Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.🔍 Which is the odd one out? (a) starting on the last day (b) starting early (c) forgetting the due date (d) ignoring the timetable
- 2.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
- 3.True or false: “guessing how long” is good project planning. (a) True (b) False
- 4.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 5.True or false: “no spare time” is good project planning. (a) False (b) True
- 6.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
- 7.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) break it into steps (c) wait for help (d) give up
- 8.🔍 Which is the odd one out? (a) setting mini-deadlines (b) checking progress weekly (c) using a simple timetable (d) guessing how long
- 9.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
- 10.⏳ Why keep a spare day or two before the deadline? (a) to start late (b) there is no need (c) to rest only (d) for surprises
- 11.✂️ Your team must make 42 thank-you cards in 6 days, the same number each day. How many thank-you cards a day?
- 12.Which of these is poor project planning? (a) keeping spare days (b) breaking work into steps (c) guessing how long (d) setting mini-deadlines
- 13.📅 Your maths exhibit is due in 12 days. Research takes 2 days, making it takes 4 days and practice takes 3 days. How many spare days will you have?
- 14.📅 Good or poor project planning: starting on the last day? (a) good planning (b) poor planning
- 15.📅 Your class magazine is due in 13 days. Research takes 1 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 16.🗓️ Your project is due in three weeks. When should you start? (a) the night before (b) this week (c) in the third week (d) after it is due
- 17.True or false: “one huge deadline” is poor project planning. (a) True (b) False
- 18.True or false: “starting early” is poor project planning. (a) True (b) False
- 19.📅 Good or poor project planning: one huge deadline? (a) poor planning (b) good planning
- 20.📅 Your class magazine is due in 15 days. Research takes 4 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 21.True or false: “guessing how long” is poor project planning. (a) False (b) True
- 22.📅 Your art display is due in 11 days. Research takes 3 days, making it takes 4 days and practice takes 2 days. How many spare days will you have?
- 23.True or false: “breaking work into steps” is good project planning. (a) False (b) True
- 24.✂️ Your team must make 9 paper flowers in 3 days, the same number each day. How many paper flowers a day?
- 25.Which of these is poor project planning? (a) starting on the last day (b) keeping spare days (c) hard part first (d) breaking work into steps
- 26.⏰ You start at 5:15 PM. Homework takes 20 minutes, then project work takes 40 minutes. When will you finish? (a) 6:15 PM (b) 5:55 PM (c) 5:35 PM (d) 6:30 PM
- 27.True or false: “no task list” is poor project planning. (a) False (b) True
- 28.Which of these is good project planning? (a) using a simple timetable (b) one huge deadline (c) starting on the last day (d) forgetting the due date
- 29.Which of these is poor project planning? (a) starting early (b) no spare time (c) checking progress weekly (d) breaking work into steps
- 30.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) study for the test (c) neither (d) make the poster
- 31.🔍 Which is the odd one out? (a) no task list (b) doing only easy bits (c) keeping spare days (d) ignoring the timetable
- 32.True or false: “keeping spare days” is good project planning. (a) True (b) False
- 33.Which of these is good project planning? (a) no task list (b) no spare time (c) keeping spare days (d) starting on the last day
- 34.🔍 Which is the odd one out? (a) checking progress weekly (b) keeping spare days (c) no task list (d) hard part first
- 35.✂️ Your team must make 12 paper flowers in 2 days, the same number each day. How many paper flowers a day?
- 36.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
- 37.✅ What is a mini-deadline? (a) the final due date (b) a late fine (c) a date for one step (d) a holiday
- 38.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 39.📅 Your art display is due in 12 days. Research takes 4 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 40.🔍 Which is the odd one out? (a) breaking work into steps (b) hard part first (c) forgetting the due date (d) using a simple timetable
Answer key
- starting early
- good planning
- False
- good planning
- False
- good planning
- break it into steps
- guessing how long
- poor planning
- for surprises
- 7
- guessing how long
- 3
- poor planning
- 5
- this week
- True
- False
- poor planning
- 5
- True
- 2
- True
- 3
- starting on the last day
- 6:15 PM
- True
- using a simple timetable
- no spare time
- study for the test
- keeping spare days
- True
- keeping spare days
- no task list
- 6
- good planning
- a date for one step
- poor planning
- 4
- forgetting the due date