Leadership Skills Worksheet: Project Time Management

Leadership lesson 4: Managing time on a project · Set 602 · 40 questions
TalentJR

Leader's tip (Steps, dates, spare days): List the steps and give each step a number of days and a mini-deadline. Days needed = add up the steps. Spare days = days you have − days needed. Due in 14 days, tasks 3 + 5 + 2 = 10 days → 4 spare days. Do what is due sooner first, start early and check your progress every week.

NameDateTime takenScore ___ / 40
  1. 1.📅 Good or poor project planning: starting early? (a) good planning (b) poor planning
  2. 2.Which of these is good project planning? (a) forgetting the due date (b) no task list (c) ignoring the timetable (d) using a simple timetable
  3. 3.📅 Good or poor project planning: guessing how long? (a) good planning (b) poor planning
  4. 4.Which of these is good project planning? (a) breaking work into steps (b) one huge deadline (c) no task list (d) starting on the last day
  5. 5.🔍 Which is the odd one out? (a) checking progress weekly (b) starting on the last day (c) no spare time (d) one huge deadline
  6. 6.🔍 Which is the odd one out? (a) no task list (b) using a simple timetable (c) starting on the last day (d) no spare time
  7. 7.Which of these is good project planning? (a) guessing how long (b) ignoring the timetable (c) setting mini-deadlines (d) doing only easy bits
  8. 8.🧩 A big project feels scary. What should you do first? (a) wait for help (b) do it all at once (c) give up (d) break it into steps
  9. 9.⏰ You start at 4:30 PM. Homework takes 30 minutes, then project work takes 35 minutes. When will you finish? (a) 5:05 PM (b) 5:35 PM (c) 5:50 PM (d) 5:00 PM
  10. 10.🔍 Which is the odd one out? (a) checking progress weekly (b) listing tasks first (c) hard part first (d) forgetting the due date
  11. 11.📋 A test is due tomorrow and a poster next week. Which do you do first? (a) neither (b) make the poster (c) study for the test (d) play first
  12. 12.Which of these is poor project planning? (a) setting mini-deadlines (b) using a simple timetable (c) hard part first (d) one huge deadline
  13. 13.🔍 Which is the odd one out? (a) guessing how long (b) starting early (c) keeping spare days (d) hard part first
  14. 14.📅 Good or poor project planning: breaking work into steps? (a) poor planning (b) good planning
  15. 15.🔍 Which is the odd one out? (a) doing only easy bits (b) checking progress weekly (c) using a simple timetable (d) keeping spare days
  16. 16.📅 Good or poor project planning: listing tasks first? (a) poor planning (b) good planning
  17. 17.🔍 Which is the odd one out? (a) hard part first (b) checking progress weekly (c) starting on the last day (d) starting early
  18. 18.🔍 Which is the odd one out? (a) no task list (b) no spare time (c) starting on the last day (d) starting early
  19. 19.📅 Good or poor project planning: no spare time? (a) poor planning (b) good planning
  20. 20.⏳ Why keep a spare day or two before the deadline? (a) to rest only (b) for surprises (c) there is no need (d) to start late
  21. 21.True or false: “checking progress weekly” is good project planning. (a) False (b) True
  22. 22.True or false: “checking progress weekly” is poor project planning. (a) False (b) True
  23. 23.📅 Your eco-club poster is due in 10 days. Research takes 3 days, making it takes 3 days and practice takes 1 days. How many spare days will you have?
  24. 24.Which of these is poor project planning? (a) checking progress weekly (b) doing only easy bits (c) using a simple timetable (d) starting early
  25. 25.📅 Your maths exhibit is due in 11 days. Research takes 1 days, making it takes 5 days and practice takes 1 days. How many spare days will you have?
  26. 26.⏰ You start at 3:00 PM. Homework takes 25 minutes, then project work takes 35 minutes. When will you finish? (a) 3:25 PM (b) 4:00 PM (c) 4:15 PM (d) 3:35 PM
  27. 27.🗓️ Your project is due in three weeks. When should you start? (a) after it is due (b) in the third week (c) the night before (d) this week
  28. 28.Which of these is good project planning? (a) no spare time (b) doing only easy bits (c) starting early (d) no task list
  29. 29.Which of these is poor project planning? (a) setting mini-deadlines (b) breaking work into steps (c) forgetting the due date (d) starting early
  30. 30.🔍 Which is the odd one out? (a) listing tasks first (b) setting mini-deadlines (c) no spare time (d) keeping spare days
  31. 31.🔍 Which is the odd one out? (a) ignoring the timetable (b) no spare time (c) keeping spare days (d) starting on the last day
  32. 32.True or false: “breaking work into steps” is poor project planning. (a) False (b) True
  33. 33.True or false: “doing only easy bits” is poor project planning. (a) True (b) False
  34. 34.True or false: “one huge deadline” is good project planning. (a) False (b) True
  35. 35.True or false: “setting mini-deadlines” is poor project planning. (a) False (b) True
  36. 36.✂️ Your team must make 32 paper bags in 4 days, the same number each day. How many paper bags a day?
  37. 37.✂️ Your team must make 18 thank-you cards in 6 days, the same number each day. How many thank-you cards a day?
  38. 38.⏰ You start at 3:15 PM. Homework takes 40 minutes, then project work takes 20 minutes. When will you finish? (a) 4:15 PM (b) 3:35 PM (c) 4:30 PM (d) 3:55 PM
  39. 39.📅 Your class magazine is due in 11 days. Research takes 2 days, making it takes 4 days and practice takes 1 days. How many spare days will you have?
  40. 40.Which of these is poor project planning? (a) listing tasks first (b) no task list (c) breaking work into steps (d) using a simple timetable

Answer key

  1. good planning
  2. using a simple timetable
  3. poor planning
  4. breaking work into steps
  5. checking progress weekly
  6. using a simple timetable
  7. setting mini-deadlines
  8. break it into steps
  9. 5:35 PM
  10. forgetting the due date
  11. study for the test
  12. one huge deadline
  13. guessing how long
  14. good planning
  15. doing only easy bits
  16. good planning
  17. starting on the last day
  18. starting early
  19. poor planning
  20. for surprises
  21. True
  22. False
  23. 3
  24. doing only easy bits
  25. 4
  26. 4:00 PM
  27. this week
  28. starting early
  29. forgetting the due date
  30. no spare time
  31. keeping spare days
  32. False
  33. True
  34. False
  35. False
  36. 8
  37. 3
  38. 4:15 PM
  39. 4
  40. no task list