Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.True or false: “using a simple timetable” is poor project planning. (a) False (b) True
- 2.📅 Good or poor project planning: keeping spare days? (a) poor planning (b) good planning
- 3.📅 Good or poor project planning: using a simple timetable? (a) good planning (b) poor planning
- 4.Which of these is good project planning? (a) one huge deadline (b) no spare time (c) starting early (d) ignoring the timetable
- 5.📅 Good or poor project planning: one huge deadline? (a) good planning (b) poor planning
- 6.📅 Your art display is due in 8 days. Research takes 2 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 7.⏰ You start at 3:45 PM. Homework takes 45 minutes, then project work takes 15 minutes. When will you finish? (a) 4:45 PM (b) 4:30 PM (c) 5:00 PM (d) 4:00 PM
- 8.Which of these is good project planning? (a) starting on the last day (b) no task list (c) no spare time (d) checking progress weekly
- 9.🧩 A big project feels scary. What should you do first? (a) do it all at once (b) give up (c) wait for help (d) break it into steps
- 10.🔍 Which is the odd one out? (a) forgetting the due date (b) setting mini-deadlines (c) starting on the last day (d) one huge deadline
- 11.📅 Good or poor project planning: checking progress weekly? (a) poor planning (b) good planning
- 12.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
- 13.📅 Your art display is due in 11 days. Research takes 4 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
- 14.🔍 Which is the odd one out? (a) listing tasks first (b) using a simple timetable (c) hard part first (d) forgetting the due date
- 15.⏳ Why keep a spare day or two before the deadline? (a) there is no need (b) to start late (c) for surprises (d) to rest only
- 16.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) make the poster (b) play first (c) study for the test (d) neither
- 17.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
- 18.🔍 Which is the odd one out? (a) doing only easy bits (b) forgetting the due date (c) keeping spare days (d) starting on the last day
- 19.Which of these is good project planning? (a) one huge deadline (b) forgetting the due date (c) breaking work into steps (d) no task list
- 20.🗓️ Your project is due in three weeks. When should you start? (a) this week (b) after it is due (c) in the third week (d) the night before
- 21.Which of these is poor project planning? (a) breaking work into steps (b) starting early (c) listing tasks first (d) guessing how long
- 22.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
- 23.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
- 24.Which of these is good project planning? (a) ignoring the timetable (b) one huge deadline (c) keeping spare days (d) no task list
- 25.📅 Your art display is due in 9 days. Research takes 4 days, making it takes 2 days and practice takes 1 days. How many spare days will you have?
- 26.✂️ Your team must make 9 posters in 3 days, the same number each day. How many posters a day?
- 27.Which of these is poor project planning? (a) breaking work into steps (b) one huge deadline (c) starting early (d) hard part first
- 28.✂️ Your team must make 36 bookmarks in 4 days, the same number each day. How many bookmarks a day?
- 29.True or false: “starting on the last day” is good project planning. (a) True (b) False
- 30.📅 Your school play is due in 9 days. Research takes 3 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
- 31.🔍 Which is the odd one out? (a) guessing how long (b) starting on the last day (c) no spare time (d) starting early
- 32.🔍 Which is the odd one out? (a) breaking work into steps (b) using a simple timetable (c) guessing how long (d) listing tasks first
- 33.Which of these is good project planning? (a) starting on the last day (b) no task list (c) doing only easy bits (d) using a simple timetable
- 34.True or false: “guessing how long” is poor project planning. (a) False (b) True
- 35.✅ What is a mini-deadline? (a) the final due date (b) a date for one step (c) a late fine (d) a holiday
- 36.🔍 Which is the odd one out? (a) forgetting the due date (b) checking progress weekly (c) ignoring the timetable (d) guessing how long
- 37.📅 Good or poor project planning: no task list? (a) poor planning (b) good planning
- 38.⏰ You start at 5:30 PM. Homework takes 35 minutes, then project work takes 40 minutes. When will you finish? (a) 6:05 PM (b) 7:00 PM (c) 6:45 PM (d) 6:10 PM
- 39.📅 Good or poor project planning: ignoring the timetable? (a) good planning (b) poor planning
- 40.📅 Your eco-club poster is due in 12 days. Research takes 3 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
Answer key
- False
- good planning
- good planning
- starting early
- poor planning
- 2
- 4:45 PM
- checking progress weekly
- break it into steps
- setting mini-deadlines
- good planning
- good planning
- 1
- forgetting the due date
- for surprises
- study for the test
- poor planning
- keeping spare days
- breaking work into steps
- this week
- guessing how long
- good planning
- poor planning
- keeping spare days
- 2
- 3
- one huge deadline
- 9
- False
- 1
- starting early
- guessing how long
- using a simple timetable
- True
- a date for one step
- checking progress weekly
- poor planning
- 6:45 PM
- poor planning
- 4