Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 514 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Your science model is due in 7 days. Research takes 2 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
  2. 2.🔍 Which is the odd one out? (a) forgetting the due date (b) one huge deadline (c) listing tasks first (d) ignoring the timetable
  3. 3.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) the night before (c) in the third week (d) this week
  4. 4.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
  5. 5.True or false: “keeping spare days” is good project planning. (a) True (b) False
  6. 6.✂️ Your team must make 10 thank-you cards in 2 days, the same number each day. How many thank-you cards a day?
  7. 7.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
  8. 8.🔍 Which is the odd one out? (a) hard part first (b) setting mini-deadlines (c) one huge deadline (d) listing tasks first
  9. 9.⏰ You start at 4:45 PM. Homework takes 20 minutes, then project work takes 25 minutes. When will you finish? (a) 5:30 PM (b) 5:05 PM (c) 5:45 PM (d) 5:10 PM
  10. 10.📅 Your maths exhibit is due in 10 days. Research takes 4 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
  11. 11.✂️ Your team must make 15 paper flowers in 3 days, the same number each day. How many paper flowers a day?
  12. 12.🔍 Which is the odd one out? (a) starting on the last day (b) forgetting the due date (c) checking progress weekly (d) no task list
  13. 13.✅ What is a mini-deadline? (a) the final due date (b) a late fine (c) a holiday (d) a date for one step
  14. 14.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
  15. 15.🔍 Which is the odd one out? (a) checking progress weekly (b) starting early (c) forgetting the due date (d) keeping spare days
  16. 16.⏰ You start at 5:00 PM. Homework takes 30 minutes, then project work takes 40 minutes. When will you finish? (a) 6:25 PM (b) 6:10 PM (c) 5:30 PM (d) 5:40 PM
  17. 17.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) make the poster (b) play first (c) study for the test (d) neither
  18. 18.Which of these is poor project planning? (a) listing tasks first (b) hard part first (c) keeping spare days (d) no task list
  19. 19.Which of these is poor project planning? (a) hard part first (b) using a simple timetable (c) starting on the last day (d) checking progress weekly
  20. 20.Which of these is poor project planning? (a) ignoring the timetable (b) breaking work into steps (c) setting mini-deadlines (d) using a simple timetable
  21. 21.Which of these is poor project planning? (a) keeping spare days (b) breaking work into steps (c) listing tasks first (d) guessing how long
  22. 22.🔍 Which is the odd one out? (a) ignoring the timetable (b) breaking work into steps (c) checking progress weekly (d) hard part first
  23. 23.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
  24. 24.🔍 Which is the odd one out? (a) no task list (b) hard part first (c) doing only easy bits (d) starting on the last day
  25. 25.🔍 Which is the odd one out? (a) breaking work into steps (b) checking progress weekly (c) starting early (d) doing only easy bits
  26. 26.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
  27. 27.Which of these is good project planning? (a) breaking work into steps (b) ignoring the timetable (c) one huge deadline (d) starting on the last day
  28. 28.True or false: “forgetting the due date” is poor project planning. (a) False (b) True
  29. 29.True or false: “listing tasks first” is poor project planning. (a) False (b) True
  30. 30.📅 Your class magazine is due in 6 days. Research takes 2 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  31. 31.🔍 Which is the odd one out? (a) listing tasks first (b) hard part first (c) no task list (d) starting early
  32. 32.True or false: “starting on the last day” is good project planning. (a) False (b) True
  33. 33.📅 Good or poor project planning: starting early? (a) poor planning (b) good planning
  34. 34.🧩 A big project feels scary. What should you do first? (a) wait for help (b) do it all at once (c) give up (d) break it into steps
  35. 35.⏰ You start at 3:00 PM. Homework takes 40 minutes, then project work takes 35 minutes. When will you finish? (a) 4:30 PM (b) 4:15 PM (c) 3:40 PM (d) 3:35 PM
  36. 36.📅 Your eco-club poster is due in 11 days. Research takes 3 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
  37. 37.True or false: “one huge deadline” is poor project planning. (a) True (b) False
  38. 38.🔍 Which is the odd one out? (a) starting on the last day (b) breaking work into steps (c) checking progress weekly (d) hard part first
  39. 39.📅 Your school play is due in 10 days. Research takes 2 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
  40. 40.⏳ Why keep a spare day or two before the deadline? (a) for surprises (b) there is no need (c) to rest only (d) to start late

Answer key

  1. 1
  2. listing tasks first
  3. this week
  4. poor planning
  5. True
  6. 5
  7. poor planning
  8. one huge deadline
  9. 5:30 PM
  10. 1
  11. 5
  12. checking progress weekly
  13. a date for one step
  14. poor planning
  15. forgetting the due date
  16. 6:10 PM
  17. study for the test
  18. no task list
  19. starting on the last day
  20. ignoring the timetable
  21. guessing how long
  22. ignoring the timetable
  23. poor planning
  24. hard part first
  25. doing only easy bits
  26. good planning
  27. breaking work into steps
  28. True
  29. False
  30. 1
  31. no task list
  32. False
  33. good planning
  34. break it into steps
  35. 4:15 PM
  36. 2
  37. True
  38. starting on the last day
  39. 3
  40. for surprises