Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.📅 Good or poor project planning: guessing how long? (a) poor planning (b) good planning
- 2.⏰ You start at 5:45 PM. Homework takes 40 minutes, then project work takes 30 minutes. When will you finish? (a) 6:55 PM (b) 6:15 PM (c) 7:10 PM (d) 6:25 PM
- 3.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
- 4.True or false: “listing tasks first” is good project planning. (a) False (b) True
- 5.Which of these is good project planning? (a) forgetting the due date (b) no task list (c) hard part first (d) no spare time
- 6.Which of these is poor project planning? (a) breaking work into steps (b) forgetting the due date (c) hard part first (d) listing tasks first
- 7.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) give up (c) wait for help (d) break it into steps
- 8.🔍 Which is the odd one out? (a) no spare time (b) setting mini-deadlines (c) one huge deadline (d) no task list
- 9.✂️ Your team must make 30 thank-you cards in 5 days, the same number each day. How many thank-you cards a day?
- 10.📅 Your eco-club poster is due in 12 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 11.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
- 12.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
- 13.🔍 Which is the odd one out? (a) hard part first (b) checking progress weekly (c) listing tasks first (d) forgetting the due date
- 14.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
- 15.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) in the third week (c) the night before (d) after it is due
- 16.📅 Your school play is due in 12 days. Research takes 3 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 17.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) make the poster (c) play first (d) study for the test
- 18.Which of these is poor project planning? (a) checking progress weekly (b) starting early (c) one huge deadline (d) setting mini-deadlines
- 19.⏰ You start at 3:45 PM. Homework takes 20 minutes, then project work takes 35 minutes. When will you finish? (a) 4:20 PM (b) 4:05 PM (c) 4:40 PM (d) 4:55 PM
- 20.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) for surprises (c) there is no need (d) to start late
- 21.True or false: “forgetting the due date” is good project planning. (a) True (b) False
- 22.True or false: “ignoring the timetable” is poor project planning. (a) False (b) True
- 23.🔍 Which is the odd one out? (a) doing only easy bits (b) forgetting the due date (c) one huge deadline (d) using a simple timetable
- 24.True or false: “no task list” is good project planning. (a) False (b) True
- 25.✂️ Your team must make 4 name badges in 2 days, the same number each day. How many name badges a day?
- 26.Which of these is good project planning? (a) forgetting the due date (b) keeping spare days (c) guessing how long (d) ignoring the timetable
- 27.True or false: “guessing how long” is good project planning. (a) False (b) True
- 28.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 29.Which of these is poor project planning? (a) checking progress weekly (b) hard part first (c) starting on the last day (d) keeping spare days
- 30.📅 Your school play is due in 8 days. Research takes 1 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 31.✅ What is a mini-deadline? (a) the final due date (b) a holiday (c) a late fine (d) a date for one step
- 32.Which of these is poor project planning? (a) using a simple timetable (b) listing tasks first (c) checking progress weekly (d) ignoring the timetable
- 33.Which of these is poor project planning? (a) listing tasks first (b) breaking work into steps (c) setting mini-deadlines (d) no task list
- 34.Which of these is good project planning? (a) starting early (b) ignoring the timetable (c) guessing how long (d) one huge deadline
- 35.🔍 Which is the odd one out? (a) starting on the last day (b) one huge deadline (c) breaking work into steps (d) no task list
- 36.True or false: “forgetting the due date” is poor project planning. (a) False (b) True
- 37.Which of these is good project planning? (a) starting on the last day (b) guessing how long (c) breaking work into steps (d) no spare time
- 38.True or false: “guessing how long” is poor project planning. (a) True (b) False
- 39.📅 Your science model is due in 10 days. Research takes 3 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
- 40.True or false: “one huge deadline” is good project planning. (a) False (b) True
Answer key
- poor planning
- 6:55 PM
- poor planning
- True
- hard part first
- forgetting the due date
- break it into steps
- setting mini-deadlines
- 6
- 5
- good planning
- poor planning
- forgetting the due date
- good planning
- this week
- 5
- study for the test
- one huge deadline
- 4:40 PM
- for surprises
- False
- True
- using a simple timetable
- False
- 2
- keeping spare days
- False
- good planning
- starting on the last day
- 3
- a date for one step
- ignoring the timetable
- no task list
- starting early
- breaking work into steps
- True
- breaking work into steps
- True
- 2
- False