Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 444 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.🔍 Which is the odd one out? (a) starting on the last day (b) ignoring the timetable (c) doing only easy bits (d) checking progress weekly
  2. 2.True or false: “starting on the last day” is poor project planning. (a) True (b) False
  3. 3.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
  4. 4.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
  5. 5.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) make the poster (c) play first (d) neither
  6. 6.🔍 Which is the odd one out? (a) ignoring the timetable (b) checking progress weekly (c) using a simple timetable (d) keeping spare days
  7. 7.Which of these is good project planning? (a) one huge deadline (b) forgetting the due date (c) hard part first (d) doing only easy bits
  8. 8.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
  9. 9.🔍 Which is the odd one out? (a) no task list (b) no spare time (c) using a simple timetable (d) ignoring the timetable
  10. 10.True or false: “doing only easy bits” is poor project planning. (a) False (b) True
  11. 11.🔍 Which is the odd one out? (a) starting early (b) doing only easy bits (c) checking progress weekly (d) breaking work into steps
  12. 12.✅ What is a mini-deadline? (a) the final due date (b) a late fine (c) a date for one step (d) a holiday
  13. 13.Which of these is poor project planning? (a) starting early (b) hard part first (c) setting mini-deadlines (d) no spare time
  14. 14.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
  15. 15.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
  16. 16.🔍 Which is the odd one out? (a) setting mini-deadlines (b) forgetting the due date (c) ignoring the timetable (d) guessing how long
  17. 17.🔍 Which is the odd one out? (a) hard part first (b) no spare time (c) starting early (d) keeping spare days
  18. 18.✂️ Your team must make 30 paper bags in 5 days, the same number each day. How many paper bags a day?
  19. 19.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
  20. 20.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
  21. 21.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
  22. 22.⏰ You start at 4:45 PM. Homework takes 25 minutes, then project work takes 15 minutes. When will you finish? (a) 5:00 PM (b) 5:10 PM (c) 5:25 PM (d) 5:40 PM
  23. 23.🧩 A big project feels scary. What should you do first? (a) wait for help (b) break it into steps (c) do it all at once (d) give up
  24. 24.Which of these is good project planning? (a) no spare time (b) starting early (c) forgetting the due date (d) doing only easy bits
  25. 25.🔍 Which is the odd one out? (a) guessing how long (b) listing tasks first (c) forgetting the due date (d) ignoring the timetable
  26. 26.Which of these is good project planning? (a) forgetting the due date (b) starting on the last day (c) setting mini-deadlines (d) no spare time
  27. 27.Which of these is poor project planning? (a) checking progress weekly (b) using a simple timetable (c) no task list (d) setting mini-deadlines
  28. 28.📅 Your school play is due in 9 days. Research takes 1 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
  29. 29.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
  30. 30.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) the night before (c) after it is due (d) in the third week
  31. 31.True or false: “guessing how long” is good project planning. (a) True (b) False
  32. 32.Which of these is poor project planning? (a) doing only easy bits (b) keeping spare days (c) hard part first (d) setting mini-deadlines
  33. 33.🔍 Which is the odd one out? (a) hard part first (b) breaking work into steps (c) starting on the last day (d) setting mini-deadlines
  34. 34.Which of these is good project planning? (a) starting on the last day (b) no spare time (c) no task list (d) keeping spare days
  35. 35.📅 Your eco-club poster is due in 11 days. Research takes 3 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
  36. 36.Which of these is poor project planning? (a) starting on the last day (b) starting early (c) setting mini-deadlines (d) checking progress weekly
  37. 37.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
  38. 38.🔍 Which is the odd one out? (a) setting mini-deadlines (b) breaking work into steps (c) listing tasks first (d) one huge deadline
  39. 39.Which of these is poor project planning? (a) setting mini-deadlines (b) keeping spare days (c) starting early (d) guessing how long
  40. 40.📅 Your class magazine is due in 14 days. Research takes 4 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?

Answer key

  1. checking progress weekly
  2. True
  3. good planning
  4. good planning
  5. study for the test
  6. ignoring the timetable
  7. hard part first
  8. poor planning
  9. using a simple timetable
  10. True
  11. doing only easy bits
  12. a date for one step
  13. no spare time
  14. poor planning
  15. good planning
  16. setting mini-deadlines
  17. no spare time
  18. 6
  19. good planning
  20. poor planning
  21. poor planning
  22. 5:25 PM
  23. break it into steps
  24. starting early
  25. listing tasks first
  26. setting mini-deadlines
  27. no task list
  28. 3
  29. poor planning
  30. this week
  31. False
  32. doing only easy bits
  33. starting on the last day
  34. keeping spare days
  35. 1
  36. starting on the last day
  37. poor planning
  38. one huge deadline
  39. guessing how long
  40. 3