Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.🔍 Which is the odd one out? (a) no spare time (b) starting early (c) forgetting the due date (d) starting on the last day
- 2.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 3.📅 Your art display is due in 13 days. Research takes 3 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
- 4.✂️ Your team must make 45 bookmarks in 5 days, the same number each day. How many bookmarks a day?
- 5.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) in the third week (c) the night before (d) this week
- 6.🧩 A big project feels scary. What should you do first? (a) wait for help (b) break it into steps (c) do it all at once (d) give up
- 7.Which of these is good project planning? (a) one huge deadline (b) doing only easy bits (c) guessing how long (d) breaking work into steps
- 8.🔍 Which is the odd one out? (a) checking progress weekly (b) setting mini-deadlines (c) no spare time (d) using a simple timetable
- 9.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 10.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) make the poster (c) study for the test (d) neither
- 11.Which of these is poor project planning? (a) listing tasks first (b) doing only easy bits (c) checking progress weekly (d) breaking work into steps
- 12.True or false: “checking progress weekly” is poor project planning. (a) True (b) False
- 13.🔍 Which is the odd one out? (a) doing only easy bits (b) forgetting the due date (c) using a simple timetable (d) no task list
- 14.True or false: “no spare time” is good project planning. (a) False (b) True
- 15.🔍 Which is the odd one out? (a) listing tasks first (b) guessing how long (c) hard part first (d) setting mini-deadlines
- 16.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
- 17.Which of these is poor project planning? (a) starting early (b) checking progress weekly (c) using a simple timetable (d) one huge deadline
- 18.✂️ Your team must make 4 posters in 2 days, the same number each day. How many posters a day?
- 19.True or false: “keeping spare days” is poor project planning. (a) True (b) False
- 20.✂️ Your team must make 12 bookmarks in 3 days, the same number each day. How many bookmarks a day?
- 21.True or false: “listing tasks first” is poor project planning. (a) True (b) False
- 22.⏰ You start at 5:45 PM. Homework takes 25 minutes, then project work takes 20 minutes. When will you finish? (a) 6:30 PM (b) 6:45 PM (c) 6:05 PM (d) 6:10 PM
- 23.🔍 Which is the odd one out? (a) breaking work into steps (b) one huge deadline (c) setting mini-deadlines (d) hard part first
- 24.✅ What is a mini-deadline? (a) the final due date (b) a late fine (c) a date for one step (d) a holiday
- 25.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
- 26.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
- 27.✂️ Your team must make 10 bookmarks in 5 days, the same number each day. How many bookmarks a day?
- 28.🔍 Which is the odd one out? (a) ignoring the timetable (b) no task list (c) listing tasks first (d) one huge deadline
- 29.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
- 30.Which of these is poor project planning? (a) keeping spare days (b) guessing how long (c) listing tasks first (d) setting mini-deadlines
- 31.True or false: “ignoring the timetable” is good project planning. (a) True (b) False
- 32.🔍 Which is the odd one out? (a) hard part first (b) starting on the last day (c) one huge deadline (d) guessing how long
- 33.True or false: “no task list” is good project planning. (a) True (b) False
- 34.True or false: “doing only easy bits” is good project planning. (a) False (b) True
- 35.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
- 36.Which of these is good project planning? (a) no spare time (b) one huge deadline (c) doing only easy bits (d) listing tasks first
- 37.🔍 Which is the odd one out? (a) forgetting the due date (b) guessing how long (c) starting on the last day (d) setting mini-deadlines
- 38.Which of these is good project planning? (a) forgetting the due date (b) starting on the last day (c) ignoring the timetable (d) using a simple timetable
- 39.True or false: “hard part first” is good project planning. (a) True (b) False
- 40.True or false: “forgetting the due date” is poor project planning. (a) True (b) False
Answer key
- starting early
- poor planning
- 3
- 9
- this week
- break it into steps
- breaking work into steps
- no spare time
- poor planning
- study for the test
- doing only easy bits
- False
- using a simple timetable
- False
- guessing how long
- good planning
- one huge deadline
- 2
- False
- 4
- False
- 6:30 PM
- one huge deadline
- a date for one step
- poor planning
- good planning
- 2
- listing tasks first
- good planning
- guessing how long
- False
- hard part first
- False
- False
- good planning
- listing tasks first
- setting mini-deadlines
- using a simple timetable
- True
- True