Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Good or poor project planning: guessing how long? (a) poor planning (b) good planning
- 2.Which of these is good project planning? (a) guessing how long (b) breaking work into steps (c) no task list (d) ignoring the timetable
- 3.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 4.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
- 5.✂️ Your team must make 14 name badges in 2 days, the same number each day. How many name badges a day?
- 6.🧩 A big project feels scary. What should you do first? (a) break it into steps (b) do it all at once (c) wait for help (d) give up
- 7.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 8.🔍 Which is the odd one out? (a) ignoring the timetable (b) doing only easy bits (c) keeping spare days (d) no spare time
- 9.✂️ Your team must make 6 paper flowers in 3 days, the same number each day. How many paper flowers a day?
- 10.True or false: “using a simple timetable” is poor project planning. (a) False (b) True
- 11.⏰ You start at 4:30 PM. Homework takes 45 minutes, then project work takes 20 minutes. When will you finish? (a) 5:15 PM (b) 4:50 PM (c) 5:50 PM (d) 5:35 PM
- 12.⏰ You start at 4:45 PM. Homework takes 35 minutes, then project work takes 15 minutes. When will you finish? (a) 5:50 PM (b) 5:35 PM (c) 5:20 PM (d) 5:00 PM
- 13.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
- 14.📅 Your school play is due in 11 days. Research takes 3 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 15.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
- 16.✅ What is a mini-deadline? (a) a date for one step (b) a late fine (c) the final due date (d) a holiday
- 17.✂️ Your team must make 30 thank-you cards in 6 days, the same number each day. How many thank-you cards a day?
- 18.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
- 19.📅 Your science model is due in 6 days. Research takes 1 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 20.✂️ Your team must make 14 paper flowers in 2 days, the same number each day. How many paper flowers a day?
- 21.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
- 22.Which of these is good project planning? (a) keeping spare days (b) ignoring the timetable (c) no task list (d) doing only easy bits
- 23.🔍 Which is the odd one out? (a) no task list (b) guessing how long (c) doing only easy bits (d) using a simple timetable
- 24.Which of these is good project planning? (a) listing tasks first (b) one huge deadline (c) starting on the last day (d) no spare time
- 25.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 26.🔍 Which is the odd one out? (a) using a simple timetable (b) breaking work into steps (c) listing tasks first (d) starting on the last day
- 27.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) there is no need (c) to start late (d) for surprises
- 28.🔍 Which is the odd one out? (a) setting mini-deadlines (b) no task list (c) starting on the last day (d) one huge deadline
- 29.🔍 Which is the odd one out? (a) starting early (b) one huge deadline (c) guessing how long (d) starting on the last day
- 30.True or false: “starting early” is poor project planning. (a) True (b) False
- 31.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
- 32.Which of these is poor project planning? (a) breaking work into steps (b) setting mini-deadlines (c) guessing how long (d) keeping spare days
- 33.Which of these is poor project planning? (a) breaking work into steps (b) listing tasks first (c) starting early (d) no task list
- 34.True or false: “no task list” is poor project planning. (a) False (b) True
- 35.Which of these is poor project planning? (a) no spare time (b) hard part first (c) keeping spare days (d) starting early
- 36.Which of these is good project planning? (a) one huge deadline (b) starting on the last day (c) hard part first (d) no task list
- 37.True or false: “ignoring the timetable” is good project planning. (a) True (b) False
- 38.🔍 Which is the odd one out? (a) using a simple timetable (b) guessing how long (c) listing tasks first (d) setting mini-deadlines
- 39.📅 Your history chart is due in 13 days. Research takes 3 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
- 40.Which of these is good project planning? (a) one huge deadline (b) setting mini-deadlines (c) forgetting the due date (d) no task list
Answer key
- poor planning
- breaking work into steps
- poor planning
- good planning
- 7
- break it into steps
- good planning
- keeping spare days
- 2
- False
- 5:35 PM
- 5:35 PM
- poor planning
- 4
- poor planning
- a date for one step
- 5
- poor planning
- 2
- 7
- good planning
- keeping spare days
- using a simple timetable
- listing tasks first
- poor planning
- starting on the last day
- for surprises
- setting mini-deadlines
- starting early
- False
- good planning
- guessing how long
- no task list
- True
- no spare time
- hard part first
- False
- guessing how long
- 5
- setting mini-deadlines
Free leadership lessons, practice and worksheets at talentjr.in/leadership-skills-for-students