Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 422 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.🔍 Which is the odd one out? (a) setting mini-deadlines (b) doing only easy bits (c) forgetting the due date (d) one huge deadline
  2. 2.📅 Your art display is due in 9 days. Research takes 3 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
  3. 3.📅 Your school play is due in 11 days. Research takes 2 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
  4. 4.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) study for the test (c) make the poster (d) neither
  5. 5.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
  6. 6.🔍 Which is the odd one out? (a) no task list (b) setting mini-deadlines (c) hard part first (d) breaking work into steps
  7. 7.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
  8. 8.Which of these is poor project planning? (a) breaking work into steps (b) starting on the last day (c) keeping spare days (d) checking progress weekly
  9. 9.🔍 Which is the odd one out? (a) checking progress weekly (b) keeping spare days (c) doing only easy bits (d) using a simple timetable
  10. 10.✂️ Your team must make 6 paper flowers in 3 days, the same number each day. How many paper flowers a day?
  11. 11.🔍 Which is the odd one out? (a) starting on the last day (b) doing only easy bits (c) one huge deadline (d) starting early
  12. 12.Which of these is poor project planning? (a) using a simple timetable (b) no spare time (c) keeping spare days (d) starting early
  13. 13.True or false: “starting early” is good project planning. (a) False (b) True
  14. 14.Which of these is good project planning? (a) doing only easy bits (b) listing tasks first (c) guessing how long (d) starting on the last day
  15. 15.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
  16. 16.✂️ Your team must make 25 posters in 5 days, the same number each day. How many posters a day?
  17. 17.Which of these is good project planning? (a) no task list (b) using a simple timetable (c) doing only easy bits (d) ignoring the timetable
  18. 18.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to start late (c) for surprises (d) to rest only
  19. 19.🧩 A big project feels scary. What should you do first? (a) wait for help (b) break it into steps (c) do it all at once (d) give up
  20. 20.True or false: “hard part first” is poor project planning. (a) True (b) False
  21. 21.📅 Your school play is due in 8 days. Research takes 1 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
  22. 22.True or false: “starting early” is poor project planning. (a) False (b) True
  23. 23.🔍 Which is the odd one out? (a) guessing how long (b) forgetting the due date (c) no task list (d) hard part first
  24. 24.True or false: “listing tasks first” is poor project planning. (a) True (b) False
  25. 25.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
  26. 26.✅ What is a mini-deadline? (a) the final due date (b) a date for one step (c) a late fine (d) a holiday
  27. 27.🔍 Which is the odd one out? (a) keeping spare days (b) starting early (c) setting mini-deadlines (d) ignoring the timetable
  28. 28.True or false: “checking progress weekly” is good project planning. (a) True (b) False
  29. 29.🔍 Which is the odd one out? (a) checking progress weekly (b) listing tasks first (c) starting on the last day (d) setting mini-deadlines
  30. 30.True or false: “checking progress weekly” is poor project planning. (a) False (b) True
  31. 31.🔍 Which is the odd one out? (a) using a simple timetable (b) forgetting the due date (c) listing tasks first (d) breaking work into steps
  32. 32.✂️ Your team must make 15 name badges in 3 days, the same number each day. How many name badges a day?
  33. 33.Which of these is poor project planning? (a) breaking work into steps (b) no task list (c) hard part first (d) setting mini-deadlines
  34. 34.⏰ You start at 5:45 PM. Homework takes 30 minutes, then project work takes 20 minutes. When will you finish? (a) 6:50 PM (b) 6:05 PM (c) 6:35 PM (d) 6:15 PM
  35. 35.Which of these is good project planning? (a) no task list (b) setting mini-deadlines (c) no spare time (d) forgetting the due date
  36. 36.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
  37. 37.🔍 Which is the odd one out? (a) breaking work into steps (b) keeping spare days (c) guessing how long (d) listing tasks first
  38. 38.🔍 Which is the odd one out? (a) ignoring the timetable (b) keeping spare days (c) starting on the last day (d) no task list
  39. 39.📅 Your art display is due in 8 days. Research takes 2 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
  40. 40.Which of these is poor project planning? (a) forgetting the due date (b) keeping spare days (c) starting early (d) using a simple timetable

Answer key

  1. setting mini-deadlines
  2. 1
  3. 4
  4. study for the test
  5. poor planning
  6. no task list
  7. good planning
  8. starting on the last day
  9. doing only easy bits
  10. 2
  11. starting early
  12. no spare time
  13. True
  14. listing tasks first
  15. poor planning
  16. 5
  17. using a simple timetable
  18. for surprises
  19. break it into steps
  20. False
  21. 3
  22. False
  23. hard part first
  24. False
  25. good planning
  26. a date for one step
  27. ignoring the timetable
  28. True
  29. starting on the last day
  30. False
  31. forgetting the due date
  32. 5
  33. no task list
  34. 6:35 PM
  35. setting mini-deadlines
  36. poor planning
  37. guessing how long
  38. keeping spare days
  39. 2
  40. forgetting the due date