Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 388 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Your school play is due in 10 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
  2. 2.True or false: “forgetting the due date” is poor project planning. (a) False (b) True
  3. 3.Which of these is poor project planning? (a) listing tasks first (b) guessing how long (c) setting mini-deadlines (d) breaking work into steps
  4. 4.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
  5. 5.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) study for the test (c) neither (d) make the poster
  6. 6.📅 Your maths exhibit is due in 8 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
  7. 7.🔍 Which is the odd one out? (a) breaking work into steps (b) using a simple timetable (c) no task list (d) hard part first
  8. 8.Which of these is good project planning? (a) doing only easy bits (b) breaking work into steps (c) ignoring the timetable (d) forgetting the due date
  9. 9.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
  10. 10.⏳ Why keep a spare day or two before the deadline? (a) to start late (b) for surprises (c) there is no need (d) to rest only
  11. 11.Which of these is good project planning? (a) doing only easy bits (b) no task list (c) guessing how long (d) hard part first
  12. 12.🔍 Which is the odd one out? (a) breaking work into steps (b) hard part first (c) listing tasks first (d) no spare time
  13. 13.🔍 Which is the odd one out? (a) ignoring the timetable (b) no spare time (c) breaking work into steps (d) guessing how long
  14. 14.Which of these is good project planning? (a) no task list (b) starting on the last day (c) using a simple timetable (d) no spare time
  15. 15.🔍 Which is the odd one out? (a) hard part first (b) starting early (c) checking progress weekly (d) guessing how long
  16. 16.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
  17. 17.Which of these is poor project planning? (a) using a simple timetable (b) checking progress weekly (c) one huge deadline (d) setting mini-deadlines
  18. 18.Which of these is poor project planning? (a) starting early (b) hard part first (c) setting mini-deadlines (d) no task list
  19. 19.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
  20. 20.✂️ Your team must make 24 thank-you cards in 3 days, the same number each day. How many thank-you cards a day?
  21. 21.🔍 Which is the odd one out? (a) doing only easy bits (b) setting mini-deadlines (c) ignoring the timetable (d) guessing how long
  22. 22.Which of these is good project planning? (a) forgetting the due date (b) no task list (c) guessing how long (d) listing tasks first
  23. 23.✅ What is a mini-deadline? (a) a late fine (b) a holiday (c) the final due date (d) a date for one step
  24. 24.True or false: “checking progress weekly” is poor project planning. (a) True (b) False
  25. 25.⏰ You start at 5:45 PM. Homework takes 40 minutes, then project work takes 35 minutes. When will you finish? (a) 7:00 PM (b) 6:20 PM (c) 7:15 PM (d) 6:25 PM
  26. 26.🔍 Which is the odd one out? (a) doing only easy bits (b) using a simple timetable (c) one huge deadline (d) no task list
  27. 27.🗓️ Your project is due in three weeks. When should you start? (a) the night before (b) in the third week (c) this week (d) after it is due
  28. 28.🔍 Which is the odd one out? (a) listing tasks first (b) one huge deadline (c) setting mini-deadlines (d) starting early
  29. 29.Which of these is good project planning? (a) forgetting the due date (b) starting on the last day (c) starting early (d) ignoring the timetable
  30. 30.True or false: “using a simple timetable” is good project planning. (a) False (b) True
  31. 31.🔍 Which is the odd one out? (a) starting early (b) setting mini-deadlines (c) using a simple timetable (d) ignoring the timetable
  32. 32.🔍 Which is the odd one out? (a) hard part first (b) setting mini-deadlines (c) starting on the last day (d) listing tasks first
  33. 33.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
  34. 34.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
  35. 35.True or false: “forgetting the due date” is good project planning. (a) True (b) False
  36. 36.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
  37. 37.Which of these is good project planning? (a) forgetting the due date (b) checking progress weekly (c) guessing how long (d) one huge deadline
  38. 38.📅 Your art display is due in 7 days. Research takes 1 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
  39. 39.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
  40. 40.True or false: “one huge deadline” is good project planning. (a) True (b) False

Answer key

  1. 5
  2. True
  3. guessing how long
  4. good planning
  5. study for the test
  6. 3
  7. no task list
  8. breaking work into steps
  9. good planning
  10. for surprises
  11. hard part first
  12. no spare time
  13. breaking work into steps
  14. using a simple timetable
  15. guessing how long
  16. poor planning
  17. one huge deadline
  18. no task list
  19. good planning
  20. 8
  21. setting mini-deadlines
  22. listing tasks first
  23. a date for one step
  24. False
  25. 7:00 PM
  26. using a simple timetable
  27. this week
  28. one huge deadline
  29. starting early
  30. True
  31. ignoring the timetable
  32. starting on the last day
  33. good planning
  34. good planning
  35. False
  36. poor planning
  37. checking progress weekly
  38. 1
  39. poor planning
  40. False