Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 440 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
  2. 2.🔍 Which is the odd one out? (a) hard part first (b) starting on the last day (c) doing only easy bits (d) no task list
  3. 3.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
  4. 4.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
  5. 5.🔍 Which is the odd one out? (a) starting early (b) one huge deadline (c) listing tasks first (d) setting mini-deadlines
  6. 6.True or false: “breaking work into steps” is good project planning. (a) True (b) False
  7. 7.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
  8. 8.✂️ Your team must make 42 thank-you cards in 6 days, the same number each day. How many thank-you cards a day?
  9. 9.📅 Your class magazine is due in 11 days. Research takes 1 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  10. 10.🔍 Which is the odd one out? (a) breaking work into steps (b) hard part first (c) checking progress weekly (d) doing only easy bits
  11. 11.True or false: “starting early” is good project planning. (a) False (b) True
  12. 12.Which of these is good project planning? (a) keeping spare days (b) doing only easy bits (c) starting on the last day (d) ignoring the timetable
  13. 13.Which of these is poor project planning? (a) no task list (b) using a simple timetable (c) hard part first (d) checking progress weekly
  14. 14.✂️ Your team must make 18 posters in 2 days, the same number each day. How many posters a day?
  15. 15.⏰ You start at 5:30 PM. Homework takes 20 minutes, then project work takes 40 minutes. When will you finish? (a) 5:50 PM (b) 6:45 PM (c) 6:30 PM (d) 6:10 PM
  16. 16.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) in the third week (c) after it is due (d) the night before
  17. 17.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) make the poster (c) play first (d) study for the test
  18. 18.Which of these is good project planning? (a) guessing how long (b) doing only easy bits (c) no spare time (d) listing tasks first
  19. 19.🔍 Which is the odd one out? (a) checking progress weekly (b) no spare time (c) guessing how long (d) ignoring the timetable
  20. 20.✂️ Your team must make 54 paper flowers in 6 days, the same number each day. How many paper flowers a day?
  21. 21.⏰ You start at 3:30 PM. Homework takes 25 minutes, then project work takes 25 minutes. When will you finish? (a) 4:20 PM (b) 4:35 PM (c) 3:55 PM
  22. 22.✂️ Your team must make 40 paper flowers in 5 days, the same number each day. How many paper flowers a day?
  23. 23.✂️ Your team must make 27 thank-you cards in 3 days, the same number each day. How many thank-you cards a day?
  24. 24.Which of these is good project planning? (a) forgetting the due date (b) no spare time (c) breaking work into steps (d) ignoring the timetable
  25. 25.🔍 Which is the odd one out? (a) starting early (b) keeping spare days (c) hard part first (d) starting on the last day
  26. 26.🔍 Which is the odd one out? (a) breaking work into steps (b) doing only easy bits (c) starting on the last day (d) forgetting the due date
  27. 27.Which of these is good project planning? (a) ignoring the timetable (b) starting early (c) no spare time (d) forgetting the due date
  28. 28.🧩 A big project feels scary. What should you do first? (a) give up (b) break it into steps (c) do it all at once (d) wait for help
  29. 29.⏰ You start at 3:00 PM. Homework takes 30 minutes, then project work takes 15 minutes. When will you finish? (a) 3:30 PM (b) 4:00 PM (c) 3:45 PM (d) 3:15 PM
  30. 30.✅ What is a mini-deadline? (a) a date for one step (b) a late fine (c) the final due date (d) a holiday
  31. 31.True or false: “using a simple timetable” is poor project planning. (a) False (b) True
  32. 32.📅 Good or poor project planning: guessing how long? (a) poor planning (b) good planning
  33. 33.📅 Your school play is due in 11 days. Research takes 1 days, making it takes 5 days and practice takes 3 days. How many spare days will you have?
  34. 34.🔍 Which is the odd one out? (a) starting on the last day (b) using a simple timetable (c) no task list (d) forgetting the due date
  35. 35.📅 Your class magazine is due in 13 days. Research takes 2 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
  36. 36.📅 Your eco-club poster is due in 6 days. Research takes 1 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
  37. 37.Which of these is poor project planning? (a) guessing how long (b) listing tasks first (c) starting early (d) hard part first
  38. 38.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
  39. 39.📅 Your class magazine is due in 13 days. Research takes 4 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
  40. 40.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning

Answer key

  1. good planning
  2. hard part first
  3. poor planning
  4. good planning
  5. one huge deadline
  6. True
  7. good planning
  8. 7
  9. 2
  10. doing only easy bits
  11. True
  12. keeping spare days
  13. no task list
  14. 9
  15. 6:30 PM
  16. this week
  17. study for the test
  18. listing tasks first
  19. checking progress weekly
  20. 9
  21. 4:20 PM
  22. 8
  23. 9
  24. breaking work into steps
  25. starting on the last day
  26. breaking work into steps
  27. starting early
  28. break it into steps
  29. 3:45 PM
  30. a date for one step
  31. False
  32. poor planning
  33. 2
  34. using a simple timetable
  35. 5
  36. 1
  37. guessing how long
  38. poor planning
  39. 5
  40. poor planning