Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.🔍 Which is the odd one out? (a) no spare time (b) doing only easy bits (c) no task list (d) checking progress weekly
- 2.📅 Your maths exhibit is due in 13 days. Research takes 4 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
- 3.✂️ Your team must make 42 posters in 6 days, the same number each day. How many posters a day?
- 4.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 5.True or false: “listing tasks first” is poor project planning. (a) False (b) True
- 6.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
- 7.Which of these is good project planning? (a) checking progress weekly (b) no task list (c) ignoring the timetable (d) forgetting the due date
- 8.📅 Your school play is due in 10 days. Research takes 1 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
- 9.True or false: “breaking work into steps” is good project planning. (a) False (b) True
- 10.🔍 Which is the odd one out? (a) using a simple timetable (b) guessing how long (c) one huge deadline (d) no spare time
- 11.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
- 12.Which of these is good project planning? (a) starting early (b) starting on the last day (c) forgetting the due date (d) no task list
- 13.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) in the third week (c) this week (d) the night before
- 14.🧩 A big project feels scary. What should you do first? (a) wait for help (b) do it all at once (c) break it into steps (d) give up
- 15.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
- 16.True or false: “no spare time” is poor project planning. (a) True (b) False
- 17.✂️ Your team must make 18 thank-you cards in 2 days, the same number each day. How many thank-you cards a day?
- 18.True or false: “starting early” is good project planning. (a) False (b) True
- 19.🔍 Which is the odd one out? (a) starting early (b) listing tasks first (c) ignoring the timetable (d) setting mini-deadlines
- 20.Which of these is poor project planning? (a) one huge deadline (b) setting mini-deadlines (c) breaking work into steps (d) hard part first
- 21.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 22.True or false: “starting early” is poor project planning. (a) True (b) False
- 23.True or false: “no task list” is good project planning. (a) True (b) False
- 24.Which of these is good project planning? (a) guessing how long (b) setting mini-deadlines (c) forgetting the due date (d) ignoring the timetable
- 25.🔍 Which is the odd one out? (a) using a simple timetable (b) one huge deadline (c) listing tasks first (d) keeping spare days
- 26.📅 Your history chart is due in 8 days. Research takes 1 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
- 27.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to rest only (c) to start late (d) for surprises
- 28.✂️ Your team must make 12 posters in 4 days, the same number each day. How many posters a day?
- 29.📅 Your art display is due in 7 days. Research takes 1 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
- 30.📅 Good or poor project planning: guessing how long? (a) poor planning (b) good planning
- 31.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) neither (c) make the poster (d) study for the test
- 32.Which of these is good project planning? (a) listing tasks first (b) starting on the last day (c) guessing how long (d) no spare time
- 33.True or false: “starting on the last day” is poor project planning. (a) True (b) False
- 34.✅ What is a mini-deadline? (a) a holiday (b) the final due date (c) a date for one step (d) a late fine
- 35.Which of these is poor project planning? (a) breaking work into steps (b) starting early (c) hard part first (d) forgetting the due date
- 36.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
- 37.📅 Your art display is due in 12 days. Research takes 3 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 38.🔍 Which is the odd one out? (a) forgetting the due date (b) listing tasks first (c) no spare time (d) no task list
- 39.🔍 Which is the odd one out? (a) forgetting the due date (b) setting mini-deadlines (c) doing only easy bits (d) one huge deadline
- 40.Which of these is poor project planning? (a) breaking work into steps (b) doing only easy bits (c) keeping spare days (d) setting mini-deadlines
Answer key
- checking progress weekly
- 4
- 7
- good planning
- False
- poor planning
- checking progress weekly
- 3
- True
- using a simple timetable
- poor planning
- starting early
- this week
- break it into steps
- good planning
- True
- 9
- True
- ignoring the timetable
- one huge deadline
- good planning
- False
- False
- setting mini-deadlines
- one huge deadline
- 2
- for surprises
- 3
- 1
- poor planning
- study for the test
- listing tasks first
- True
- a date for one step
- forgetting the due date
- good planning
- 3
- listing tasks first
- setting mini-deadlines
- doing only easy bits
Free leadership lessons, practice and worksheets at talentjr.in/leadership-skills-for-students