Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 486 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.Which of these is poor project planning? (a) using a simple timetable (b) no task list (c) breaking work into steps (d) starting early
  2. 2.📅 Your history chart is due in 14 days. Research takes 3 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
  3. 3.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
  4. 4.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
  5. 5.🔍 Which is the odd one out? (a) hard part first (b) guessing how long (c) starting early (d) listing tasks first
  6. 6.🔍 Which is the odd one out? (a) guessing how long (b) no spare time (c) ignoring the timetable (d) starting early
  7. 7.🔍 Which is the odd one out? (a) doing only easy bits (b) guessing how long (c) no task list (d) listing tasks first
  8. 8.⏰ You start at 5:00 PM. Homework takes 40 minutes, then project work takes 25 minutes. When will you finish? (a) 5:40 PM (b) 6:20 PM (c) 6:05 PM (d) 5:25 PM
  9. 9.Which of these is good project planning? (a) no spare time (b) doing only easy bits (c) ignoring the timetable (d) setting mini-deadlines
  10. 10.Which of these is poor project planning? (a) checking progress weekly (b) setting mini-deadlines (c) starting on the last day (d) hard part first
  11. 11.🔍 Which is the odd one out? (a) keeping spare days (b) doing only easy bits (c) starting early (d) checking progress weekly
  12. 12.✅ What is a mini-deadline? (a) a holiday (b) the final due date (c) a date for one step (d) a late fine
  13. 13.True or false: “one huge deadline” is poor project planning. (a) True (b) False
  14. 14.📅 Your science model is due in 10 days. Research takes 2 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  15. 15.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
  16. 16.True or false: “no task list” is poor project planning. (a) True (b) False
  17. 17.Which of these is poor project planning? (a) using a simple timetable (b) starting early (c) hard part first (d) ignoring the timetable
  18. 18.True or false: “doing only easy bits” is poor project planning. (a) False (b) True
  19. 19.True or false: “starting early” is poor project planning. (a) True (b) False
  20. 20.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
  21. 21.⏰ You start at 3:30 PM. Homework takes 20 minutes, then project work takes 30 minutes. When will you finish? (a) 4:00 PM (b) 4:35 PM (c) 4:20 PM (d) 3:50 PM
  22. 22.Which of these is poor project planning? (a) listing tasks first (b) starting early (c) setting mini-deadlines (d) doing only easy bits
  23. 23.📅 Good or poor project planning: using a simple timetable? (a) poor planning (b) good planning
  24. 24.Which of these is good project planning? (a) doing only easy bits (b) using a simple timetable (c) forgetting the due date (d) starting on the last day
  25. 25.True or false: “using a simple timetable” is poor project planning. (a) True (b) False
  26. 26.✂️ Your team must make 10 bookmarks in 5 days, the same number each day. How many bookmarks a day?
  27. 27.⏰ You start at 3:45 PM. Homework takes 30 minutes, then project work takes 40 minutes. When will you finish? (a) 4:55 PM (b) 5:10 PM (c) 4:25 PM (d) 4:15 PM
  28. 28.🔍 Which is the odd one out? (a) checking progress weekly (b) forgetting the due date (c) keeping spare days (d) listing tasks first
  29. 29.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) make the poster (c) study for the test (d) play first
  30. 30.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
  31. 31.Which of these is poor project planning? (a) hard part first (b) keeping spare days (c) forgetting the due date (d) checking progress weekly
  32. 32.⏰ You start at 5:30 PM. Homework takes 40 minutes, then project work takes 20 minutes. When will you finish? (a) 5:50 PM (b) 6:10 PM (c) 6:45 PM (d) 6:30 PM
  33. 33.🗓️ Your project is due in three weeks. When should you start? (a) the night before (b) this week (c) in the third week (d) after it is due
  34. 34.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
  35. 35.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) break it into steps (c) give up (d) wait for help
  36. 36.Which of these is good project planning? (a) doing only easy bits (b) forgetting the due date (c) checking progress weekly (d) no task list
  37. 37.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
  38. 38.True or false: “starting early” is good project planning. (a) True (b) False
  39. 39.Which of these is poor project planning? (a) using a simple timetable (b) listing tasks first (c) starting early (d) guessing how long
  40. 40.🔍 Which is the odd one out? (a) forgetting the due date (b) hard part first (c) no task list (d) starting on the last day

Answer key

  1. no task list
  2. 5
  3. poor planning
  4. good planning
  5. guessing how long
  6. starting early
  7. listing tasks first
  8. 6:05 PM
  9. setting mini-deadlines
  10. starting on the last day
  11. doing only easy bits
  12. a date for one step
  13. True
  14. 5
  15. good planning
  16. True
  17. ignoring the timetable
  18. True
  19. False
  20. good planning
  21. 4:20 PM
  22. doing only easy bits
  23. good planning
  24. using a simple timetable
  25. False
  26. 2
  27. 4:55 PM
  28. forgetting the due date
  29. study for the test
  30. poor planning
  31. forgetting the due date
  32. 6:30 PM
  33. this week
  34. poor planning
  35. break it into steps
  36. checking progress weekly
  37. poor planning
  38. True
  39. guessing how long
  40. hard part first