Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Your maths exhibit is due in 10 days. Research takes 2 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 2.🔍 Which is the odd one out? (a) no task list (b) one huge deadline (c) ignoring the timetable (d) hard part first
- 3.🔍 Which is the odd one out? (a) listing tasks first (b) starting on the last day (c) ignoring the timetable (d) no spare time
- 4.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 5.⏰ You start at 4:30 PM. Homework takes 20 minutes, then project work takes 30 minutes. When will you finish? (a) 5:20 PM (b) 4:50 PM (c) 5:35 PM (d) 5:00 PM
- 6.True or false: “listing tasks first” is good project planning. (a) False (b) True
- 7.🔍 Which is the odd one out? (a) starting on the last day (b) guessing how long (c) no spare time (d) starting early
- 8.True or false: “starting early” is poor project planning. (a) False (b) True
- 9.Which of these is poor project planning? (a) one huge deadline (b) breaking work into steps (c) hard part first (d) keeping spare days
- 10.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
- 11.Which of these is good project planning? (a) starting on the last day (b) forgetting the due date (c) one huge deadline (d) keeping spare days
- 12.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) study for the test (c) make the poster (d) neither
- 13.True or false: “no task list” is poor project planning. (a) True (b) False
- 14.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 15.True or false: “starting early” is good project planning. (a) True (b) False
- 16.🔍 Which is the odd one out? (a) using a simple timetable (b) breaking work into steps (c) keeping spare days (d) no task list
- 17.Which of these is good project planning? (a) setting mini-deadlines (b) starting on the last day (c) one huge deadline (d) no spare time
- 18.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 19.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
- 20.🔍 Which is the odd one out? (a) doing only easy bits (b) checking progress weekly (c) ignoring the timetable (d) starting on the last day
- 21.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) after it is due (c) the night before (d) this week
- 22.Which of these is good project planning? (a) no task list (b) ignoring the timetable (c) one huge deadline (d) listing tasks first
- 23.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 24.Which of these is poor project planning? (a) breaking work into steps (b) listing tasks first (c) hard part first (d) starting on the last day
- 25.✂️ Your team must make 24 bookmarks in 4 days, the same number each day. How many bookmarks a day?
- 26.Which of these is good project planning? (a) forgetting the due date (b) starting on the last day (c) hard part first (d) one huge deadline
- 27.True or false: “keeping spare days” is poor project planning. (a) True (b) False
- 28.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 29.True or false: “setting mini-deadlines” is poor project planning. (a) True (b) False
- 30.Which of these is good project planning? (a) doing only easy bits (b) forgetting the due date (c) ignoring the timetable (d) breaking work into steps
- 31.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to start late (c) for surprises (d) to rest only
- 32.📅 Your class magazine is due in 8 days. Research takes 1 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
- 33.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
- 34.🔍 Which is the odd one out? (a) no task list (b) keeping spare days (c) ignoring the timetable (d) one huge deadline
- 35.✂️ Your team must make 12 paper bags in 4 days, the same number each day. How many paper bags a day?
- 36.True or false: “keeping spare days” is good project planning. (a) True (b) False
- 37.⏰ You start at 5:45 PM. Homework takes 35 minutes, then project work takes 35 minutes. When will you finish? (a) 6:55 PM (b) 6:20 PM (c) 7:10 PM
- 38.🔍 Which is the odd one out? (a) starting early (b) no spare time (c) checking progress weekly (d) breaking work into steps
- 39.🔍 Which is the odd one out? (a) starting early (b) breaking work into steps (c) using a simple timetable (d) guessing how long
- 40.📅 Your maths exhibit is due in 11 days. Research takes 2 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
Answer key
- 4
- hard part first
- listing tasks first
- poor planning
- 5:20 PM
- True
- starting early
- False
- one huge deadline
- good planning
- keeping spare days
- study for the test
- True
- good planning
- True
- no task list
- setting mini-deadlines
- good planning
- good planning
- checking progress weekly
- this week
- listing tasks first
- poor planning
- starting on the last day
- 6
- hard part first
- False
- poor planning
- False
- breaking work into steps
- for surprises
- 1
- poor planning
- keeping spare days
- 3
- True
- 6:55 PM
- no spare time
- guessing how long
- 2