Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
- 2.⏰ You start at 5:15 PM. Homework takes 20 minutes, then project work takes 35 minutes. When will you finish? (a) 5:35 PM (b) 6:10 PM (c) 5:50 PM (d) 6:25 PM
- 3.True or false: “guessing how long” is poor project planning. (a) False (b) True
- 4.🧩 A big project feels scary. What should you do first? (a) give up (b) do it all at once (c) break it into steps (d) wait for help
- 5.Which of these is poor project planning? (a) hard part first (b) starting on the last day (c) listing tasks first (d) keeping spare days
- 6.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) neither (c) play first (d) make the poster
- 7.✂️ Your team must make 18 posters in 2 days, the same number each day. How many posters a day?
- 8.📅 Your art display is due in 12 days. Research takes 2 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 9.True or false: “checking progress weekly” is poor project planning. (a) True (b) False
- 10.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to rest only (c) for surprises (d) to start late
- 11.🔍 Which is the odd one out? (a) no task list (b) one huge deadline (c) setting mini-deadlines (d) guessing how long
- 12.Which of these is poor project planning? (a) keeping spare days (b) hard part first (c) breaking work into steps (d) ignoring the timetable
- 13.📅 Your maths exhibit is due in 10 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 14.📅 Your eco-club poster is due in 12 days. Research takes 2 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 15.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
- 16.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
- 17.📅 Good or poor project planning: one huge deadline? (a) poor planning (b) good planning
- 18.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 19.Which of these is poor project planning? (a) starting early (b) listing tasks first (c) keeping spare days (d) guessing how long
- 20.🔍 Which is the odd one out? (a) keeping spare days (b) doing only easy bits (c) setting mini-deadlines (d) breaking work into steps
- 21.📅 Your eco-club poster is due in 7 days. Research takes 2 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 22.✅ What is a mini-deadline? (a) a late fine (b) a holiday (c) a date for one step (d) the final due date
- 23.True or false: “no spare time” is good project planning. (a) False (b) True
- 24.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) this week (c) after it is due (d) the night before
- 25.✂️ Your team must make 10 paper flowers in 5 days, the same number each day. How many paper flowers a day?
- 26.True or false: “ignoring the timetable” is poor project planning. (a) False (b) True
- 27.📅 Your science model is due in 9 days. Research takes 1 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 28.True or false: “one huge deadline” is poor project planning. (a) False (b) True
- 29.True or false: “starting early” is good project planning. (a) False (b) True
- 30.📅 Your school play is due in 11 days. Research takes 4 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 31.Which of these is poor project planning? (a) hard part first (b) using a simple timetable (c) forgetting the due date (d) starting early
- 32.📅 Your maths exhibit is due in 10 days. Research takes 1 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 33.Which of these is good project planning? (a) guessing how long (b) no spare time (c) setting mini-deadlines (d) no task list
- 34.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
- 35.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
- 36.True or false: “breaking work into steps” is poor project planning. (a) True (b) False
- 37.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 38.🔍 Which is the odd one out? (a) one huge deadline (b) starting on the last day (c) forgetting the due date (d) keeping spare days
- 39.True or false: “setting mini-deadlines” is poor project planning. (a) False (b) True
- 40.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
Answer key
- poor planning
- 6:10 PM
- True
- break it into steps
- starting on the last day
- study for the test
- 9
- 4
- False
- for surprises
- setting mini-deadlines
- ignoring the timetable
- 3
- 3
- poor planning
- good planning
- poor planning
- poor planning
- guessing how long
- doing only easy bits
- 1
- a date for one step
- False
- this week
- 2
- True
- 5
- True
- True
- 3
- forgetting the due date
- 3
- setting mini-deadlines
- poor planning
- good planning
- False
- good planning
- keeping spare days
- False
- good planning
Free leadership lessons, practice and worksheets at talentjr.in/leadership-skills-for-students