Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Your maths exhibit is due in 7 days. Research takes 1 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
- 2.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
- 3.Which of these is good project planning? (a) starting on the last day (b) no task list (c) setting mini-deadlines (d) doing only easy bits
- 4.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
- 5.⏰ You start at 3:45 PM. Homework takes 25 minutes, then project work takes 35 minutes. When will you finish? (a) 5:00 PM (b) 4:20 PM (c) 4:45 PM (d) 4:10 PM
- 6.✅ What is a mini-deadline? (a) a late fine (b) a holiday (c) a date for one step (d) the final due date
- 7.🔍 Which is the odd one out? (a) listing tasks first (b) setting mini-deadlines (c) using a simple timetable (d) doing only easy bits
- 8.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
- 9.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) make the poster (c) play first (d) study for the test
- 10.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
- 11.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
- 12.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
- 13.True or false: “using a simple timetable” is poor project planning. (a) True (b) False
- 14.Which of these is good project planning? (a) doing only easy bits (b) ignoring the timetable (c) one huge deadline (d) checking progress weekly
- 15.True or false: “starting on the last day” is good project planning. (a) True (b) False
- 16.Which of these is poor project planning? (a) breaking work into steps (b) using a simple timetable (c) one huge deadline (d) keeping spare days
- 17.Which of these is good project planning? (a) no task list (b) forgetting the due date (c) listing tasks first (d) no spare time
- 18.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 19.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
- 20.Which of these is poor project planning? (a) hard part first (b) starting on the last day (c) breaking work into steps (d) checking progress weekly
- 21.🔍 Which is the odd one out? (a) hard part first (b) setting mini-deadlines (c) no task list (d) listing tasks first
- 22.True or false: “ignoring the timetable” is poor project planning. (a) True (b) False
- 23.True or false: “starting early” is poor project planning. (a) True (b) False
- 24.True or false: “one huge deadline” is poor project planning. (a) False (b) True
- 25.🔍 Which is the odd one out? (a) doing only easy bits (b) checking progress weekly (c) no task list (d) guessing how long
- 26.⏰ You start at 3:00 PM. Homework takes 45 minutes, then project work takes 20 minutes. When will you finish? (a) 3:45 PM (b) 4:20 PM (c) 3:20 PM (d) 4:05 PM
- 27.📅 Your eco-club poster is due in 10 days. Research takes 3 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 28.✂️ Your team must make 24 bookmarks in 4 days, the same number each day. How many bookmarks a day?
- 29.True or false: “checking progress weekly” is poor project planning. (a) False (b) True
- 30.⏰ You start at 4:00 PM. Homework takes 25 minutes, then project work takes 30 minutes. When will you finish? (a) 5:10 PM (b) 4:55 PM (c) 4:30 PM (d) 4:25 PM
- 31.✂️ Your team must make 30 posters in 6 days, the same number each day. How many posters a day?
- 32.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) this week (c) the night before (d) after it is due
- 33.True or false: “no spare time” is poor project planning. (a) True (b) False
- 34.🔍 Which is the odd one out? (a) no spare time (b) starting early (c) one huge deadline (d) starting on the last day
- 35.Which of these is good project planning? (a) forgetting the due date (b) no task list (c) no spare time (d) hard part first
- 36.Which of these is poor project planning? (a) forgetting the due date (b) listing tasks first (c) breaking work into steps (d) starting early
- 37.Which of these is poor project planning? (a) using a simple timetable (b) keeping spare days (c) doing only easy bits (d) hard part first
- 38.✂️ Your team must make 9 thank-you cards in 3 days, the same number each day. How many thank-you cards a day?
- 39.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) give up (c) wait for help (d) break it into steps
- 40.📅 Your maths exhibit is due in 13 days. Research takes 1 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
Answer key
- 1
- good planning
- setting mini-deadlines
- good planning
- 4:45 PM
- a date for one step
- doing only easy bits
- good planning
- study for the test
- poor planning
- poor planning
- poor planning
- False
- checking progress weekly
- False
- one huge deadline
- listing tasks first
- poor planning
- poor planning
- starting on the last day
- no task list
- True
- False
- True
- checking progress weekly
- 4:05 PM
- 3
- 6
- False
- 4:55 PM
- 5
- this week
- True
- starting early
- hard part first
- forgetting the due date
- doing only easy bits
- 3
- break it into steps
- 5