Leadership Skills Worksheet: Project Time Management
Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.
NameDateTime takenScore ___ / 40
- 1.✂️ Your team must make 12 paper flowers in 2 days, the same number each day. How many paper flowers a day?
- 2.📅 Good or poor project planning: hard part first? (a) poor planning (b) good planning
- 3.📅 Good or poor project planning: forgetting the due date? (a) poor planning (b) good planning
- 4.📅 Good or poor project planning: keeping spare days? (a) good planning (b) poor planning
- 5.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) play first (b) make the poster (c) neither (d) study for the test
- 6.True or false: “setting mini-deadlines” is poor project planning. (a) False (b) True
- 7.🔍 Which is the odd one out? (a) guessing how long (b) doing only easy bits (c) forgetting the due date (d) using a simple timetable
- 8.True or false: “hard part first” is poor project planning. (a) False (b) True
- 9.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) the night before (c) this week (d) in the third week
- 10.🔍 Which is the odd one out? (a) forgetting the due date (b) no task list (c) one huge deadline (d) checking progress weekly
- 11.🧩 A big project feels scary. What should you do first? (a) give up (b) wait for help (c) break it into steps (d) do it all at once
- 12.📅 Your school play is due in 9 days. Research takes 2 days, making it takes 2 days and practice takes 3 days. How many spare days will you have?
- 13.📅 Good or poor project planning: doing only easy bits? (a) poor planning (b) good planning
- 14.📅 Good or poor project planning: starting on the last day? (a) poor planning (b) good planning
- 15.🔍 Which is the odd one out? (a) keeping spare days (b) guessing how long (c) using a simple timetable (d) setting mini-deadlines
- 16.Which of these is poor project planning? (a) hard part first (b) checking progress weekly (c) keeping spare days (d) starting on the last day
- 17.True or false: “no task list” is good project planning. (a) True (b) False
- 18.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) there is no need (c) for surprises (d) to start late
- 19.📅 Your eco-club poster is due in 12 days. Research takes 2 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
- 20.📅 Your school play is due in 12 days. Research takes 3 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
- 21.🔍 Which is the odd one out? (a) ignoring the timetable (b) no task list (c) doing only easy bits (d) hard part first
- 22.✂️ Your team must make 18 paper flowers in 2 days, the same number each day. How many paper flowers a day?
- 23.✂️ Your team must make 24 paper flowers in 3 days, the same number each day. How many paper flowers a day?
- 24.📅 Your school play is due in 8 days. Research takes 3 days, making it takes 2 days and practice takes 2 days. How many spare days will you have?
- 25.🔍 Which is the odd one out? (a) starting early (b) hard part first (c) one huge deadline (d) checking progress weekly
- 26.True or false: “doing only easy bits” is good project planning. (a) True (b) False
- 27.True or false: “hard part first” is good project planning. (a) True (b) False
- 28.Which of these is good project planning? (a) breaking work into steps (b) starting on the last day (c) no task list (d) one huge deadline
- 29.📅 Your history chart is due in 11 days. Research takes 4 days, making it takes 3 days and practice takes 2 days. How many spare days will you have?
- 30.📅 Good or poor project planning: listing tasks first? (a) good planning (b) poor planning
- 31.🔍 Which is the odd one out? (a) hard part first (b) listing tasks first (c) no task list (d) keeping spare days
- 32.✅ What is a mini-deadline? (a) a late fine (b) a holiday (c) the final due date (d) a date for one step
- 33.Which of these is good project planning? (a) doing only easy bits (b) one huge deadline (c) listing tasks first (d) no task list
- 34.True or false: “one huge deadline” is good project planning. (a) True (b) False
- 35.Which of these is good project planning? (a) one huge deadline (b) ignoring the timetable (c) no task list (d) hard part first
- 36.Which of these is poor project planning? (a) starting early (b) hard part first (c) forgetting the due date (d) keeping spare days
- 37.🔍 Which is the odd one out? (a) using a simple timetable (b) setting mini-deadlines (c) forgetting the due date (d) hard part first
- 38.🔍 Which is the odd one out? (a) no task list (b) one huge deadline (c) no spare time (d) setting mini-deadlines
- 39.True or false: “keeping spare days” is good project planning. (a) False (b) True
- 40.📅 Your art display is due in 10 days. Research takes 2 days, making it takes 3 days and practice takes 3 days. How many spare days will you have?
Answer key
- 6
- good planning
- poor planning
- good planning
- study for the test
- False
- using a simple timetable
- False
- this week
- checking progress weekly
- break it into steps
- 2
- poor planning
- poor planning
- guessing how long
- starting on the last day
- False
- for surprises
- 4
- 5
- hard part first
- 9
- 8
- 1
- one huge deadline
- False
- True
- breaking work into steps
- 2
- good planning
- no task list
- a date for one step
- listing tasks first
- False
- hard part first
- forgetting the due date
- forgetting the due date
- setting mini-deadlines
- True
- 2
Free leadership lessons, practice and worksheets at talentjr.in/leadership-skills-for-students