Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 358 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
  2. 2.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
  3. 3.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
  4. 4.📅 Your class magazine is due in 12 days. Research takes 4 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
  5. 5.Which of these is poor project planning? (a) setting mini-deadlines (b) hard part first (c) one huge deadline (d) starting early
  6. 6.✂️ Your team must make 27 paper flowers in 3 days, the same number each day. How many paper flowers a day?
  7. 7.🔍 Which is the odd one out? (a) guessing how long (b) listing tasks first (c) forgetting the due date (d) doing only easy bits
  8. 8.⏰ You start at 5:45 PM. Homework takes 20 minutes, then project work takes 30 minutes. When will you finish? (a) 6:05 PM (b) 6:35 PM (c) 6:15 PM (d) 6:50 PM
  9. 9.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
  10. 10.🔍 Which is the odd one out? (a) setting mini-deadlines (b) hard part first (c) one huge deadline (d) listing tasks first
  11. 11.Which of these is good project planning? (a) no task list (b) doing only easy bits (c) guessing how long (d) hard part first
  12. 12.✅ What is a mini-deadline? (a) a date for one step (b) a holiday (c) the final due date (d) a late fine
  13. 13.🔍 Which is the odd one out? (a) listing tasks first (b) no task list (c) starting early (d) hard part first
  14. 14.True or false: “one huge deadline” is good project planning. (a) False (b) True
  15. 15.Which of these is good project planning? (a) no spare time (b) listing tasks first (c) starting on the last day (d) forgetting the due date
  16. 16.Which of these is good project planning? (a) forgetting the due date (b) starting on the last day (c) ignoring the timetable (d) checking progress weekly
  17. 17.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
  18. 18.⏰ You start at 4:30 PM. Homework takes 40 minutes, then project work takes 30 minutes. When will you finish? (a) 5:10 PM (b) 5:40 PM (c) 5:00 PM (d) 5:55 PM
  19. 19.🔍 Which is the odd one out? (a) starting on the last day (b) breaking work into steps (c) guessing how long (d) one huge deadline
  20. 20.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) study for the test (c) make the poster (d) neither
  21. 21.True or false: “ignoring the timetable” is poor project planning. (a) True (b) False
  22. 22.🔍 Which is the odd one out? (a) setting mini-deadlines (b) no spare time (c) using a simple timetable (d) keeping spare days
  23. 23.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) wait for help (c) break it into steps (d) give up
  24. 24.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to rest only (c) to start late (d) for surprises
  25. 25.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
  26. 26.True or false: “listing tasks first” is poor project planning. (a) False (b) True
  27. 27.True or false: “starting early” is good project planning. (a) False (b) True
  28. 28.🔍 Which is the odd one out? (a) setting mini-deadlines (b) guessing how long (c) breaking work into steps (d) listing tasks first
  29. 29.🔍 Which is the odd one out? (a) hard part first (b) listing tasks first (c) keeping spare days (d) doing only easy bits
  30. 30.Which of these is poor project planning? (a) listing tasks first (b) checking progress weekly (c) starting early (d) doing only easy bits
  31. 31.📅 Your art display is due in 10 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  32. 32.📅 Your maths exhibit is due in 12 days. Research takes 2 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
  33. 33.🔍 Which is the odd one out? (a) no task list (b) starting early (c) one huge deadline (d) guessing how long
  34. 34.True or false: “breaking work into steps” is good project planning. (a) False (b) True
  35. 35.True or false: “using a simple timetable” is poor project planning. (a) True (b) False
  36. 36.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
  37. 37.🔍 Which is the odd one out? (a) checking progress weekly (b) using a simple timetable (c) ignoring the timetable (d) breaking work into steps
  38. 38.Which of these is poor project planning? (a) hard part first (b) keeping spare days (c) setting mini-deadlines (d) ignoring the timetable
  39. 39.Which of these is poor project planning? (a) keeping spare days (b) hard part first (c) breaking work into steps (d) guessing how long
  40. 40.📅 Your maths exhibit is due in 9 days. Research takes 2 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?

Answer key

  1. poor planning
  2. good planning
  3. good planning
  4. 3
  5. one huge deadline
  6. 9
  7. listing tasks first
  8. 6:35 PM
  9. good planning
  10. one huge deadline
  11. hard part first
  12. a date for one step
  13. no task list
  14. False
  15. listing tasks first
  16. checking progress weekly
  17. good planning
  18. 5:40 PM
  19. breaking work into steps
  20. study for the test
  21. True
  22. no spare time
  23. break it into steps
  24. for surprises
  25. good planning
  26. False
  27. True
  28. guessing how long
  29. doing only easy bits
  30. doing only easy bits
  31. 3
  32. 5
  33. starting early
  34. True
  35. False
  36. poor planning
  37. ignoring the timetable
  38. ignoring the timetable
  39. guessing how long
  40. 2