Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Your eco-club poster is due in 13 days. Research takes 3 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
- 2.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 3.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
- 4.Which of these is good project planning? (a) guessing how long (b) ignoring the timetable (c) forgetting the due date (d) hard part first
- 5.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
- 6.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
- 7.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 8.🔍 Which is the odd one out? (a) breaking work into steps (b) setting mini-deadlines (c) ignoring the timetable (d) using a simple timetable
- 9.Which of these is poor project planning? (a) hard part first (b) starting early (c) doing only easy bits (d) listing tasks first
- 10.🔍 Which is the odd one out? (a) checking progress weekly (b) setting mini-deadlines (c) breaking work into steps (d) guessing how long
- 11.📅 Good or poor project planning: one huge deadline? (a) poor planning (b) good planning
- 12.True or false: “listing tasks first” is good project planning. (a) False (b) True
- 13.True or false: “doing only easy bits” is good project planning. (a) False (b) True
- 14.📅 Your history chart is due in 13 days. Research takes 4 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 15.⏰ You start at 5:30 PM. Homework takes 25 minutes, then project work takes 20 minutes. When will you finish? (a) 6:15 PM (b) 6:30 PM (c) 5:50 PM (d) 5:55 PM
- 16.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) in the third week (c) the night before (d) this week
- 17.✂️ Your team must make 10 bookmarks in 5 days, the same number each day. How many bookmarks a day?
- 18.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to start late (c) for surprises (d) to rest only
- 19.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
- 20.True or false: “no spare time” is good project planning. (a) True (b) False
- 21.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
- 22.Which of these is poor project planning? (a) checking progress weekly (b) starting on the last day (c) starting early (d) hard part first
- 23.Which of these is poor project planning? (a) using a simple timetable (b) starting early (c) listing tasks first (d) guessing how long
- 24.✂️ Your team must make 10 paper bags in 5 days, the same number each day. How many paper bags a day?
- 25.✂️ Your team must make 4 paper flowers in 2 days, the same number each day. How many paper flowers a day?
- 26.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) study for the test (b) make the poster (c) neither (d) play first
- 27.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
- 28.🔍 Which is the odd one out? (a) one huge deadline (b) guessing how long (c) breaking work into steps (d) no spare time
- 29.✂️ Your team must make 30 name badges in 5 days, the same number each day. How many name badges a day?
- 30.Which of these is good project planning? (a) forgetting the due date (b) listing tasks first (c) guessing how long (d) no spare time
- 31.📅 Your class magazine is due in 11 days. Research takes 3 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 32.✂️ Your team must make 27 paper flowers in 3 days, the same number each day. How many paper flowers a day?
- 33.Which of these is good project planning? (a) checking progress weekly (b) one huge deadline (c) starting on the last day (d) no spare time
- 34.Which of these is good project planning? (a) ignoring the timetable (b) breaking work into steps (c) starting on the last day (d) forgetting the due date
- 35.🔍 Which is the odd one out? (a) no task list (b) using a simple timetable (c) keeping spare days (d) setting mini-deadlines
- 36.✂️ Your team must make 18 thank-you cards in 2 days, the same number each day. How many thank-you cards a day?
- 37.True or false: “doing only easy bits” is poor project planning. (a) False (b) True
- 38.🔍 Which is the odd one out? (a) starting on the last day (b) starting early (c) hard part first (d) keeping spare days
- 39.✂️ Your team must make 20 bookmarks in 4 days, the same number each day. How many bookmarks a day?
- 40.Which of these is poor project planning? (a) starting early (b) breaking work into steps (c) setting mini-deadlines (d) forgetting the due date
Answer key
- 5
- poor planning
- good planning
- hard part first
- good planning
- good planning
- poor planning
- ignoring the timetable
- doing only easy bits
- guessing how long
- poor planning
- True
- False
- 2
- 6:15 PM
- this week
- 2
- for surprises
- poor planning
- False
- good planning
- starting on the last day
- guessing how long
- 2
- 2
- study for the test
- good planning
- breaking work into steps
- 6
- listing tasks first
- 4
- 9
- checking progress weekly
- breaking work into steps
- no task list
- 9
- True
- starting on the last day
- 5
- forgetting the due date