Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.True or false: “checking progress weekly” is good project planning. (a) False (b) True
- 2.🔍 Which is the odd one out? (a) listing tasks first (b) forgetting the due date (c) starting on the last day (d) one huge deadline
- 3.📅 Your science model is due in 12 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 4.📅 Your science model is due in 7 days. Research takes 2 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 5.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) in the third week (c) this week (d) the night before
- 6.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
- 7.True or false: “one huge deadline” is good project planning. (a) True (b) False
- 8.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
- 9.🔍 Which is the odd one out? (a) checking progress weekly (b) setting mini-deadlines (c) starting on the last day (d) breaking work into steps
- 10.⏳ Why keep a spare day or two before the deadline? (a) for surprises (b) to rest only (c) there is no need (d) to start late
- 11.Which of these is poor project planning? (a) setting mini-deadlines (b) breaking work into steps (c) no task list (d) keeping spare days
- 12.True or false: “keeping spare days” is poor project planning. (a) True (b) False
- 13.🔍 Which is the odd one out? (a) no task list (b) setting mini-deadlines (c) ignoring the timetable (d) forgetting the due date
- 14.📅 Your history chart is due in 11 days. Research takes 2 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
- 15.Which of these is good project planning? (a) one huge deadline (b) doing only easy bits (c) no spare time (d) setting mini-deadlines
- 16.📅 Your class magazine is due in 13 days. Research takes 3 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
- 17.🔍 Which is the odd one out? (a) keeping spare days (b) ignoring the timetable (c) setting mini-deadlines (d) breaking work into steps
- 18.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
- 19.True or false: “ignoring the timetable” is good project planning. (a) True (b) False
- 20.🔍 Which is the odd one out? (a) hard part first (b) setting mini-deadlines (c) guessing how long (d) listing tasks first
- 21.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
- 22.Which of these is good project planning? (a) starting on the last day (b) listing tasks first (c) one huge deadline (d) no spare time
- 23.True or false: “no task list” is poor project planning. (a) True (b) False
- 24.🔍 Which is the odd one out? (a) listing tasks first (b) doing only easy bits (c) keeping spare days (d) using a simple timetable
- 25.Which of these is good project planning? (a) no task list (b) starting early (c) no spare time (d) doing only easy bits
- 26.✂️ Your team must make 24 bookmarks in 4 days, the same number each day. How many bookmarks a day?
- 27.⏰ You start at 3:30 PM. Homework takes 20 minutes, then project work takes 25 minutes. When will you finish? (a) 3:55 PM (b) 4:15 PM (c) 4:30 PM (d) 3:50 PM
- 28.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) make the poster (c) study for the test (d) play first
- 29.🔍 Which is the odd one out? (a) hard part first (b) using a simple timetable (c) setting mini-deadlines (d) one huge deadline
- 30.✂️ Your team must make 42 paper flowers in 6 days, the same number each day. How many paper flowers a day?
- 31.✅ What is a mini-deadline? (a) a holiday (b) a late fine (c) a date for one step (d) the final due date
- 32.Which of these is good project planning? (a) doing only easy bits (b) no task list (c) hard part first (d) guessing how long
- 33.🔍 Which is the odd one out? (a) doing only easy bits (b) starting on the last day (c) ignoring the timetable (d) keeping spare days
- 34.True or false: “listing tasks first” is poor project planning. (a) False (b) True
- 35.True or false: “setting mini-deadlines” is good project planning. (a) True (b) False
- 36.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
- 37.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 38.Which of these is good project planning? (a) starting on the last day (b) no spare time (c) doing only easy bits (d) keeping spare days
- 39.Which of these is good project planning? (a) checking progress weekly (b) doing only easy bits (c) starting on the last day (d) ignoring the timetable
- 40.True or false: “setting mini-deadlines” is poor project planning. (a) True (b) False
Answer key
- True
- listing tasks first
- 5
- 2
- this week
- poor planning
- False
- good planning
- starting on the last day
- for surprises
- no task list
- False
- setting mini-deadlines
- 1
- setting mini-deadlines
- 2
- ignoring the timetable
- good planning
- False
- guessing how long
- poor planning
- listing tasks first
- True
- doing only easy bits
- starting early
- 6
- 4:15 PM
- study for the test
- one huge deadline
- 7
- a date for one step
- hard part first
- keeping spare days
- False
- True
- good planning
- poor planning
- keeping spare days
- checking progress weekly
- False