Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 570 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.✂️ Your team must make 25 paper flowers in 5 days, the same number each day. How many paper flowers a day?
  2. 2.📅 Your class magazine is due in 11 days. Research takes 1 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
  3. 3.🔍 Which is the odd one out? (a) using a simple timetable (b) checking progress weekly (c) keeping spare days (d) no task list
  4. 4.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
  5. 5.🗓️ Your project is due in three weeks. When should you start? (a) in the third week (b) this week (c) after it is due (d) the night before
  6. 6.Which of these is good project planning? (a) one huge deadline (b) ignoring the timetable (c) no spare time (d) keeping spare days
  7. 7.Which of these is good project planning? (a) no task list (b) starting on the last day (c) guessing how long (d) setting mini-deadlines
  8. 8.⏰ You start at 5:15 PM. Homework takes 25 minutes, then project work takes 40 minutes. When will you finish? (a) 6:20 PM (b) 6:35 PM (c) 5:55 PM (d) 5:40 PM
  9. 9.🔍 Which is the odd one out? (a) doing only easy bits (b) using a simple timetable (c) no spare time (d) forgetting the due date
  10. 10.📅 Good or poor project planning: doing only easy bits? (a) good planning (b) poor planning
  11. 11.Which of these is good project planning? (a) no spare time (b) starting early (c) doing only easy bits (d) guessing how long
  12. 12.🔍 Which is the odd one out? (a) breaking work into steps (b) starting early (c) guessing how long (d) keeping spare days
  13. 13.📅 Good or poor project planning: no spare time? (a) good planning (b) poor planning
  14. 14.Which of these is good project planning? (a) no spare time (b) listing tasks first (c) doing only easy bits (d) forgetting the due date
  15. 15.Which of these is poor project planning? (a) starting early (b) breaking work into steps (c) doing only easy bits (d) hard part first
  16. 16.True or false: “using a simple timetable” is good project planning. (a) True (b) False
  17. 17.Which of these is good project planning? (a) using a simple timetable (b) no task list (c) guessing how long (d) one huge deadline
  18. 18.Which of these is poor project planning? (a) starting early (b) checking progress weekly (c) no spare time (d) listing tasks first
  19. 19.✅ What is a mini-deadline? (a) the final due date (b) a holiday (c) a late fine (d) a date for one step
  20. 20.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
  21. 21.True or false: “starting on the last day” is poor project planning. (a) True (b) False
  22. 22.⏰ You start at 3:45 PM. Homework takes 30 minutes, then project work takes 35 minutes. When will you finish? (a) 4:50 PM (b) 5:05 PM (c) 4:20 PM (d) 4:15 PM
  23. 23.True or false: “breaking work into steps” is poor project planning. (a) True (b) False
  24. 24.🔍 Which is the odd one out? (a) no spare time (b) guessing how long (c) keeping spare days (d) doing only easy bits
  25. 25.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) make the poster (b) neither (c) play first (d) study for the test
  26. 26.🔍 Which is the odd one out? (a) starting on the last day (b) setting mini-deadlines (c) starting early (d) breaking work into steps
  27. 27.🔍 Which is the odd one out? (a) checking progress weekly (b) no task list (c) one huge deadline (d) starting on the last day
  28. 28.Which of these is poor project planning? (a) checking progress weekly (b) listing tasks first (c) hard part first (d) starting on the last day
  29. 29.🔍 Which is the odd one out? (a) setting mini-deadlines (b) forgetting the due date (c) one huge deadline (d) doing only easy bits
  30. 30.Which of these is good project planning? (a) doing only easy bits (b) hard part first (c) no task list (d) ignoring the timetable
  31. 31.⏰ You start at 4:00 PM. Homework takes 40 minutes, then project work takes 25 minutes. When will you finish? (a) 4:40 PM (b) 4:25 PM (c) 5:05 PM (d) 5:20 PM
  32. 32.True or false: “setting mini-deadlines” is good project planning. (a) True (b) False
  33. 33.📅 Good or poor project planning: forgetting the due date? (a) good planning (b) poor planning
  34. 34.Which of these is good project planning? (a) no task list (b) one huge deadline (c) guessing how long (d) checking progress weekly
  35. 35.🧩 A big project feels scary. What should you do first? (a) give up (b) do it all at once (c) wait for help (d) break it into steps
  36. 36.Which of these is good project planning? (a) one huge deadline (b) doing only easy bits (c) no task list (d) breaking work into steps
  37. 37.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
  38. 38.📅 Good or poor project planning: hard part first? (a) good planning (b) poor planning
  39. 39.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
  40. 40.✂️ Your team must make 20 name badges in 4 days, the same number each day. How many name badges a day?

Answer key

  1. 5
  2. 4
  3. no task list
  4. good planning
  5. this week
  6. keeping spare days
  7. setting mini-deadlines
  8. 6:20 PM
  9. using a simple timetable
  10. poor planning
  11. starting early
  12. guessing how long
  13. poor planning
  14. listing tasks first
  15. doing only easy bits
  16. True
  17. using a simple timetable
  18. no spare time
  19. a date for one step
  20. poor planning
  21. True
  22. 4:50 PM
  23. False
  24. keeping spare days
  25. study for the test
  26. starting on the last day
  27. checking progress weekly
  28. starting on the last day
  29. setting mini-deadlines
  30. hard part first
  31. 5:05 PM
  32. True
  33. poor planning
  34. checking progress weekly
  35. break it into steps
  36. breaking work into steps
  37. poor planning
  38. good planning
  39. good planning
  40. 5