
- 13.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) for surprises (c) to start late (d) there is no need
- 14.Which of these is good project planning? (a) no task list (b) breaking work into steps (c) doing only easy bits (d) ignoring the timetable
- 15.🔍 Which is the odd one out? (a) starting early (b) ignoring the timetable (c) no task list (d) one huge deadline
- 16.🧩 A big project feels scary. What should you do first? (a) wait for help (b) give up (c) do it all at once (d) break it into steps
- 17.Which of these is good project planning? (a) guessing how long (b) hard part first (c) doing only easy bits (d) starting on the last day
- 18.Which of these is good project planning? (a) starting on the last day (b) no task list (c) one huge deadline (d) listing tasks first
- 19.🔍 Which is the odd one out? (a) breaking work into steps (b) no task list (c) no spare time (d) ignoring the timetable
- 20.✂️ Your team must make 21 name badges in 3 days, the same number each day. How many name badges a day?
- 21.True or false: “ignoring the timetable” is good project planning. (a) True (b) False
- 22.Which of these is poor project planning? (a) no task list (b) starting early (c) checking progress weekly (d) listing tasks first
- 23.📅 Your eco-club poster is due in 11 days. Research takes 2 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
- 24.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
- 25.✂️ Your team must make 21 paper flowers in 3 days, the same number each day. How many paper flowers a day?
- 26.🔍 Which is the odd one out? (a) keeping spare days (b) breaking work into steps (c) hard part first (d) no task list
- 27.🔍 Which is the odd one out? (a) starting early (b) starting on the last day (c) using a simple timetable (d) setting mini-deadlines
- 28.Which of these is poor project planning? (a) guessing how long (b) breaking work into steps (c) listing tasks first (d) starting early
- 29.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 30.📅 Your history chart is due in 9 days. Research takes 2 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 31.🔍 Which is the odd one out? (a) hard part first (b) doing only easy bits (c) guessing how long (d) starting on the last day
- 32.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 33.True or false: “checking progress weekly” is good project planning. (a) False (b) True
- 34.True or false: “starting early” is poor project planning. (a) False (b) True
- 35.True or false: “starting early” is good project planning. (a) False (b) True
- 36.True or false: “guessing how long” is good project planning. (a) True (b) False
- 37.✂️ Your team must make 25 name badges in 5 days, the same number each day. How many name badges a day?
- 38.🔍 Which is the odd one out? (a) using a simple timetable (b) listing tasks first (c) breaking work into steps (d) forgetting the due date
- 39.✂️ Your team must make 24 name badges in 4 days, the same number each day. How many name badges a day?
- 40.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
Answer key
- good planning
- True
- good planning
- 5
- one huge deadline
- good planning
- study for the test
- 6
- this week
- ignoring the timetable
- False
- checking progress weekly
- for surprises
- breaking work into steps
- starting early
- break it into steps
- hard part first
- listing tasks first
- breaking work into steps
- 7
- False
- no task list
- 3
- good planning
- 7
- no task list
- starting on the last day
- guessing how long
- poor planning
- 3
- hard part first
- poor planning
- True
- False
- True
- False
- 5
- forgetting the due date
- 6
- poor planning