Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) the night before (c) this week (d) in the third week
- 2.⏰ You start at 4:00 PM. Homework takes 30 minutes, then project work takes 20 minutes. When will you finish? (a) 4:20 PM (b) 5:05 PM (c) 4:30 PM (d) 4:50 PM
- 3.📅 Your art display is due in 8 days. Research takes 3 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 4.🔍 Which is the odd one out? (a) starting early (b) setting mini-deadlines (c) listing tasks first (d) starting on the last day
- 5.📅 Your art display is due in 14 days. Research takes 4 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 6.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 7.✂️ Your team must make 15 thank-you cards in 5 days, the same number each day. How many thank-you cards a day?
- 8.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
- 9.Which of these is poor project planning? (a) setting mini-deadlines (b) keeping spare days (c) guessing how long (d) breaking work into steps
- 10.Which of these is good project planning? (a) no spare time (b) keeping spare days (c) one huge deadline (d) ignoring the timetable
- 11.True or false: “one huge deadline” is poor project planning. (a) False (b) True
- 12.✂️ Your team must make 21 thank-you cards in 3 days, the same number each day. How many thank-you cards a day?
- 13.True or false: “forgetting the due date” is good project planning. (a) False (b) True
- 14.True or false: “one huge deadline” is good project planning. (a) False (b) True
- 15.Which of these is good project planning? (a) starting on the last day (b) one huge deadline (c) checking progress weekly (d) ignoring the timetable
- 16.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
- 17.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
- 18.✂️ Your team must make 12 bookmarks in 2 days, the same number each day. How many bookmarks a day?
- 19.🔍 Which is the odd one out? (a) setting mini-deadlines (b) starting early (c) keeping spare days (d) no spare time
- 20.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
- 21.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 22.✂️ Your team must make 6 paper bags in 3 days, the same number each day. How many paper bags a day?
- 23.📅 Your maths exhibit is due in 11 days. Research takes 2 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 24.True or false: “no spare time” is good project planning. (a) True (b) False
- 25.✅ What is a mini-deadline? (a) a late fine (b) a date for one step (c) the final due date (d) a holiday
- 26.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
- 27.True or false: “setting mini-deadlines” is good project planning. (a) True (b) False
- 28.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 29.Which of these is good project planning? (a) guessing how long (b) starting on the last day (c) breaking work into steps (d) ignoring the timetable
- 30.🔍 Which is the odd one out? (a) starting on the last day (b) doing only easy bits (c) breaking work into steps (d) no spare time
- 31.📅 Your class magazine is due in 13 days. Research takes 4 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 32.Which of these is good project planning? (a) no task list (b) starting on the last day (c) no spare time (d) setting mini-deadlines
- 33.Which of these is poor project planning? (a) checking progress weekly (b) setting mini-deadlines (c) starting early (d) no spare time
- 34.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
- 35.📅 Your art display is due in 11 days. Research takes 2 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 36.⏳ Why keep a spare day or two before the deadline? (a) to start late (b) to rest only (c) there is no need (d) for surprises
- 37.📅 Good or poor project planning: using a simple timetable? (a) poor planning (b) good planning
- 38.Which of these is poor project planning? (a) no task list (b) keeping spare days (c) checking progress weekly (d) setting mini-deadlines
- 39.Which of these is good project planning? (a) starting on the last day (b) no spare time (c) guessing how long (d) using a simple timetable
- 40.🔍 Which is the odd one out? (a) keeping spare days (b) listing tasks first (c) guessing how long (d) breaking work into steps
Answer key
- this week
- 4:50 PM
- 1
- starting on the last day
- 4
- poor planning
- 3
- good planning
- guessing how long
- keeping spare days
- True
- 7
- False
- False
- checking progress weekly
- poor planning
- good planning
- 6
- no spare time
- good planning
- good planning
- 2
- 2
- False
- a date for one step
- poor planning
- True
- poor planning
- breaking work into steps
- breaking work into steps
- 5
- setting mini-deadlines
- no spare time
- good planning
- 3
- for surprises
- good planning
- no task list
- using a simple timetable
- guessing how long