Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) this week (c) in the third week (d) the night before
- 2.True or false: “using a simple timetable” is poor project planning. (a) False (b) True
- 3.📅 Your eco-club poster is due in 11 days. Research takes 1 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
- 4.🔍 Which is the odd one out? (a) breaking work into steps (b) hard part first (c) ignoring the timetable (d) setting mini-deadlines
- 5.📅 Your class magazine is due in 6 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 6.True or false: “forgetting the due date” is poor project planning. (a) True (b) False
- 7.Which of these is good project planning? (a) doing only easy bits (b) breaking work into steps (c) no spare time (d) starting on the last day
- 8.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 9.Which of these is good project planning? (a) no spare time (b) forgetting the due date (c) ignoring the timetable (d) starting early
- 10.🔍 Which is the odd one out? (a) using a simple timetable (b) hard part first (c) starting on the last day (d) starting early
- 11.📅 Your class magazine is due in 10 days. Research takes 3 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 12.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
- 13.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 14.🔍 Which is the odd one out? (a) one huge deadline (b) starting on the last day (c) breaking work into steps (d) no task list
- 15.Which of these is poor project planning? (a) using a simple timetable (b) no spare time (c) listing tasks first (d) setting mini-deadlines
- 16.📅 Your school play is due in 12 days. Research takes 3 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
- 17.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) break it into steps (c) give up (d) wait for help
- 18.✅ What is a mini-deadline? (a) a date for one step (b) the final due date (c) a late fine (d) a holiday
- 19.🔍 Which is the odd one out? (a) no spare time (b) starting on the last day (c) no task list (d) listing tasks first
- 20.Which of these is good project planning? (a) starting on the last day (b) one huge deadline (c) guessing how long (d) keeping spare days
- 21.True or false: “guessing how long” is good project planning. (a) False (b) True
- 22.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
- 23.True or false: “guessing how long” is poor project planning. (a) False (b) True
- 24.🔍 Which is the odd one out? (a) listing tasks first (b) hard part first (c) guessing how long (d) using a simple timetable
- 25.🔍 Which is the odd one out? (a) ignoring the timetable (b) keeping spare days (c) forgetting the due date (d) starting on the last day
- 26.True or false: “ignoring the timetable” is good project planning. (a) True (b) False
- 27.True or false: “setting mini-deadlines” is poor project planning. (a) False (b) True
- 28.Which of these is good project planning? (a) forgetting the due date (b) no task list (c) listing tasks first (d) starting on the last day
- 29.Which of these is poor project planning? (a) listing tasks first (b) starting early (c) breaking work into steps (d) doing only easy bits
- 30.⏰ You start at 4:15 PM. Homework takes 40 minutes, then project work takes 40 minutes. When will you finish? (a) 4:55 PM (b) 5:35 PM (c) 5:50 PM
- 31.True or false: “keeping spare days” is good project planning. (a) True (b) False
- 32.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 33.True or false: “keeping spare days” is poor project planning. (a) True (b) False
- 34.🔍 Which is the odd one out? (a) starting on the last day (b) doing only easy bits (c) setting mini-deadlines (d) no spare time
- 35.Which of these is good project planning? (a) hard part first (b) ignoring the timetable (c) doing only easy bits (d) starting on the last day
- 36.📅 Your science model is due in 13 days. Research takes 4 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
- 37.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to rest only (c) for surprises (d) to start late
- 38.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) play first (c) make the poster (d) neither
- 39.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 40.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
Answer key
- this week
- False
- 3
- ignoring the timetable
- 1
- True
- breaking work into steps
- good planning
- starting early
- starting on the last day
- 4
- poor planning
- poor planning
- breaking work into steps
- no spare time
- 3
- break it into steps
- a date for one step
- listing tasks first
- keeping spare days
- False
- good planning
- True
- guessing how long
- keeping spare days
- False
- False
- listing tasks first
- doing only easy bits
- 5:35 PM
- True
- good planning
- False
- setting mini-deadlines
- hard part first
- 3
- for surprises
- study for the test
- poor planning
- poor planning
Free leadership lessons, practice and worksheets at talentjr.in/leadership-skills-for-students