Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 556 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.🔍 Which is the odd one out? (a) no spare time (b) starting early (c) forgetting the due date (d) starting on the last day
  2. 2.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
  3. 3.📅 Your art display is due in 13 days. Research takes 3 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
  4. 4.✂️ Your team must make 45 bookmarks in 5 days, the same number each day. How many bookmarks a day?
  5. 5.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) in the third week (c) the night before (d) this week
  6. 6.🧩 A big project feels scary. What should you do first? (a) wait for help (b) break it into steps (c) do it all at once (d) give up
  7. 7.Which of these is good project planning? (a) one huge deadline (b) doing only easy bits (c) guessing how long (d) breaking work into steps
  8. 8.🔍 Which is the odd one out? (a) checking progress weekly (b) setting mini-deadlines (c) no spare time (d) using a simple timetable
  9. 9.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
  10. 10.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) make the poster (c) study for the test (d) neither
  11. 11.Which of these is poor project planning? (a) listing tasks first (b) doing only easy bits (c) checking progress weekly (d) breaking work into steps
  12. 12.True or false: “checking progress weekly” is poor project planning. (a) True (b) False
  13. 13.🔍 Which is the odd one out? (a) doing only easy bits (b) forgetting the due date (c) using a simple timetable (d) no task list
  14. 14.True or false: “no spare time” is good project planning. (a) False (b) True
  15. 15.🔍 Which is the odd one out? (a) listing tasks first (b) guessing how long (c) hard part first (d) setting mini-deadlines
  16. 16.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
  17. 17.Which of these is poor project planning? (a) starting early (b) checking progress weekly (c) using a simple timetable (d) one huge deadline
  18. 18.✂️ Your team must make 4 posters in 2 days, the same number each day. How many posters a day?
  19. 19.True or false: “keeping spare days” is poor project planning. (a) True (b) False
  20. 20.✂️ Your team must make 12 bookmarks in 3 days, the same number each day. How many bookmarks a day?
  21. 21.True or false: “listing tasks first” is poor project planning. (a) True (b) False
  22. 22.⏰ You start at 5:45 PM. Homework takes 25 minutes, then project work takes 20 minutes. When will you finish? (a) 6:30 PM (b) 6:45 PM (c) 6:05 PM (d) 6:10 PM
  23. 23.🔍 Which is the odd one out? (a) breaking work into steps (b) one huge deadline (c) setting mini-deadlines (d) hard part first
  24. 24.✅ What is a mini-deadline? (a) the final due date (b) a late fine (c) a date for one step (d) a holiday
  25. 25.📅 Good or poor project planning: no task list? (a) good planning (b) poor planning
  26. 26.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
  27. 27.✂️ Your team must make 10 bookmarks in 5 days, the same number each day. How many bookmarks a day?
  28. 28.🔍 Which is the odd one out? (a) ignoring the timetable (b) no task list (c) listing tasks first (d) one huge deadline
  29. 29.📅 Good or poor project planning: breaking work into steps? (a) good planning (b) poor planning
  30. 30.Which of these is poor project planning? (a) keeping spare days (b) guessing how long (c) listing tasks first (d) setting mini-deadlines
  31. 31.True or false: “ignoring the timetable” is good project planning. (a) True (b) False
  32. 32.🔍 Which is the odd one out? (a) hard part first (b) starting on the last day (c) one huge deadline (d) guessing how long
  33. 33.True or false: “no task list” is good project planning. (a) True (b) False
  34. 34.True or false: “doing only easy bits” is good project planning. (a) False (b) True
  35. 35.📅 Good or poor project planning: setting mini-deadlines? (a) good planning (b) poor planning
  36. 36.Which of these is good project planning? (a) no spare time (b) one huge deadline (c) doing only easy bits (d) listing tasks first
  37. 37.🔍 Which is the odd one out? (a) forgetting the due date (b) guessing how long (c) starting on the last day (d) setting mini-deadlines
  38. 38.Which of these is good project planning? (a) forgetting the due date (b) starting on the last day (c) ignoring the timetable (d) using a simple timetable
  39. 39.True or false: “hard part first” is good project planning. (a) True (b) False
  40. 40.True or false: “forgetting the due date” is poor project planning. (a) True (b) False

Answer key

  1. starting early
  2. poor planning
  3. 3
  4. 9
  5. this week
  6. break it into steps
  7. breaking work into steps
  8. no spare time
  9. poor planning
  10. study for the test
  11. doing only easy bits
  12. False
  13. using a simple timetable
  14. False
  15. guessing how long
  16. good planning
  17. one huge deadline
  18. 2
  19. False
  20. 4
  21. False
  22. 6:30 PM
  23. one huge deadline
  24. a date for one step
  25. poor planning
  26. good planning
  27. 2
  28. listing tasks first
  29. good planning
  30. guessing how long
  31. False
  32. hard part first
  33. False
  34. False
  35. good planning
  36. listing tasks first
  37. setting mini-deadlines
  38. using a simple timetable
  39. True
  40. True