Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.Which of these is poor project planning? (a) starting on the last day (b) breaking work into steps (c) setting mini-deadlines (d) starting early
- 2.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
- 3.True or false: “guessing how long” is poor project planning. (a) True (b) False
- 4.True or false: “starting on the last day” is good project planning. (a) True (b) False
- 5.Which of these is good project planning? (a) forgetting the due date (b) no task list (c) guessing how long (d) setting mini-deadlines
- 6.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
- 7.Which of these is good project planning? (a) guessing how long (b) starting on the last day (c) forgetting the due date (d) listing tasks first
- 8.🧩 A big project feels scary. What should you do first? (a) break it into steps (b) wait for help (c) give up (d) do it all at once
- 9.📅 Your science model is due in 11 days. Research takes 3 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
- 10.Which of these is poor project planning? (a) ignoring the timetable (b) setting mini-deadlines (c) breaking work into steps (d) keeping spare days
- 11.Which of these is poor project planning? (a) forgetting the due date (b) breaking work into steps (c) checking progress weekly (d) keeping spare days
- 12.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
- 13.🔍 Which is the odd one out? (a) breaking work into steps (b) guessing how long (c) starting early (d) using a simple timetable
- 14.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
- 15.🔍 Which is the odd one out? (a) forgetting the due date (b) doing only easy bits (c) using a simple timetable (d) guessing how long
- 16.🗓️ Your project is due in three weeks. When should you start? (a) the night before (b) in the third week (c) after it is due (d) this week
- 17.True or false: “forgetting the due date” is poor project planning. (a) True (b) False
- 18.True or false: “breaking work into steps” is poor project planning. (a) False (b) True
- 19.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
- 20.True or false: “checking progress weekly” is good project planning. (a) False (b) True
- 21.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) play first (c) make the poster (d) neither
- 22.⏰ You start at 4:30 PM. Homework takes 25 minutes, then project work takes 25 minutes. When will you finish? (a) 4:55 PM (b) 5:20 PM (c) 5:35 PM
- 23.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
- 24.Which of these is poor project planning? (a) setting mini-deadlines (b) doing only easy bits (c) using a simple timetable (d) starting early
- 25.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 26.📅 Your art display is due in 12 days. Research takes 3 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
- 27.✂️ Your team must make 6 posters in 3 days, the same number each day. How many posters a day?
- 28.Which of these is good project planning? (a) no task list (b) breaking work into steps (c) one huge deadline (d) no spare time
- 29.⏰ You start at 3:30 PM. Homework takes 40 minutes, then project work takes 25 minutes. When will you finish? (a) 3:55 PM (b) 4:10 PM (c) 4:35 PM (d) 4:50 PM
- 30.⏰ You start at 4:15 PM. Homework takes 45 minutes, then project work takes 40 minutes. When will you finish? (a) 5:00 PM (b) 5:40 PM (c) 4:55 PM (d) 5:55 PM
- 31.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) there is no need (c) to start late (d) for surprises
- 32.📅 Your class magazine is due in 14 days. Research takes 3 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 33.🔍 Which is the odd one out? (a) breaking work into steps (b) setting mini-deadlines (c) no spare time (d) keeping spare days
- 34.True or false: “guessing how long” is good project planning. (a) False (b) True
- 35.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
- 36.📅 Your art display is due in 11 days. Research takes 1 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
- 37.🔍 Which is the odd one out? (a) using a simple timetable (b) setting mini-deadlines (c) forgetting the due date (d) keeping spare days
- 38.📅 Your eco-club poster is due in 11 days. Research takes 3 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
- 39.Which of these is good project planning? (a) one huge deadline (b) guessing how long (c) starting on the last day (d) checking progress weekly
- 40.✅ What is a mini-deadline? (a) the final due date (b) a holiday (c) a late fine (d) a date for one step
Answer key
- starting on the last day
- good planning
- True
- False
- setting mini-deadlines
- good planning
- listing tasks first
- break it into steps
- 1
- ignoring the timetable
- forgetting the due date
- poor planning
- guessing how long
- good planning
- using a simple timetable
- this week
- True
- False
- poor planning
- True
- study for the test
- 5:20 PM
- good planning
- doing only easy bits
- poor planning
- 1
- 2
- breaking work into steps
- 4:35 PM
- 5:40 PM
- for surprises
- 5
- no spare time
- False
- poor planning
- 2
- forgetting the due date
- 3
- checking progress weekly
- a date for one step
Free leadership lessons, practice and worksheets at talentjr.in/leadership-skills-for-students