Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.⏳ Why keep a spare day or two before the deadline? (a) to start late (b) there is no need (c) for surprises (d) to rest only
- 2.🔍 Which is the odd one out? (a) hard part first (b) no spare time (c) keeping spare days (d) breaking work into steps
- 3.⏰ You start at 5:15 PM. Homework takes 25 minutes, then project work takes 15 minutes. When will you finish? (a) 5:55 PM (b) 5:40 PM (c) 6:10 PM (d) 5:30 PM
- 4.Which of these is good project planning? (a) no task list (b) forgetting the due date (c) keeping spare days (d) guessing how long
- 5.⏰ You start at 4:30 PM. Homework takes 20 minutes, then project work takes 35 minutes. When will you finish? (a) 5:05 PM (b) 4:50 PM (c) 5:25 PM (d) 5:40 PM
- 6.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) the night before (c) after it is due (d) this week
- 7.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 8.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 9.Which of these is good project planning? (a) one huge deadline (b) no spare time (c) setting mini-deadlines (d) no task list
- 10.✂️ Your team must make 16 name badges in 4 days, the same number each day. How many name badges a day?
- 11.🔍 Which is the odd one out? (a) hard part first (b) doing only easy bits (c) starting early (d) listing tasks first
- 12.🔍 Which is the odd one out? (a) forgetting the due date (b) keeping spare days (c) guessing how long (d) ignoring the timetable
- 13.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
- 14.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
- 15.🔍 Which is the odd one out? (a) ignoring the timetable (b) using a simple timetable (c) doing only easy bits (d) forgetting the due date
- 16.⏰ You start at 3:30 PM. Homework takes 25 minutes, then project work takes 15 minutes. When will you finish? (a) 4:25 PM (b) 3:45 PM (c) 4:10 PM (d) 3:55 PM
- 17.📅 Your school play is due in 11 days. Research takes 1 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 18.✂️ Your team must make 54 name badges in 6 days, the same number each day. How many name badges a day?
- 19.✅ What is a mini-deadline? (a) the final due date (b) a late fine (c) a holiday (d) a date for one step
- 20.⏰ You start at 5:30 PM. Homework takes 40 minutes, then project work takes 40 minutes. When will you finish? (a) 7:05 PM (b) 6:10 PM (c) 6:50 PM
- 21.True or false: “one huge deadline” is good project planning. (a) True (b) False
- 22.🔍 Which is the odd one out? (a) starting early (b) keeping spare days (c) listing tasks first (d) one huge deadline
- 23.True or false: “guessing how long” is poor project planning. (a) True (b) False
- 24.✂️ Your team must make 18 posters in 6 days, the same number each day. How many posters a day?
- 25.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
- 26.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) study for the test (c) play first (d) make the poster
- 27.📅 Your class magazine is due in 10 days. Research takes 4 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 28.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 29.Which of these is poor project planning? (a) setting mini-deadlines (b) ignoring the timetable (c) checking progress weekly (d) breaking work into steps
- 30.True or false: “doing only easy bits” is good project planning. (a) True (b) False
- 31.Which of these is poor project planning? (a) listing tasks first (b) setting mini-deadlines (c) keeping spare days (d) doing only easy bits
- 32.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
- 33.True or false: “no task list” is good project planning. (a) True (b) False
- 34.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
- 35.True or false: “setting mini-deadlines” is poor project planning. (a) True (b) False
- 36.🔍 Which is the odd one out? (a) doing only easy bits (b) guessing how long (c) breaking work into steps (d) one huge deadline
- 37.📅 Good or poor project planning: one huge deadline? (a) poor planning (b) good planning
- 38.True or false: “listing tasks first” is poor project planning. (a) False (b) True
- 39.📅 Your science model is due in 11 days. Research takes 2 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 40.📅 Your art display is due in 14 days. Research takes 2 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
Answer key
- for surprises
- no spare time
- 5:55 PM
- keeping spare days
- 5:25 PM
- this week
- good planning
- poor planning
- setting mini-deadlines
- 4
- doing only easy bits
- keeping spare days
- poor planning
- good planning
- using a simple timetable
- 4:10 PM
- 4
- 9
- a date for one step
- 6:50 PM
- False
- one huge deadline
- True
- 3
- good planning
- study for the test
- 2
- good planning
- ignoring the timetable
- False
- doing only easy bits
- good planning
- False
- poor planning
- False
- breaking work into steps
- poor planning
- False
- 3
- 4