Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.⏳ Why keep a spare day or two before the deadline? (a) for surprises (b) to rest only (c) there is no need (d) to start late
- 2.True or false: “forgetting the due date” is poor project planning. (a) True (b) False
- 3.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 4.🔍 Which is the odd one out? (a) one huge deadline (b) hard part first (c) using a simple timetable (d) setting mini-deadlines
- 5.Which of these is poor project planning? (a) keeping spare days (b) forgetting the due date (c) listing tasks first (d) hard part first
- 6.Which of these is good project planning? (a) checking progress weekly (b) ignoring the timetable (c) no spare time (d) starting on the last day
- 7.Which of these is poor project planning? (a) one huge deadline (b) listing tasks first (c) using a simple timetable (d) checking progress weekly
- 8.Which of these is good project planning? (a) no spare time (b) forgetting the due date (c) using a simple timetable (d) ignoring the timetable
- 9.True or false: “breaking work into steps” is poor project planning. (a) False (b) True
- 10.Which of these is poor project planning? (a) starting early (b) breaking work into steps (c) checking progress weekly (d) no task list
- 11.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
- 12.🔍 Which is the odd one out? (a) starting on the last day (b) keeping spare days (c) no spare time (d) ignoring the timetable
- 13.Which of these is good project planning? (a) doing only easy bits (b) starting on the last day (c) breaking work into steps (d) guessing how long
- 14.True or false: “forgetting the due date” is good project planning. (a) False (b) True
- 15.⏰ You start at 3:15 PM. Homework takes 25 minutes, then project work takes 15 minutes. When will you finish? (a) 3:55 PM (b) 4:10 PM (c) 3:30 PM (d) 3:40 PM
- 16.🔍 Which is the odd one out? (a) using a simple timetable (b) breaking work into steps (c) keeping spare days (d) guessing how long
- 17.🔍 Which is the odd one out? (a) no task list (b) starting early (c) forgetting the due date (d) starting on the last day
- 18.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
- 19.True or false: “checking progress weekly” is good project planning. (a) False (b) True
- 20.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
- 21.True or false: “no task list” is poor project planning. (a) False (b) True
- 22.✅ What is a mini-deadline? (a) a date for one step (b) the final due date (c) a holiday (d) a late fine
- 23.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
- 24.True or false: “listing tasks first” is good project planning. (a) False (b) True
- 25.✂️ Your team must make 8 paper flowers in 4 days, the same number each day. How many paper flowers a day?
- 26.True or false: “starting early” is poor project planning. (a) False (b) True
- 27.🧩 A big project feels scary. What should you do first? (a) break it into steps (b) wait for help (c) do it all at once (d) give up
- 28.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
- 29.Which of these is poor project planning? (a) checking progress weekly (b) setting mini-deadlines (c) doing only easy bits (d) using a simple timetable
- 30.📅 Your maths exhibit is due in 10 days. Research takes 2 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
- 31.✂️ Your team must make 42 paper bags in 6 days, the same number each day. How many paper bags a day?
- 32.✂️ Your team must make 12 bookmarks in 2 days, the same number each day. How many bookmarks a day?
- 33.True or false: “no spare time” is good project planning. (a) False (b) True
- 34.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) after it is due (c) the night before (d) in the third week
- 35.✂️ Your team must make 24 posters in 4 days, the same number each day. How many posters a day?
- 36.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
- 37.True or false: “starting early” is good project planning. (a) False (b) True
- 38.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
- 39.⏰ You start at 5:30 PM. Homework takes 25 minutes, then project work takes 35 minutes. When will you finish? (a) 5:55 PM (b) 6:30 PM (c) 6:05 PM (d) 6:45 PM
- 40.📅 Your maths exhibit is due in 8 days. Research takes 1 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
Answer key
- for surprises
- True
- poor planning
- one huge deadline
- forgetting the due date
- checking progress weekly
- one huge deadline
- using a simple timetable
- False
- no task list
- good planning
- keeping spare days
- breaking work into steps
- False
- 3:55 PM
- guessing how long
- starting early
- good planning
- True
- poor planning
- True
- a date for one step
- poor planning
- True
- 2
- False
- break it into steps
- good planning
- doing only easy bits
- 3
- 7
- 6
- False
- this week
- 6
- poor planning
- True
- good planning
- 6:30 PM
- 3