Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 207 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.🔍 Which is the odd one out? (a) one huge deadline (b) starting early (c) checking progress weekly (d) listing tasks first
  2. 2.⏰ You start at 3:15 PM. Homework takes 35 minutes, then project work takes 25 minutes. When will you finish? (a) 4:30 PM (b) 3:50 PM (c) 3:40 PM (d) 4:15 PM
  3. 3.✂️ Your team must make 6 paper flowers in 2 days, the same number each day. How many paper flowers a day?
  4. 4.📅 Your maths exhibit is due in 12 days. Research takes 2 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
  5. 5.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
  6. 6.Which of these is poor project planning? (a) starting early (b) using a simple timetable (c) setting mini-deadlines (d) no spare time
  7. 7.Which of these is good project planning? (a) starting early (b) no spare time (c) guessing how long (d) ignoring the timetable
  8. 8.Which of these is poor project planning? (a) hard part first (b) listing tasks first (c) doing only easy bits (d) breaking work into steps
  9. 9.True or false: “breaking work into steps” is good project planning. (a) False (b) True
  10. 10.Which of these is poor project planning? (a) using a simple timetable (b) checking progress weekly (c) starting early (d) no task list
  11. 11.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
  12. 12.True or false: “hard part first” is poor project planning. (a) True (b) False
  13. 13.⏰ You start at 3:15 PM. Homework takes 25 minutes, then project work takes 35 minutes. When will you finish? (a) 3:40 PM (b) 3:50 PM (c) 4:30 PM (d) 4:15 PM
  14. 14.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) make the poster (c) play first (d) neither
  15. 15.🔍 Which is the odd one out? (a) checking progress weekly (b) using a simple timetable (c) forgetting the due date (d) setting mini-deadlines
  16. 16.Which of these is good project planning? (a) doing only easy bits (b) hard part first (c) starting on the last day (d) ignoring the timetable
  17. 17.✅ What is a mini-deadline? (a) the final due date (b) a late fine (c) a holiday (d) a date for one step
  18. 18.True or false: “checking progress weekly” is good project planning. (a) True (b) False
  19. 19.🧩 A big project feels scary. What should you do first? (a) wait for help (b) give up (c) break it into steps (d) do it all at once
  20. 20.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
  21. 21.📅 Your history chart is due in 10 days. Research takes 4 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
  22. 22.✂️ Your team must make 24 paper flowers in 6 days, the same number each day. How many paper flowers a day?
  23. 23.✂️ Your team must make 10 paper bags in 5 days, the same number each day. How many paper bags a day?
  24. 24.Which of these is poor project planning? (a) listing tasks first (b) hard part first (c) starting on the last day (d) keeping spare days
  25. 25.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) to start late (c) there is no need (d) for surprises
  26. 26.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
  27. 27.📅 Good or poor project planning: one huge deadline? (a) poor planning (b) good planning
  28. 28.🔍 Which is the odd one out? (a) listing tasks first (b) no spare time (c) setting mini-deadlines (d) keeping spare days
  29. 29.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
  30. 30.🔍 Which is the odd one out? (a) listing tasks first (b) using a simple timetable (c) setting mini-deadlines (d) guessing how long
  31. 31.🔍 Which is the odd one out? (a) starting early (b) listing tasks first (c) setting mini-deadlines (d) doing only easy bits
  32. 32.True or false: “checking progress weekly” is poor project planning. (a) True (b) False
  33. 33.Which of these is poor project planning? (a) checking progress weekly (b) setting mini-deadlines (c) listing tasks first (d) one huge deadline
  34. 34.True or false: “guessing how long” is poor project planning. (a) True (b) False
  35. 35.Which of these is poor project planning? (a) ignoring the timetable (b) checking progress weekly (c) keeping spare days (d) starting early
  36. 36.⏰ You start at 3:30 PM. Homework takes 20 minutes, then project work takes 25 minutes. When will you finish? (a) 3:50 PM (b) 4:15 PM (c) 4:30 PM (d) 3:55 PM
  37. 37.True or false: “starting on the last day” is poor project planning. (a) False (b) True
  38. 38.🔍 Which is the odd one out? (a) no task list (b) using a simple timetable (c) hard part first (d) starting early
  39. 39.📅 Your class magazine is due in 10 days. Research takes 3 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
  40. 40.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning

Answer key

  1. one huge deadline
  2. 4:15 PM
  3. 3
  4. 3
  5. good planning
  6. no spare time
  7. starting early
  8. doing only easy bits
  9. True
  10. no task list
  11. poor planning
  12. False
  13. 4:15 PM
  14. study for the test
  15. forgetting the due date
  16. hard part first
  17. a date for one step
  18. True
  19. break it into steps
  20. good planning
  21. 1
  22. 4
  23. 2
  24. starting on the last day
  25. for surprises
  26. poor planning
  27. poor planning
  28. no spare time
  29. good planning
  30. guessing how long
  31. doing only easy bits
  32. False
  33. one huge deadline
  34. True
  35. ignoring the timetable
  36. 4:15 PM
  37. True
  38. no task list
  39. 1
  40. poor planning