Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 565 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.True or false: “setting mini-deadlines” is good project planning. (a) False (b) True
  2. 2.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
  3. 3.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) after it is due (c) this week (d) the night before
  4. 4.🔍 Which is the odd one out? (a) keeping spare days (b) no task list (c) doing only easy bits (d) ignoring the timetable
  5. 5.⏰ You start at 3:00 PM. Homework takes 30 minutes, then project work takes 20 minutes. When will you finish? (a) 3:30 PM (b) 4:05 PM (c) 3:50 PM (d) 3:20 PM
  6. 6.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
  7. 7.🔍 Which is the odd one out? (a) checking progress weekly (b) one huge deadline (c) starting early (d) keeping spare days
  8. 8.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) wait for help (c) give up (d) break it into steps
  9. 9.✅ What is a mini-deadline? (a) a holiday (b) a date for one step (c) the final due date (d) a late fine
  10. 10.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
  11. 11.True or false: “starting on the last day” is good project planning. (a) True (b) False
  12. 12.True or false: “starting on the last day” is poor project planning. (a) False (b) True
  13. 13.🔍 Which is the odd one out? (a) hard part first (b) breaking work into steps (c) keeping spare days (d) starting on the last day
  14. 14.Which of these is poor project planning? (a) using a simple timetable (b) setting mini-deadlines (c) no spare time (d) keeping spare days
  15. 15.🔍 Which is the odd one out? (a) keeping spare days (b) no spare time (c) setting mini-deadlines (d) starting early
  16. 16.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
  17. 17.Which of these is good project planning? (a) starting on the last day (b) one huge deadline (c) ignoring the timetable (d) hard part first
  18. 18.Which of these is poor project planning? (a) guessing how long (b) using a simple timetable (c) breaking work into steps (d) hard part first
  19. 19.Which of these is good project planning? (a) guessing how long (b) no task list (c) keeping spare days (d) no spare time
  20. 20.True or false: “one huge deadline” is good project planning. (a) True (b) False
  21. 21.📅 Your history chart is due in 11 days. Research takes 4 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
  22. 22.True or false: “breaking work into steps” is poor project planning. (a) False (b) True
  23. 23.✂️ Your team must make 15 posters in 5 days, the same number each day. How many posters a day?
  24. 24.True or false: “no task list” is good project planning. (a) True (b) False
  25. 25.Which of these is poor project planning? (a) breaking work into steps (b) setting mini-deadlines (c) listing tasks first (d) ignoring the timetable
  26. 26.📅 Your science model is due in 12 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
  27. 27.🔍 Which is the odd one out? (a) doing only easy bits (b) guessing how long (c) starting on the last day (d) breaking work into steps
  28. 28.⏰ You start at 3:45 PM. Homework takes 40 minutes, then project work takes 15 minutes. When will you finish? (a) 4:25 PM (b) 4:40 PM (c) 4:00 PM (d) 4:55 PM
  29. 29.📅 Your class magazine is due in 11 days. Research takes 2 days, making it takes 5 days and practice takes 2 days. How many spare days will you have?
  30. 30.📅 Good or poor project planning: setting mini-deadlines? (a) poor planning (b) good planning
  31. 31.Which of these is good project planning? (a) one huge deadline (b) guessing how long (c) setting mini-deadlines (d) no task list
  32. 32.⏳ Why keep a spare day or two before the deadline? (a) for surprises (b) to rest only (c) to start late (d) there is no need
  33. 33.Which of these is poor project planning? (a) listing tasks first (b) keeping spare days (c) forgetting the due date (d) hard part first
  34. 34.True or false: “hard part first” is poor project planning. (a) False (b) True
  35. 35.Which of these is good project planning? (a) starting on the last day (b) forgetting the due date (c) no task list (d) listing tasks first
  36. 36.True or false: “checking progress weekly” is good project planning. (a) False (b) True
  37. 37.⏰ You start at 3:30 PM. Homework takes 35 minutes, then project work takes 20 minutes. When will you finish? (a) 3:50 PM (b) 4:25 PM (c) 4:05 PM (d) 4:40 PM
  38. 38.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
  39. 39.Which of these is poor project planning? (a) checking progress weekly (b) no task list (c) starting early (d) setting mini-deadlines
  40. 40.True or false: “one huge deadline” is poor project planning. (a) False (b) True

Answer key

  1. True
  2. good planning
  3. this week
  4. keeping spare days
  5. 3:50 PM
  6. good planning
  7. one huge deadline
  8. break it into steps
  9. a date for one step
  10. good planning
  11. False
  12. True
  13. starting on the last day
  14. no spare time
  15. no spare time
  16. poor planning
  17. hard part first
  18. guessing how long
  19. keeping spare days
  20. False
  21. 2
  22. False
  23. 3
  24. False
  25. ignoring the timetable
  26. 5
  27. breaking work into steps
  28. 4:40 PM
  29. 2
  30. good planning
  31. setting mini-deadlines
  32. for surprises
  33. forgetting the due date
  34. False
  35. listing tasks first
  36. True
  37. 4:25 PM
  38. poor planning
  39. no task list
  40. True