Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
- 2.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
- 3.Which of these is good project planning? (a) guessing how long (b) doing only easy bits (c) listing tasks first (d) starting on the last day
- 4.📅 Good or poor project planning: one huge deadline? (a) poor planning (b) good planning
- 5.📅 Your art display is due in 8 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 6.Which of these is poor project planning? (a) listing tasks first (b) checking progress weekly (c) starting early (d) doing only easy bits
- 7.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
- 8.Which of these is poor project planning? (a) ignoring the timetable (b) checking progress weekly (c) hard part first (d) setting mini-deadlines
- 9.True or false: “using a simple timetable” is poor project planning. (a) False (b) True
- 10.Which of these is poor project planning? (a) checking progress weekly (b) keeping spare days (c) starting on the last day (d) listing tasks first
- 11.✂️ Your team must make 14 posters in 2 days, the same number each day. How many posters a day?
- 12.📅 Your science model is due in 16 days. Research takes 4 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 13.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
- 14.True or false: “hard part first” is poor project planning. (a) False (b) True
- 15.True or false: “checking progress weekly” is poor project planning. (a) True (b) False
- 16.True or false: “no spare time” is good project planning. (a) True (b) False
- 17.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
- 18.Which of these is poor project planning? (a) starting early (b) checking progress weekly (c) setting mini-deadlines (d) no spare time
- 19.🔍 Which is the odd one out? (a) starting on the last day (b) hard part first (c) doing only easy bits (d) no task list
- 20.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 21.📅 Your school play is due in 13 days. Research takes 1 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 22.Which of these is good project planning? (a) ignoring the timetable (b) setting mini-deadlines (c) doing only easy bits (d) one huge deadline
- 23.⏰ You start at 3:15 PM. Homework takes 30 minutes, then project work takes 35 minutes. When will you finish? (a) 4:35 PM (b) 3:50 PM (c) 4:20 PM (d) 3:45 PM
- 24.🧩 A big project feels scary. What should you do first? (a) give up (b) wait for help (c) break it into steps (d) do it all at once
- 25.Which of these is good project planning? (a) guessing how long (b) no spare time (c) no task list (d) breaking work into steps
- 26.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
- 27.🗓️ Your project is due in three weeks. When should you start? (a) the night before (b) after it is due (c) in the third week (d) this week
- 28.📅 Your maths exhibit is due in 11 days. Research takes 1 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 29.🔍 Which is the odd one out? (a) forgetting the due date (b) ignoring the timetable (c) no task list (d) breaking work into steps
- 30.🔍 Which is the odd one out? (a) listing tasks first (b) keeping spare days (c) no spare time (d) hard part first
- 31.Which of these is good project planning? (a) no spare time (b) guessing how long (c) doing only easy bits (d) hard part first
- 32.🔍 Which is the odd one out? (a) starting early (b) hard part first (c) using a simple timetable (d) doing only easy bits
- 33.🔍 Which is the odd one out? (a) starting on the last day (b) hard part first (c) checking progress weekly (d) starting early
- 34.Which of these is good project planning? (a) guessing how long (b) no task list (c) using a simple timetable (d) forgetting the due date
- 35.📅 Your school play is due in 8 days. Research takes 2 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 36.✂️ Your team must make 10 name badges in 5 days, the same number each day. How many name badges a day?
- 37.Which of these is good project planning? (a) ignoring the timetable (b) starting on the last day (c) doing only easy bits (d) keeping spare days
- 38.📅 Your maths exhibit is due in 7 days. Research takes 2 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 39.True or false: “setting mini-deadlines” is good project planning. (a) False (b) True
- 40.✂️ Your team must make 25 posters in 5 days, the same number each day. How many posters a day?
Answer key
- good planning
- poor planning
- listing tasks first
- poor planning
- 3
- doing only easy bits
- good planning
- ignoring the timetable
- False
- starting on the last day
- 7
- 5
- good planning
- False
- False
- False
- good planning
- no spare time
- hard part first
- poor planning
- 5
- setting mini-deadlines
- 4:20 PM
- break it into steps
- breaking work into steps
- poor planning
- this week
- 4
- breaking work into steps
- no spare time
- hard part first
- doing only easy bits
- starting on the last day
- using a simple timetable
- 2
- 2
- keeping spare days
- 2
- True
- 5