Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) in the third week (c) the night before (d) after it is due
- 2.🔍 Which is the odd one out? (a) starting early (b) no task list (c) doing only easy bits (d) starting on the last day
- 3.Which of these is poor project planning? (a) checking progress weekly (b) listing tasks first (c) ignoring the timetable (d) setting mini-deadlines
- 4.True or false: “hard part first” is poor project planning. (a) False (b) True
- 5.✅ What is a mini-deadline? (a) a late fine (b) a holiday (c) the final due date (d) a date for one step
- 6.✂️ Your team must make 9 paper bags in 3 days, the same number each day. How many paper bags a day?
- 7.✂️ Your team must make 12 paper flowers in 3 days, the same number each day. How many paper flowers a day?
- 8.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 9.True or false: “checking progress weekly” is good project planning. (a) True (b) False
- 10.🧩 A big project feels scary. What should you do first? (a) wait for help (b) break it into steps (c) give up (d) do it all at once
- 11.📅 Your class magazine is due in 12 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 12.📅 Good or poor project planning: guessing how long? (a) poor planning (b) good planning
- 13.🔍 Which is the odd one out? (a) ignoring the timetable (b) keeping spare days (c) one huge deadline (d) guessing how long
- 14.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
- 15.Which of these is good project planning? (a) guessing how long (b) no spare time (c) doing only easy bits (d) starting early
- 16.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to start late (c) for surprises (d) to rest only
- 17.⏰ You start at 5:45 PM. Homework takes 45 minutes, then project work takes 30 minutes. When will you finish? (a) 6:15 PM (b) 7:15 PM (c) 6:30 PM (d) 7:00 PM
- 18.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
- 19.🔍 Which is the odd one out? (a) forgetting the due date (b) one huge deadline (c) doing only easy bits (d) listing tasks first
- 20.True or false: “listing tasks first” is good project planning. (a) True (b) False
- 21.✂️ Your team must make 40 thank-you cards in 5 days, the same number each day. How many thank-you cards a day?
- 22.🔍 Which is the odd one out? (a) starting on the last day (b) breaking work into steps (c) one huge deadline (d) no task list
- 23.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) play first (c) make the poster (d) neither
- 24.📅 Your history chart is due in 12 days. Research takes 3 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
- 25.True or false: “guessing how long” is poor project planning. (a) True (b) False
- 26.Which of these is good project planning? (a) listing tasks first (b) ignoring the timetable (c) forgetting the due date (d) doing only easy bits
- 27.True or false: “breaking work into steps” is poor project planning. (a) False (b) True
- 28.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 29.Which of these is good project planning? (a) keeping spare days (b) starting on the last day (c) guessing how long (d) no task list
- 30.🔍 Which is the odd one out? (a) breaking work into steps (b) using a simple timetable (c) no task list (d) listing tasks first
- 31.🔍 Which is the odd one out? (a) using a simple timetable (b) listing tasks first (c) setting mini-deadlines (d) starting on the last day
- 32.📅 Good or poor project planning: checking progress weekly? (a) good planning (b) poor planning
- 33.🔍 Which is the odd one out? (a) breaking work into steps (b) no spare time (c) using a simple timetable (d) keeping spare days
- 34.Which of these is good project planning? (a) one huge deadline (b) no spare time (c) using a simple timetable (d) no task list
- 35.🔍 Which is the odd one out? (a) starting early (b) breaking work into steps (c) forgetting the due date (d) hard part first
- 36.📅 Good or poor project planning: ignoring the timetable? (a) poor planning (b) good planning
- 37.Which of these is good project planning? (a) no task list (b) starting on the last day (c) one huge deadline (d) checking progress weekly
- 38.⏰ You start at 4:30 PM. Homework takes 25 minutes, then project work takes 35 minutes. When will you finish? (a) 5:05 PM (b) 5:30 PM (c) 4:55 PM (d) 5:45 PM
- 39.Which of these is poor project planning? (a) keeping spare days (b) setting mini-deadlines (c) no spare time (d) hard part first
- 40.True or false: “forgetting the due date” is poor project planning. (a) True (b) False
Answer key
- this week
- starting early
- ignoring the timetable
- False
- a date for one step
- 3
- 4
- poor planning
- True
- break it into steps
- 5
- poor planning
- keeping spare days
- poor planning
- starting early
- for surprises
- 7:00 PM
- good planning
- listing tasks first
- True
- 8
- breaking work into steps
- study for the test
- 4
- True
- listing tasks first
- False
- poor planning
- keeping spare days
- no task list
- starting on the last day
- good planning
- no spare time
- using a simple timetable
- forgetting the due date
- poor planning
- checking progress weekly
- 5:30 PM
- no spare time
- True