Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 352 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
  2. 2.📅 Your maths exhibit is due in 9 days. Research takes 3 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
  3. 3.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
  4. 4.Which of these is good project planning? (a) guessing how long (b) doing only easy bits (c) ignoring the timetable (d) hard part first
  5. 5.🔍 Which is the odd one out? (a) keeping spare days (b) starting early (c) setting mini-deadlines (d) forgetting the due date
  6. 6.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) play first (c) make the poster (d) neither
  7. 7.🔍 Which is the odd one out? (a) doing only easy bits (b) starting on the last day (c) guessing how long (d) hard part first
  8. 8.⏰ You start at 4:30 PM. Homework takes 35 minutes, then project work takes 15 minutes. When will you finish? (a) 5:05 PM (b) 5:35 PM (c) 4:45 PM (d) 5:20 PM
  9. 9.Which of these is good project planning? (a) one huge deadline (b) doing only easy bits (c) checking progress weekly (d) starting on the last day
  10. 10.✅ What is a mini-deadline? (a) a date for one step (b) a holiday (c) a late fine (d) the final due date
  11. 11.⏰ You start at 4:00 PM. Homework takes 30 minutes, then project work takes 30 minutes. When will you finish? (a) 4:30 PM (b) 5:00 PM (c) 5:15 PM
  12. 12.🔍 Which is the odd one out? (a) breaking work into steps (b) setting mini-deadlines (c) ignoring the timetable (d) hard part first
  13. 13.True or false: “doing only easy bits” is good project planning. (a) True (b) False
  14. 14.🔍 Which is the odd one out? (a) hard part first (b) checking progress weekly (c) using a simple timetable (d) no task list
  15. 15.✂️ Your team must make 20 thank-you cards in 4 days, the same number each day. How many thank-you cards a day?
  16. 16.Which of these is good project planning? (a) no task list (b) doing only easy bits (c) starting early (d) one huge deadline
  17. 17.True or false: “guessing how long” is good project planning. (a) True (b) False
  18. 18.✂️ Your team must make 12 posters in 3 days, the same number each day. How many posters a day?
  19. 19.🔍 Which is the odd one out? (a) one huge deadline (b) using a simple timetable (c) breaking work into steps (d) setting mini-deadlines
  20. 20.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
  21. 21.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
  22. 22.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
  23. 23.True or false: “listing tasks first” is poor project planning. (a) True (b) False
  24. 24.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
  25. 25.⏰ You start at 3:45 PM. Homework takes 40 minutes, then project work takes 15 minutes. When will you finish? (a) 4:55 PM (b) 4:40 PM (c) 4:25 PM (d) 4:00 PM
  26. 26.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to rest only (c) to start late (d) for surprises
  27. 27.🔍 Which is the odd one out? (a) no task list (b) ignoring the timetable (c) starting on the last day (d) using a simple timetable
  28. 28.Which of these is poor project planning? (a) forgetting the due date (b) using a simple timetable (c) keeping spare days (d) setting mini-deadlines
  29. 29.Which of these is good project planning? (a) forgetting the due date (b) ignoring the timetable (c) starting on the last day (d) keeping spare days
  30. 30.🔍 Which is the odd one out? (a) listing tasks first (b) one huge deadline (c) no task list (d) guessing how long
  31. 31.Which of these is good project planning? (a) setting mini-deadlines (b) doing only easy bits (c) forgetting the due date (d) starting on the last day
  32. 32.📅 Your maths exhibit is due in 12 days. Research takes 1 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
  33. 33.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) give up (c) wait for help (d) break it into steps
  34. 34.True or false: “starting on the last day” is good project planning. (a) True (b) False
  35. 35.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
  36. 36.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
  37. 37.True or false: “one huge deadline” is good project planning. (a) False (b) True
  38. 38.⏰ You start at 3:45 PM. Homework takes 20 minutes, then project work takes 15 minutes. When will you finish? (a) 4:00 PM (b) 4:20 PM (c) 4:35 PM (d) 4:05 PM
  39. 39.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
  40. 40.Which of these is good project planning? (a) forgetting the due date (b) doing only easy bits (c) using a simple timetable (d) guessing how long

Answer key

  1. good planning
  2. 2
  3. good planning
  4. hard part first
  5. forgetting the due date
  6. study for the test
  7. hard part first
  8. 5:20 PM
  9. checking progress weekly
  10. a date for one step
  11. 5:00 PM
  12. ignoring the timetable
  13. False
  14. no task list
  15. 5
  16. starting early
  17. False
  18. 4
  19. one huge deadline
  20. poor planning
  21. good planning
  22. poor planning
  23. False
  24. poor planning
  25. 4:40 PM
  26. for surprises
  27. using a simple timetable
  28. forgetting the due date
  29. keeping spare days
  30. listing tasks first
  31. setting mini-deadlines
  32. 5
  33. break it into steps
  34. False
  35. poor planning
  36. poor planning
  37. False
  38. 4:20 PM
  39. good planning
  40. using a simple timetable