Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.✅ What is a mini-deadline? (a) a date for one step (b) a holiday (c) the final due date (d) a late fine
- 2.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
- 3.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 4.📅 Your eco-club poster is due in 13 days. Research takes 4 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 5.Which of these is good project planning? (a) no spare time (b) starting on the last day (c) checking progress weekly (d) no task list
- 6.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 7.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) in the third week (c) the night before (d) after it is due
- 8.⏰ You start at 4:15 PM. Homework takes 20 minutes, then project work takes 20 minutes. When will you finish? (a) 4:35 PM (b) 5:10 PM (c) 4:55 PM
- 9.🔍 Which is the odd one out? (a) ignoring the timetable (b) using a simple timetable (c) forgetting the due date (d) starting on the last day
- 10.✂️ Your team must make 10 paper flowers in 2 days, the same number each day. How many paper flowers a day?
- 11.Which of these is poor project planning? (a) guessing how long (b) listing tasks first (c) setting mini-deadlines (d) keeping spare days
- 12.🔍 Which is the odd one out? (a) setting mini-deadlines (b) starting on the last day (c) breaking work into steps (d) starting early
- 13.True or false: “one huge deadline” is good project planning. (a) False (b) True
- 14.True or false: “guessing how long” is good project planning. (a) True (b) False
- 15.Which of these is good project planning? (a) forgetting the due date (b) starting early (c) no task list (d) starting on the last day
- 16.True or false: “doing only easy bits” is poor project planning. (a) True (b) False
- 17.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
- 18.True or false: “listing tasks first” is poor project planning. (a) False (b) True
- 19.Which of these is good project planning? (a) no task list (b) one huge deadline (c) setting mini-deadlines (d) ignoring the timetable
- 20.🔍 Which is the odd one out? (a) listing tasks first (b) one huge deadline (c) breaking work into steps (d) using a simple timetable
- 21.🔍 Which is the odd one out? (a) keeping spare days (b) using a simple timetable (c) guessing how long (d) checking progress weekly
- 22.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
- 23.Which of these is good project planning? (a) one huge deadline (b) doing only easy bits (c) using a simple timetable (d) starting on the last day
- 24.📅 Good or poor project planning: using a simple timetable? (a) poor planning (b) good planning
- 25.🔍 Which is the odd one out? (a) breaking work into steps (b) setting mini-deadlines (c) starting early (d) no task list
- 26.Which of these is poor project planning? (a) breaking work into steps (b) setting mini-deadlines (c) keeping spare days (d) starting on the last day
- 27.True or false: “guessing how long” is poor project planning. (a) False (b) True
- 28.✂️ Your team must make 27 thank-you cards in 3 days, the same number each day. How many thank-you cards a day?
- 29.Which of these is good project planning? (a) guessing how long (b) starting on the last day (c) forgetting the due date (d) hard part first
- 30.✂️ Your team must make 45 bookmarks in 5 days, the same number each day. How many bookmarks a day?
- 31.Which of these is good project planning? (a) starting on the last day (b) forgetting the due date (c) keeping spare days (d) doing only easy bits
- 32.True or false: “keeping spare days” is poor project planning. (a) True (b) False
- 33.Which of these is poor project planning? (a) starting early (b) ignoring the timetable (c) breaking work into steps (d) setting mini-deadlines
- 34.⏰ You start at 4:00 PM. Homework takes 20 minutes, then project work takes 25 minutes. When will you finish? (a) 4:25 PM (b) 4:45 PM (c) 5:00 PM (d) 4:20 PM
- 35.✂️ Your team must make 42 bookmarks in 6 days, the same number each day. How many bookmarks a day?
- 36.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 37.✂️ Your team must make 28 name badges in 4 days, the same number each day. How many name badges a day?
- 38.🔍 Which is the odd one out? (a) hard part first (b) setting mini-deadlines (c) forgetting the due date (d) checking progress weekly
- 39.Which of these is poor project planning? (a) doing only easy bits (b) hard part first (c) listing tasks first (d) starting early
- 40.True or false: “starting on the last day” is poor project planning. (a) True (b) False
Answer key
- a date for one step
- good planning
- poor planning
- 2
- checking progress weekly
- poor planning
- this week
- 4:55 PM
- using a simple timetable
- 5
- guessing how long
- starting on the last day
- False
- False
- starting early
- True
- good planning
- False
- setting mini-deadlines
- one huge deadline
- guessing how long
- poor planning
- using a simple timetable
- good planning
- no task list
- starting on the last day
- True
- 9
- hard part first
- 9
- keeping spare days
- False
- ignoring the timetable
- 4:45 PM
- 7
- good planning
- 7
- forgetting the due date
- doing only easy bits
- True