Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Your art display is due in 14 days. Research takes 4 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 2.📅 Your school play is due in 5 days. Research takes 1 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 3.📅 Good or poor project planning: using a simple timetable? (a) poor planning (b) good planning
- 4.🗓️ Your project is due in three weeks. When should you start? (a) the night before (b) in the third week (c) after it is due (d) this week
- 5.✅ What is a mini-deadline? (a) a holiday (b) a date for one step (c) a late fine (d) the final due date
- 6.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
- 7.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 8.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
- 9.📅 Your eco-club poster is due in 12 days. Research takes 1 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
- 10.✂️ Your team must make 8 name badges in 2 days, the same number each day. How many name badges a day?
- 11.Which of these is good project planning? (a) one huge deadline (b) breaking work into steps (c) no task list (d) starting on the last day
- 12.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to start late (c) for surprises (d) to rest only
- 13.🧩 A big project feels scary. What should you do first? (a) wait for help (b) break it into steps (c) do it all at once (d) give up
- 14.True or false: “one huge deadline” is good project planning. (a) False (b) True
- 15.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
- 16.🔍 Which is the odd one out? (a) no spare time (b) breaking work into steps (c) one huge deadline (d) starting on the last day
- 17.Which of these is good project planning? (a) doing only easy bits (b) ignoring the timetable (c) checking progress weekly (d) guessing how long
- 18.True or false: “forgetting the due date” is poor project planning. (a) True (b) False
- 19.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
- 20.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 21.✂️ Your team must make 14 thank-you cards in 2 days, the same number each day. How many thank-you cards a day?
- 22.🔍 Which is the odd one out? (a) guessing how long (b) starting early (c) no task list (d) starting on the last day
- 23.🔍 Which is the odd one out? (a) listing tasks first (b) breaking work into steps (c) keeping spare days (d) no spare time
- 24.🔍 Which is the odd one out? (a) listing tasks first (b) hard part first (c) doing only easy bits (d) starting early
- 25.Which of these is good project planning? (a) guessing how long (b) listing tasks first (c) no task list (d) starting on the last day
- 26.📅 Your class magazine is due in 9 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 27.True or false: “setting mini-deadlines” is good project planning. (a) False (b) True
- 28.Which of these is good project planning? (a) using a simple timetable (b) forgetting the due date (c) no task list (d) guessing how long
- 29.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 30.⏰ You start at 3:00 PM. Homework takes 30 minutes, then project work takes 30 minutes. When will you finish? (a) 3:30 PM (b) 4:15 PM (c) 4:00 PM
- 31.🔍 Which is the odd one out? (a) starting early (b) checking progress weekly (c) hard part first (d) starting on the last day
- 32.True or false: “no task list” is good project planning. (a) True (b) False
- 33.Which of these is poor project planning? (a) keeping spare days (b) hard part first (c) listing tasks first (d) guessing how long
- 34.Which of these is poor project planning? (a) one huge deadline (b) using a simple timetable (c) hard part first (d) starting early
- 35.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 36.✂️ Your team must make 8 name badges in 4 days, the same number each day. How many name badges a day?
- 37.⏰ You start at 4:30 PM. Homework takes 20 minutes, then project work takes 15 minutes. When will you finish? (a) 4:50 PM (b) 4:45 PM (c) 5:20 PM (d) 5:05 PM
- 38.🔍 Which is the odd one out? (a) guessing how long (b) setting mini-deadlines (c) one huge deadline (d) forgetting the due date
- 39.True or false: “hard part first” is poor project planning. (a) True (b) False
- 40.🔍 Which is the odd one out? (a) doing only easy bits (b) one huge deadline (c) guessing how long (d) hard part first
Answer key
- 3
- 1
- good planning
- this week
- a date for one step
- good planning
- poor planning
- good planning
- 3
- 4
- breaking work into steps
- for surprises
- break it into steps
- False
- good planning
- breaking work into steps
- checking progress weekly
- True
- poor planning
- good planning
- 7
- starting early
- no spare time
- doing only easy bits
- listing tasks first
- 2
- True
- using a simple timetable
- poor planning
- 4:00 PM
- starting on the last day
- False
- guessing how long
- one huge deadline
- poor planning
- 2
- 5:05 PM
- setting mini-deadlines
- False
- hard part first